Oakbend Addn-CS 910520May 20, 1991 Mr. Larry Davis Construction Inspector City of Coppell P.O. Box 478 Coppell, Texas 75019 Reference: Oakbend Addition Final City Acceptance Dear Larry: Per your request, following is a summary of the efforts to complete construction on the above referenced project. We have reviewed your checklists and have made the following determinations: Checklist of April 23, 1991: with following exceptions: Ail items have been addressed 1) 36" RCP in Beal Court has had a headwall poured per our field discussions. 2) Drop inlet behind Lot 43 on Oakbend Drive - Capacity of inlet = 9 CFS, Discharge = 8.3 CFS. In addition, emergency overflow directly into creek is available without crossing any lots. Checklist of April 26, 1991: Ail items have been addressed. State Road Punchlist (No date): Ail items have been addressed with the following exceptions: 1) Traffic signs - The Engineer is preparing a disclaimer letter for the change of signs, the Engineering Department approved the sign plan. as installed and thus will have to accept any responsibility for any changes. Upon completion of this letter, signs wlll be changed. 2) Power pole at Thweatt intersection - TU Electric has committed to move this pole when it adjusts the power line along Thweatt Road. This should occur in the next two to three weeks. 3) Water valve at Thweatt will be painted red and cleaned by the utility contractor. 4) Guardrails to be installed per plans by 5/22/91 1660 S. Stemmons Frwy., Suite 150 / hewisville, Texas 75067 / 214-221-5556 Mr. Larry Davis Page 2/2 Punchlist of May 17, 1991: Ail items have been addressed with the following exceptions: 1) Ail streets have been cleaned. Centex is aware that it is our responsibility to keep the s[reets clean during home construction. It has been difficult recently due to the heavy rains that have plagued the area. 2) Gravel witl be placed along the State Road asphalt transition to prevent erosion. 3) Ditch along State Road has been regraded and rip-rap added to prevent erosion. In addition, hydromulch will be added to stabilize the channel banks. The above mentioned measures were not a part of the original plans and thus, should not hold up City acceptance. 4) Box culvert will be cleaned 5/21/91. 5) Guardrails will be placed by 5/22/91. 6) Concrete rip-rap will be backfilled by 5/21/91. 7) Erosion protection will be placed at outfall of box culvert by 5/21/91. 8) Please note that the channel adjacent to lot 52 will not be accepted for City maintenance. It is our intention to regrade and stabilize this channel but this should not be required for City acceptance of the subdivision. 9) Signs on State Road will be resolved as discussed above. We anticipate receiving final City acceptance on the project by May 23, 1991. Please contact me concerning any questions on the above information. Sincerely, CENTEX REAL ESTATE CORPORATION Derek E. Earle, P.E. Land Development Project Manager DEE/s