Northlake WE P12-CS 890727July 27, 1989
MEMORANDUM
TO: Russell R. Doyle, P.E., City Engineer
FRO!{: Larry Davis, Construction Inspector
I) Approved Engineering Plans Required - Stamped & Signed by the City
Engineer
2) Approved Site Plan for Excavation
3) Pre-Construction Conference With The Engineering Construction
Inspector Required Prior to Start of Construction
Excavation Permit Required
5)Utility Construction Permit Required
Paving Construction Permit Required
7) Additional Permitting May Be Required - Other City Departments,
State, County and Federal
8) Early Rough Grading Must Be Approved Separately
LD/!sg
PERM.N,~