Loading...
Parkview Addition-CS 870915 (3)Project: Contractor: Owner: Developer: Da te: Time: Place: PIERC; -LUNSFORD ASSOI_;IATES, INC. CONSULTING ENGINEERS Ref. 515356.10 CF PC9177 Parkview Addition American Development & Contractor, Inc. Coppell Municipal Utility District No. i (CMUD) Warren Clark & Assoc. September 15, 1987 1:30 City Hall - Coppell, Texas Discussion: A Preconstruc tion Parkview Addi tion participants: Conference Subdivision was held for the with the following Jeff Hawkins Brad Williams Dale Clark Richard Dotter St·yen Morton Rick Ivy Jack Mulanax Samuel K. Parrent Kerry Kochiss Mike Dural George L. Dudley Pierce-Luns ford Assoc. Pierce-Luns ford Assoc. Warren Clark & Assoc. Warren Clark & Assoc. City of Coppell American Dev. & Contr. American Dev. & Contr. Parrent Eng. & Const. L. H. Lacy Co. Dural & Associates Roberts & Dowdey Assoc. The following items were discussed: CMUD Engineer CMUD Proj. Observer Devel ope r De ve 1 ope r City Inspector Utility Contractor Utility Contractor Retaining Wall Contr. Paving Contractor CMUD Testing Lab Design Engineer The earthwork and site grading contractor, R. L. Merrill, has moved on site and should finish putting streets, alleys and lots to grade by end of next week. Notice to Proceed should be issued to American within one week to begin placement of 4" sanitarky sewer services along Parkway Boulevard only. Placement of other utilities can proceed as soon as on-site excavation is complete, at which time American will move two crews on-site. Work Schedule will be 10 hour days, 5 days per week. Roberts & Dowdey will coordinate construction staking with American including scheduling crews for staking and determining offset distances for utilities. 4" sanitary sewer services will be staked at center of lot and water services placed 10' upstream from sanitary services in relation to sewer main flow. Contractor asked if wet bore will be allowed in lieu of dry bore required by City of Coppell subdivision ordinance and contract specifications. Steve Morton will allow wet bore as long as Contractor uses subcontractor approved by City to do boring, grouts encasement pipe sufficiently and cleans up during and after boring operations. CMUD has no problem with wet bore as long as unit price for this bid item is decreased accordingly. 1 of 4 3109 CARLISLE, SUITE 206 DALLAS, TEXAS 75204 (214) 871-2126 3901 W. PIONEER PARKWAY, SUITE 100 ARLINGTON, TEXAS 76013 (817) 461-5868 Metro The riprap and retaining wall detail at outfall of the 54" storm sewer has been modified as shown on Plate No. 9, 10, and 12 of the construction plans. The quantities and amounts for bid items 1, 6 and 8 of the Drainage Facilities part of the Bid Proposal will be adjusted accordingly by change order. Contractor was warned to keep 3/4" water services minimum 3' below top/curb elevation and also keep plenty of cover behind curb to avoid conflict with soil stabilization and paving operations. 95% soil compaction required under existin9 and proposed streets and 90% outside paving at maximum + 3%, - 2% deviation from optimum moisture content. Contractor will use Hydromatic pneumatic or vibratory compactor. Dural will take frequent soil compaction tests on various lifts for trench backfill at start of project and adjust frequency according to results. Contractor will keep backfill and compaction of trenches up close behind placement of utilities. Contractor will coordinate with Brad Williams and Duval as to when backfill will be ready for compaction tests. Contractor pays for any ret.sting of densities which do not pass original compaction and/or moisture test. Utility contractor is required to return subgrade to within 0.1' of what it is when they move on site. Excess spoil can be leveled off on adjacent lots as long as adequate drainage is maintained. e Adjustment rings will be placed on all manholes - minimum 6", maximum 12". 10. Water needed for hydrostatic testing of water system is to be obtained through service line from existing fire hydrants, 2" copper line from existin9 to new water line, or by water truck. Feeder line must have in-line double check valve to prevent contamination. 11. A weekly meeting will be held each Wednesday on site at 9:00 a.m. for all participants to coordinate scheduling, discuss any problems and check status of project· 12. Contractor will abide by OSHA's specifications concerning excavation and shoring of trenches more than five feet in depth. Contractor generally maintains vertical walls to 5' above bottom of excavation and then slopes back according to OSHA specifications for type of soil encountered. Contractor indicated shoring will be utilized in some locations such as water line borings, connection into existing 10" sanitary sewer line and 4" sewer service connections into existing main along Parkway Blvd. 2 of 4 13. Contractor was warned that there is an existing sprinkler system in the R.O.W. on south side of Parkway Boulevard. 14. A final inspection of utilities will be made by CMUD, City of Coppell, Developer and Contractor representatives to insure mutual acceptance by all parties. All comments or inquiries concerning construction practice or workmanship during construction should be directed through CMUD project observer. 15. Plans stamped by the City of Coppell as "Approved for Construction" must be received before contractor moves'on the job site. One set will be given to the contractor and two to Pierce-Lunsford. 16. Pay estimates will be submitted on forms provided by Coppell M.U.D. The cut off date for work completed will be the 15th of the month. Quantities completed will be agreed upon by the M.U.D. inspector and construction foreman, who are to sign the form and have it to Pierce-Lunsford no later than the 20th. Payment to the contractor will be recommended to Coppell M.U.D. Board of Directors at the following month's meeting, usually the second Tuesday of the month. 17. Curb inlets will be cast-in-place. Contractor would like to place inlets after streets are paved. Paving contractor felt this would not be a problem as long as adequate drainage is maintained. Manholes will be pre-cast and manufactured by Sherman Concrete Products as approved by City of Coppell. 18. Street cut permits must be obtained by utility contractor for each location where it is necessary to remove existing street. Appropriate barricades must be maintained. 19. Parrent Engineering and Construction will construct retaining wall on south side of project. He will schedule his work in coordination with utility contractor for placement of storm sewer adjacent to retaining wall. 20. It was agreed Contractor can proceed with extra work on a verbal approval if contractor was explicitly told the scope of work to be done and agreement was reached on the cost and time to complete work. Verbal authorizations will be followed up by written change order. 21. 8" water line is to be PVC SDR 14 with 42" minimum burial and sand embedment. T.P.& L. was contacted ~hd' 'confirmed that electric lines will be placed 36"-39" below T/curb. American should construct waterline and other utilities to avoid conflict with other proposed improvements. 3 of 4 22. City of Coppel 1 currently has right to require T.V. inspection of sanitary sewer lines after.placement if there is any reason to question the quality or workmanship of any line or services. A unit price was included for this work in the contract in case it is deemed necessary. 23. Contractor must furnish as-built plans following construction with all changes indicated and showing distance ties from fixed objects (manholes, valves, firs hydrants) to all water and sanitary sewer services. American will place a locater in backfill of each service line before paving contractor moves on site in order to relocate services. 24. A walk-through of project will be made with CMUD and paving and utility contractors to verify condition of utilities before paver moves on site. Paver is expected to return utilities to same condition before utility contractor moves on site to finish project. Telephone numbers of all parties receiving a copy of the minutes are as follows: CC: Pierce-Lunsfo rd Warren Clark & Assoc. City of Coppell American Development Parrent Engineering L. H. Lacy Co. Duval & Associates Roberts and Dowdey 214/871-2126 214/931-8971 214/462-8495 214/263-8884 214/384-7903 214/357-0146 214/248-0587 214/931-0694 4of 4