ST9704-CN 990608 CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Denton Tap Road Project # ST 94=01
CONTRACTOR: Rebcon Inc.
OWNER: City of Coppell
CHANGE ORDER NO.: 3 (Addition of 2~ High School Access) DATE: 6/8/99
Item Description {~3antity Ullit Unit Price Total
.ADD:
I 1 Uncl Street Excavation 1644.0 CY 7.00 11,508.00-
2 Controlled Density Fill 112.0 CY 6.00 672.00
4 ROW Prep 5.6 STA 3,100.00 17,360.00
16 6" Lime Stub Subgrade 3250.0 SY 1.50 4,875.00
17 Lime 49. 0 TON 92.019 4, 508. O0
, ~..,.18 8" 300011 Reinf. Conc St Pvmt 156.0 SY 30.00 4,680. O0,,-
w/curb
20 4" 3000# Conc Sidewalk 530.0 SY 21.00 11,130.00
28 Refi 4" White Pvmt Markers 40. 0 EA 5. 80 232. O0
32 3" Sch 40 PVC Conduit 90.0 LF 4.00 360.00-
55 Adjust Exist. SS Manhole 2.0 F_,.4 500. O0 1,000. O0---
New
ROW Prep 3.5 STA 9,600.00 33,600.00
~ i,~,,k~aw/Rem Conc Curb&Gutter 298.0 LF. 7.50 2,235.00"
Butt Joint 298. 0 LF 4. O0 1,192.00-
6" 300011Reinf. Conc St. 2832.0 SY 29.00 82,128.00
Pvmt w/curb
Road Humps 2.0 ti4 9, 500. O0 19, 000. O0~-
Pavestone Retaining Wall 680. 0 LF 53. O0 36, 040. 00~
Total Revision to Contract Amount $230,520. O0
Previous contract amount $3,677,038.15
Net increase in contract amount $ 230,520.00
Revised contract amount $3,907,558.15
Net increase in contract time of completion '0-
Revised Contract time of completion 290 Working Days
Special Conditions:
1. Prices exclude: utility adjustments or relocations; light pole relocation; grass; Irrigation; relocate trees.
2. The Pavestone Wall Unit Price is based on constructing a flex base footing in lieu of a concrete footing.
Denton Tap Road Project ST 94-01
Change Order #3 6/8/99
Page 2
The contractor hereby accepts this Contract adjustment as a final and complete
adjustment in full accord and satisfaction of all past and future liability originating
under any clause in the Contract by mason of this revision to the Contract
Recornmendediby/City Engineer Date
.