Park West CC(6)-LR 970902 CONTRACT INSPECTION SERVICE
4305 Glenwood Ct. Granbury, TX 76049 (817) 246-8096 FAX (817) 246-5889
REPORT OF
STRUCTURAL STEEL ERECTION INSPECTION
Project: Park West Center II Report No: 7638-7
Coppell, TX Attention: Keith Atkins
Client: Reed Engineering Group Date of Service 09-02-97
2424 Stutz, Suite 400
Dallas, TX 75235 Page 1 of 1
REPORT OF INSPECTION
Drawings utilized: Structural Prints/AISC/AWS D1.1-96
Locations/item inspected: #1 Grid line 15 to 8, column line J to F
#2 Grid line 15 to 23, column line B to F
Discrepancies/comments:
#1 A) Joist to girder welds- Comply.
B) Joist to joist girder bearing- Complies.
C) Joist girder to column welds and bearing- Comply.
*D) Various continuity angles missing.
E) Anchor bolts- Comply.
*#2 A) Joist to panel welds are missing or are non-compliant on the
vertical welds.
B) Joist to panel bearing- Comply.
C) Joist to joist girder- Welds and bearing comply.
D) Joist girder to column welds and bearing comply.
E) Anchor bolts- Comply.
* Open items
Technician ~ract Inspection S~rvice
This report is for the exclusive use of our clien= and shall not be modified or reproduced without written &pproval from said client