Oakbend Addn-CS 900815August 15, 1990 /
/
Mr. Steve Goram /
Director of Public Works
City of Coppell /
732 Deforest Road ~
C ooel3~ ~ .... 7~9
.........
RE:k...9~kbend Addition_9/
trt-i-lity Cons~ction
Dear Mr. Goram:
This letter will serve to inform you of the current status of the
Oakbend Addition in Coppell and to clarify the direction and
steps which we are taking in order to expedite the construction
of the project. As you are aware, the City Council passed the
final zoning ordinance for the project on August 14 while the
final plat was passed at a previous council meeting. No other
Council or P&Z action is necessary for the project to proceed.
Drainage plans for the project are being revised due to revisions
requested by the City Council and will be complete in two to
three weeks. In the meantime, however, I requested that the City
Staff approve the Water and Sanitary Sewer plans as originally
presented in order to expedite the construction of the project.
This has been done and a preconstruction meeting has been set for
utilities on Friday, August 17. This meeting is intended to
allow Water and Sanitary Sewer construction to proceed in a
timely manner. Revisions to these plans due to extension of two
cul-de-sacs at the west side of the property (mostly minor
changes) are currently underway and are expected to be complete
in a maximum of two weeks. These plans will be submitted to the
City for review as soon as they are complete and issued to the
Contractor upon approval.
I am aware that Council requested Staff to be very attentive to
the Drainage plans for the project to avoid future problems. We
are in agreement with the importance of proper drainage for the
area and are in the process of revising the drainage plans to
resolve previous comments by the City concerning the drainage
issue at the common property line with the Cistercian tract. The
only other outstanding issue concerning drainage is at the west
side of the property in the area formerly indicated as a park
dedication. All drainage in this area will be carried in an
underground system with the exception of the drainage channel at
the northern edge of this area. All stormwater will be carried
1660 S. Stemmons Frwy., Suite 150 / Lewisville, Texas 75067 / 214-221-5556
Mr. Steve Goram
Page 2 of 2
in properly engineered systems to avoid any problems for the
homeowners or City. We feel that all areas of concern of the
City are being properly addressed and that a satisfactory system
will be provided. It is anticipated that plans for drainage will
be submitted to the City in approximately two weeks for review.
At the time the plans are approved, they will be issued to the
utility contractor for construction.
The only other outstanding issue related to Oakbend is the
construction of State Road along the west side of the property as
requested by Council. Due to the complexity of the preparation
of these plans, it is anticipated that full plans for the street
will be submitted in about three to four weeks. The plans for
State Road have no impact on the Oakbend Addition and will be
totally separate. We realize that completion of State Road is a
condition for acceptance of the subdivision by the City. The
only potential problem is in the dedication of 30' of ROW by Lacy
which is necessary for construction of the street as requested by
Council. We will keep you informed of the progress on this
issue.
Centex Real Estate Corporation will accept responsibility for
changes to the utility plans and construction as a result of
review by the City of the engineering plans remaining to be
submitted. At this time, ! anticipate no further problems in
completion of the project and appreciate your and the City
Staff's cooperation in expediting construction. I will continue
to personally coordinate the construction to ensure that all
parties are informed of the latest status of the plans and
construction.
Please call me if I may be of further assistance.
Sincerely,
CENTEX REAL ESTATE CORPORATION
Derek E. Earle, P.E.
Land Development Project Manager
DEE/s
CC:
Mr. Larry Davis
Ms. Shohre Daneshmand, P.E.
Mr. Mike Daniel, P.E.