Mobil Sta MacA-CS 890605 DALLAS COUNTY
PUBLIC WORKS
June 5, 1989 /
Mr. Mostafa Setayesh
The Dimension Group, Inc.
3455 Highland Road, Suite 100
Dallas, Texas 75228 ~. . /~___
Re: Belt Line Road Projects 490-402 and 403 ......
(MacArthur Boulevard to I.H. 35E)
Dear Mr. Setayesh:
In response to your Memorandum of May 30, 1989, detailing our
meeting discussing the proposed construction of the Mobil
Station at the Belt Line Road-MacArthur Boulevard intersection
we offer the following clarifications:
1. Mobil Oil Corporation shall request through the City of
Coppell for the concrete driveway approach to be constructed
concurrent with the roadway improvements. Mobil Oil or the
City of Coppell must fund the cost of this construction.
The cost of the concrete driveway approach based on our
contract unit price is approximately $1800.00.
2. The statement that the approach along Belt Line Road will
not be closed during construction does not address the
comments made relative to construction of the approach. The
concrete approach will be constructed in two phases so that
the approach will not be closed. However, that means the
width will be reduced to approximately 18 feet during the
construction.
3. The increase in radius size was a comment and not a
requirement of Dallas County. The comment was based on the
dimensions shown on our construction plans prepared by Ginn,
Inc. which depicted the subject driveway approach as future
construction by others. It was our understanding that the
future work was based on site plans filed and approved by
the City of Coppell.
We trust you will forward our clarifications to your contact
person at Mobil Oil. Should you have any questions, please
contact me.
Sincerely,
Project Engineer
ABB: lc ~/~/
cc: Russell Doyle, City Engineer, City, of Coppell, P.O. Box
478, Coppell, Texas 75019
Elm Street Dallas, Texas 75202 653-7151