Park West CC(6)-LR 970828 CONTRACT INSPECTION SERVICE
4305 ~lenwood Ct. Granbury, TX 76049 (817) 246-8096 FAX (817) 246-5889
REPORT OF
STRUCTURAL STEEL ERECTION INSPECTION
Project: Park West Center II Report No: 7626-7
Coppell, TX Attention: Keith Atkins
Client: Reed Engineering Group Date of Service 08-28-97
2424 Stutz, Suite 400
Dallas, TX 75235 Page 1 of 1
REPORT OF INSPECTION
Drawings utilized: Structural Prints/AISC/AWS D1.1-96
Locations/item inspected: Grid line 15-23, column line J.6 to J deck inspection'
Grid line 14 to 15, column line J to F weld inspection
Discrepancies/comments:
1) Deck inspection
A) After necessary repairs decking in areas inspected was secure
on 08-28-97.
2) Visual inspection
A) Joist to girder connections- Comply.
B) Joist girder to column cap- Comply.
C) Anchor bolts- Comply.
Note: Bridging not installed.
Tim Glazier ~[~:~ ~-~ ~/'~' '~/
Technician Con~act Inspection Service
This report ~e for t~ exclusive use of our client ~d shall not be ~d~ed or reproduce~ w~t~ut written approval from sa~d client