Loading...
WA9302-LR 950914SHIMEK, JACOBS & FINKLEA CONSULTING ENGINEERS Phone: (214) 361-7900 FAX: (214) 361-0204 Subject: Village Parkway Ground Storage Tank No. 2 Memorandum To: Larry Davis ~ ~ From: Gary C. Hendricks, P.E. Date: September 14, 1995 Re: Pier Inspection Report No. 1 August 28, 1995 Larry, We have reviewed the results of Pier Inspection Report No. 1, dated August 28, 1995, prepared by Gee Consultants, Inc. Of particular concern was Pier b-13. This pier was reported to be out of plumb by 4-inches. The total depth of the pier is 40'-2". The contractor submitted shop drawings for these piers stating the drilled pier construction would conform to the contract specifications and the American Concrete Institute (ACI) specification 336.3R. The contract specification for this project and the drilled piers is based on the North Central Texas Council of Governments (NCTCOG) construction and material specifications. The NCTCOG specifications state that the drilled piers shall not be out of plumb by more than 1-1/2" in 10 feet. Extrapolating this requirement to a 40-foot deep pier, sets the plumbness requirement to no more than 6-inches. The ACI specification for plumbness is slightly more strict, allowing for out of plumbness in the amount of 1% of the total pier length. For a 40-foot deep pier, this would equal 0.4-feet, or 4.8-inches. We have discussed these standards with both Gee Consultants and Natgun Corporation. Both Agree that the ACI requirement of 1% of the total pier length shall be the criteria for acceptance for pier plumb tolerance on this project. '[~ EOTECHNICAL E I GEE Consultants, Inc. E I NVIRONMENTAL 2540 Glenda Lane · Suite 108 · Dallas, Texas 75229 · (214) 620-9791 * Fax (214) 620-9794 REPORT OF CONCRETE MIX DESIGN Report Date: October 30, 1995 Date Concrete Placed: September 29, 1995 Standard6"xl2" Client: City Of Coppell Area 28.27 Square Inches Project: 6.0 Million Gallon Water Storage Tank Concrete Report No.: 1 Contractor: Natgun Construction Project No.: 95 - 0196 Concrete Supplier and Plant: RediMix Concrete - 121 Plant Location of Placement: GEE Consultants, Inc. Laboratory Confirmation Cylinders MATERIALS soars/ Batch Wts. INSPECTION DATA Description (lbs./0.075 C.Y) Mix Number: Wall slots Mix #689 Time Sample Batched: 3:20 pm Cement: TXI Type I/II 799 Time Sampled: 3:45 pm Sample Location: GEE Consultants, Inc. Fly Ash: -0-- Truck/Ticket No: N/A Coarse Aggregate: -0- Temperature: Intermediate Aggregate: -0- Ambient Range: 87°F Fine Aggregate: sand 2691 Concrete Range: 86°F Slump Range (inches): 6~" Admixtures: Weather Conditions: Partly Cloudy 1 Monex NW (C494(A)) 24 oz./yd. Time Started: Partly Cloudy 2 Monex Air 30 (C260) 6 oz/yd. Time Completed: N/A 3 Monex M150 (C494(F)) 112 oz./yd. Sample Air Content (%): 4'h % Total Cubic Yards Placed: 0.06 C.Y. Water: 36.9 gal. Required Strength (Lbs./sq.in.): 5,000 Specimen Measured Age Date Total Load Compressive Strength Remarks Number Slump (in.) (Days) Tested (Lbs.) (Lbs,/Sq.ln.) CWT WS2 1 6~" 3 10/02/95 144,700 5,120 Unit weight: 135.2 lbs/cu.~. CWT WS2 2 6~" 3 10/02/95 138,800 4,910 CWT WS2 3 6~" 3 10/06/95 137,340 4,860 CWT WS2 4 6~" 7 10/06/95 160,020 5,660 CWT WS2 5 6~" 28 10/27/95 190,980 6,760 CWT WS2 6 6~" 28 10/27/95 179,820 6,360 Test Methods Utilized Fracture Regular Cylinders Made By: w.l. ASTM C-31,C-39,C-143 (Unless Noted Otherwise) Remarks and/or Distribution: cc: Mr. Larry Davis - City of Coppell Mr. Bob Barbarisi, Jr. - Natgun Corporation Mr. Gary Hendricks - Shimek, Jacobs and Finklea Mr. Gary Herron - RediMix Concrete GEE Consultants, Inc. Reviewed by: All letters and reports are for the exclusive use Of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Comultants, Inc. The use of our name must receive oUr prior written approval. Our letters and reports apply only to the sample tested and/or inspected and are not necessarily indicative of the quantities of apparently identical or similar products.