Oakbend Addn-CS 910520May 20, 1991
Mr. Larry Davis
Construction Inspector
City of Coppell
P.O. Box 478
Coppell, Texas 75019
Reference:
Oakbend Addition
Final City Acceptance
Dear Larry:
Per your request, following is a summary of the efforts
to complete construction on the above referenced project.
We have reviewed your checklists and have made the following
determinations:
Checklist of April 23, 1991:
with following exceptions:
Ail items have been addressed
1)
36" RCP in Beal Court has had a headwall poured per our
field discussions.
2)
Drop inlet behind Lot 43 on Oakbend Drive - Capacity of
inlet = 9 CFS, Discharge = 8.3 CFS. In addition,
emergency overflow directly into creek is available
without crossing any lots.
Checklist of April 26, 1991: Ail items have been addressed.
State Road Punchlist (No date): Ail items have been
addressed with the following exceptions:
1)
Traffic signs - The Engineer is preparing a disclaimer
letter for the change of signs, the Engineering
Department approved the sign plan. as installed and thus
will have to accept any responsibility for any changes.
Upon completion of this letter, signs wlll be changed.
2)
Power pole at Thweatt intersection - TU Electric has
committed to move this pole when it adjusts the power
line along Thweatt Road. This should occur in the next
two to three weeks.
3)
Water valve at Thweatt will be painted red and cleaned
by the utility contractor.
4)
Guardrails to be installed per plans by 5/22/91
1660 S. Stemmons Frwy., Suite 150 / hewisville, Texas 75067 / 214-221-5556
Mr. Larry Davis
Page 2/2
Punchlist of May 17, 1991: Ail items have been addressed
with the following exceptions:
1)
Ail streets have been cleaned. Centex is aware that it
is our responsibility to keep the s[reets clean during
home construction. It has been difficult recently due
to the heavy rains that have plagued the area.
2)
Gravel witl be placed along the State Road asphalt
transition to prevent erosion.
3)
Ditch along State Road has been regraded and rip-rap
added to prevent erosion. In addition, hydromulch will
be added to stabilize the channel banks. The above
mentioned measures were not a part of the original
plans and thus, should not hold up City acceptance.
4) Box culvert will be cleaned 5/21/91.
5) Guardrails will be placed by 5/22/91.
6) Concrete rip-rap will be backfilled by 5/21/91.
7)
Erosion protection will be placed at outfall of box
culvert by 5/21/91.
8)
Please note that the channel adjacent to lot 52 will
not be accepted for City maintenance. It is our
intention to regrade and stabilize this channel but
this should not be required for City acceptance of the
subdivision.
9)
Signs on State Road will be resolved as discussed
above.
We anticipate receiving final City acceptance on the project
by May 23, 1991. Please contact me concerning any questions
on the above information.
Sincerely,
CENTEX REAL ESTATE CORPORATION
Derek E. Earle, P.E.
Land Development Project Manager
DEE/s