121 BP Phase 1-LR 991123 CONTRA CT INSPECTION SER VICE, Inc.
4305 Glenwood Ct. Granbury, TX 76049 (817) 246-8096 FAX (817) 246-5889
REPORT OF
STRUCTURAL STEEL ERECTION INSPECTION
Project: 121 Business Park Report No: 15711-9
Coppell, Texas Attention: Keith Atkins
Client: Reed Engineering Group Date of Service: 11-23-99
2424 Stutz, Suite 400
Dallas, TX 75235 Page 1 of 1
I . - --- -*--*- '*::'*:'*.::-**-::.-**:*:**::*-:" ':' :::*:* '*:* **:-::.- ::,:,: :-:,:,.::,:,.,:~.: ":'*:, ":'**:::-" '," ':*.':: ':':"-. :- ........-.':'... ::-:-.--":'--.'" '"' ~
REPORT OF INSPECTIO-'q
l)rawings utilized: Structural Prints
Locations/item inspected: As noted.
Discrepancies/comments:
Reinspection of report dated 11-17-99. Building ~2
Item 2 - Joist girder to column - All connections now welded and comply.
Item 5 - Joist bridging - Bridging now installed.
Item 6 - Deck edge angle splices - Connections now comply.
Initial inspection, Building #2
1.) Metal roof deck puddle welds were found to be in compliance.
2.) Side lap screws have been installed.
Initial inspection, Building #3
* 1.) Anchor bolts - Could not inspect due to water in leave outs.
*2.) Joist girder to panel pockets - Additional welding needed due to weld size.
3.) Joist girder to column cap - Welds and bearing comply.
4.) Joist to panel - Welds and bearing comply.
5.) Joist to joist girder - Welds and bearing comply.
*6.) Perimeter angle not installed as of this visit.
*Open Items
Larry G. Peel, CWI #89120661 /~'~ ~' V~ 7 d--/¢ ~,~ff ~~')
Technician Contract Inspection Service
This report is for the exclusive use of our client and shall not be modified or reproduced without ~n'ritten approval from said client