WA9302-CS 960327 (2)SHIMEK, JACOBS & FINKLEA
CONSTRUCTION REPORT Project No. 94155
Date: 3/27/96
Prepared Is This A
By: Matt Hickey i~ ~ Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2
Construction
Contractor: NATGUN Time Allotted: 300 Used: 248
Number
Superintendent: Jim Fisher Men Working: 7 Hours: 2:30 PM tO 3:00 PM
Weather Conditions: Cloudy and Cool
Site Conditions: The site was dry and well maintained.
WORK DESCRIPTION
1. Forty nine prestressing wraps have been completed. Jim Fisher indicated that the prestress wrapping should be
completed around April 3, 1996.
2. The shotcrete cove was placed on March 22, 1996.
3. All of the scaffolding has been removed from the tank and the job site.
4. Ted Dutt and Larry Davis showed concerns about restoring irrigation to the front of the pump station. The City
indicated that it would supply Jim Fisher the irrigation piping plan so that he may begin restoring the sprinkler
system.
5. Joe Mazi, Natgun's Quality Control Inspector, visited the job site on March 22, 1996.
cc: Mr. Bob Barbarisi, Jr.