REPORT OF BUILT-UP ROOFING OBSERVATION
Coppell Tech Center II
1322 Crestside
Coppell, Texas
REPORTED TO:
Bob Moore Construction Co.
1110 N. Watson Road
Arlington, Texas 76011
ATTN: Mr. Ed T. McGuire
General Contractor: ]Bob Moore Construction Co.
Roofing Contractor: H.E.C
REPORT NO. 98
REPORT DATE: 04-16-01
REG PROJECT NO. 7044
DATE OBSERVED: 03-23-01
TECHNICIAN: C. McEntee
PAGE: 1 of 1
Weather Conditions: I Sunny
Temperature Range: 45°/70°
J Location of Work: J Roof: Lines B.5 to D, between 10 to 14 and A to B.8 between
1 and 10.
J Operations Observed: J Application of gravel and flood coat of hot asphalt.
Items Observed: Yes No Items Observed: Yes No
Roofing Materials As Specified: x Roof Sketch Attached: x
Labels Attached: x Debris Removed from Roof Surface: x
Material Sheet Attached: x Crickets Installed this Date: x
Materials Stored as Required: x Deck Inspected this Date: x
Non Conforming Materials Noted: x Photograph's taken this Date: x
Pull Test and/or Adhesion Test Performed: x Attachments: x
I Specified Temperatures
Asphalt Kettle Temperature:J 500° +/- 25 F JApplication (EVT): J 475° +/- 25 F
Actual Temperatures
Asphalt / Pitch Kettle Temperature: J Time Temp. Application (EVT): Time Temp.
AM type, III Asphalt J10:23 am 520° AM type, III 10:44 am 440°
PM type, III AsphaltJ 2:10 pm 500° PM type, III 2:20 pm 475°
Comments: Holes drilled through the scupper openings were repaired.
Mail
Distribution: (1)
(1)
(1)
(1)
(1)
(1)
Bob Moore Construction Co./
Mr. Ed T. McGuire
City of Coppell/Mr. Larry Davis
City of Coppell/Mr. Lee Stone
McHale Consulting Engineering/
Mr. Gary McHale
CMC-Commercial Realty/
Mr. Steve Huff
AECC, Inc./Mr. Chad Stevens
Submitted by:
REED ENGINEERING GROUP, INC.
Original Signed By
James F. Phipps, P.E.
BW/cg