Northlake WE P10B-LR 940908 DAILY COHHTRUL"TIOH RBPORT
PRO~BCT: Northlake Woodlands $10, Phase B LOC~TION: Coppell
JOB $: 94-1104 D~TE: 09-08-94 D~Y: Thursday TIME: 6:30am-2:30pm
CLIBNT: Fircon Venture LTD CONTRACTOR: Site Concrete
c/o Tipton Engineering
&CTIVZTIBH:
wnTHn: overcast & Humid LOW TFdfP: 68F HIGH TEMP: 87F
Travelled to job site, as requested, to make four (4)
concrete test cylinders and to pick up thirty-two (32)
test cylinders made on 09-07-94. Returned to office.
SET $19
LO~TXON: Falcon Ct
BLUMP: 5.5" ~XR: 4.9% TEMP: AT 74/CT 76 TXME: 8:00am
Patrick Corbett
Technician