Park West CC(7)-CS 990408April8,1999
Mr. Michael Martin
City of Coppell
255 Parkway Blvd.
Coppell, TX 75019
Re:
Lakeview Commerce Center
1199 S. Beltline, Coppell, TX
Dear Michael:
This letter serves to document our conversations yesterday and in the past regarding the
turn lane off Beltline and our Certificate of Compliance for the above referenced project.
It is Prentiss Properties' understanding that the City of Coppell will not deny our project
a temporary Certificate of Compliance if the southbound mm lane from Beltline to
Wrangler is incomplete, provided the work is progressing satisfactorily with imminent
completion assured.
We feel reasonably confident that this work will be complete on or by May 1, 1999 in
conjunction With our May 3, 1999 tenant occupancy. However, should the weather or the
relocation of public utilities delay our progress we may not be complete until later in
May. Per my discussion with Larry Davis this morning, we will notify the City in writing
if we are delayed and what our new anticipated completion date will be.
Please call if you have any questions.
Sincerely,
Construction Manager
DHG/ams
Cci
Larry Davis (COC)
Jerry Mays (PPL)
Myles Glynn
Dennis Chovan (HAI)
Lane Tisdale (AAI)
Alex Rakisits (BCI)
PRENTISS PROPERTIES
3860 WEST NORTHWEST HWY., SUITE 400 DALLAS, TEXAS 75220
214 654-0886 Fax: 214 358-7122