WA9302-CS 950919SHIMEK, JACOBS FINKLEA
CONSTRUCTION REPORT ProiectNo. 94155
Date: 9-19-95
Prepared Is This A
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 58
Number
Superintendent: Roy Twombley Men Working: 8 Hours: 9:00 AM to 9:47 AM
Weather Conditions: Overcast and slight rain.
Site Conditions: Well Maintained, Good Condition and Muddy
WORK DESCRIPTION
1. Sixty one piers have been completed.
2. The pier that has to be removed still contains concrete. The pier will be drilled to a 50 foot depth.
3. Due to wet conditions on the pad, concrete placement is doubtful.
4. One pier shaft was drilled and encased.
5. One drilling rig was in service, and another was being repaired.
6. One crane and one Backhoe were in use.