121 BP Phase 1-LR000106 GEOTECHNICAL AND ENV~RONI'4ENTAL CONSULTANTS REPORT OF BUILT-UP ROOFING OBSERVATION 121 Business Park - Buildings B-D 601,651,701 and 751 Canyon Drive Coppell, Texas REPORTED TO: The Industrial Group REPORT NO. 139 P.O. Box 802047 REPORT DATE: 01-06-00 Dallas, Texas 75380-2047 REG PROJECT NO. 5607 ATTN: Mr. John Walsh DATE OBSERVED: 12-22-99 TECHNICIAN: T. Belew PAGE: ! of ! iGeneral Contractor: Iwestcliffe, Inc. !Weather Conditions: I Clear Roofing Contractor: M & G Roofing Temperature Range: I 30~/55:' !Location of Work: I Building 3, line A to F between 1 and 9. iOperations Observed: Application of a flood coat of hot asphalt covered with gravel ballast. Items Observed: Yes No Items Observed: Yes No Roofing Materials As Specified: x Roof Sketch Attached: x Labels Attached: x Debris Removed from Roof Surface: x Material Sheet Attached: x Crickets Installed this Date: x Materials Stored as Required: x Deck Inspected this Date: x Non Conforming Materials Noted: . x Photograph's taken this Date: x Pull Test and/or Adhesion Test Performed: I x Attachments: I x I Specified Temperatures I Asphalt Kettle Temperature:I 500= i+/- 25 F IApplication (EVT):I450, i +/- 25 r: I Actual Temperatures Asphalt / Pitch Kettle Temperature: / Time I Temp. IApplication (EVT): Time Temp. Asphaltl 1:45 I510:I Asphalt 1:50 475: Distribution: (1) The Industrial Group/ Submitted by: Mr. John Walsh (1) Gromatzky Dupree & Associates/ REED ENGINEERING GROUP, INC. Mr. Bennett Foster (1) Westcliffe, Inc./Mr. Charlie Johnson Original Signed By (1) The Industrial Group/ Mr. Mac McClure Keith E. Atkins (1) Campbell Associates/ BW/mm Mr. Randy Pliler (1) Bear Creek Construction/ Mr. Brian Holdgate (1) Mr. Hank Metzger ; ".zZ.z _:-~-T Z::. · ~.' -= -'£- · Z..:-__-'-£ -. "~Z_;-= · -E_ ''.~ -~ "~:~ ::-~", ~ ...... . ~z, Z£'.z~ 3~:~ 3:::'-~- GEOTECHNICAL AND G F=J r-'l I I p ENV ~ON!flENTAL CONSULTANTS REPORT Of BUILT-UP ROOFING OBSERVATION 121 Business Park - Buildings B-D 601,651,701 and 751 Canyon Drive Coppell, Texas REPORTED TO: The Industrial Group REPORT NO. 140 P.O. Box 802047 REPORT DATE: 01-06-00 Dallas, Texas 75380-2047 REG PROJECT NO. 5607 ATTN: Mr. John Welsh DATE OBSERVED: 12-23-99 TECHNICIAN: Clear PAGE: 1 of 1 jGeneral Contractor: JWestcliffe, Inc. JWeather Conditions: IClear JRoofing Contractor:lM & G Roofing ITemperature Range: J 33':/60c j Location of Work: J Building 3, roof line A to F between 1 and 19. !Operations Observed: jApplication of a flood coat of hot asphalt covered with gravel ballast. Items Observed: Yes No Items Observed: Yes No Roofing Materials As Specified: x Roof Sketch Attached: x Labels Attached: x Debris Removed from Roof Surface: x Material Sheet Attached: , x Crickets Installed this Date: x Materials Stored as Required: x Deck Inspected this Date: x Non Conforming Materials Noted: i x Photograph's taken this Date: x Pull Test and/or Adhesion Test Performed: I x Attachments: x J Specified Temperatures J Asphalt Kettle Temperature:J 500: j +/- 25 f IApplication (EVT):I 450=. I +/- 25 F Actual Temperatures Asphalt/Pitch Kettle Temperature: J Time ! Temp. JApplication (EVT): Time J Temp. typellI, AsphaltJ~11:00A J 520°'l typellI. Asphalt 11:15A J 475~ Distribution: (1 The Industrial Group/ Submitted by: Mr. John Walsh (1 Gromatzky Dupree & Associates/ REED ENGINEERING GROUP, INC. Mr. Bennett Foster (1 Westcliffe, Inc./Mr. Charlie Johnson Original Signed By (1 The Industrial Group/ Mr. Mac McClure Keith E. Atkins (1) Campbell Associates/ BW/mm Mr. Randy Pliler (1) Bear Creek Construction/ Mr. Brian Holdgate (1) Mr. Hank Metzger