REPORTED TO:
REPORT OF BUILT-UP ROOFING OBSERVATION
Coppell Tech Center II
1322 Crestside
Coppell, Texas
Bob Moore Construction Co.
1110 N. Watson Road
Arlington, Texas 76011
ATTN: Mr. Ed T. McGuire
General Contractor: J Bob Moore Construction Co.
[Roofing Contractor: ]H.E.C
I Location of Work:
REPORT NO. 96
REPORT DATE: 04-16-01
REG PROJECT NO. 7044
DATE OBSERVED: 03-20-01
TECHNICIAN: C. McEntee
PAGE: 1 of 1
Weather Conditions: Sunny
[Temperature Range: ] 42°
Roof: Line A to D between line 10 and 14.
J Operations Observed: J Application of base flashing with hot asphalt and nails. Also,
install of an expansion joint.
Items Observed: Yes No Items Observed: Yes No
Roofing Materials As Specified: x Roof Sketch Attached: x
Labels Attached: x Debris Removed from Roof Surface: x
Material Sheet Attached: x Crickets Installed this Date: x
Materials Stored as Required: x Deck Inspected this Date: x
Non Conforming Materials Noted: x Photograph's taken this Date: x
Pull Test and/or Adhesion Test Performed: x Attachments: x
J Specified Temperatures J
Asphalt Kettle Temperature:J 500° +/- 25 F JApplication (EVT): J 475° +/- 25 F
Actual Temperatures
Asphalt / Pitch Kettle Temperature: Time Temp. Application (EVT): Time Temp.
AM type, III Asphalt 10:00 am 525° AM type, III Asphalt 10:15 am 495°
PM type, III Asphalt 1:15 pm 520° PM type, III Asphalt 1:30 pm 490°
Mail
Distribution: (1) Bob Moore Construction Co./
Mr. Ed T. McGuire
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
(1) McHale Consulting Engineering/
Mr. Gary McHale
(1) CMC-Commercial Realty/
Mr. Steve Huff
(1) AECC, Inc./Mr. Chad Stevens
Submitted by:
REED ENGINEERING GROUP, INC.
Original Signed By
James F. Phipps, P.E.
BW/cg