ST9604-CS 980223 February 23, 1998 Huitt-Zollars, Inc. 3131 McKinney Avenue, Suite 600 LB 105 Dallas, Texas 75204 RE: Fairway Drive ST 96-04 Dear Sir: The following represents either observations or concerns that the City of Coppell has concerning the proposed design of Fairway Drive and the railroad crossing. Once you have had the opportunity to review these comments, please feel flee to contact me at your earliest convenience so that we can discuss any issues that you may have with the comments. As has been stated throughout this process it is important for the City of Coppell to rapidly move forward with this project and bring it to bid, construction and completion as soon as possible. Page P-1 1. ls there a problem or a reason why we cannot obtain a 0.5% slope on the proposed and future roadway? 2. Show all existing utilities o~ the profile view. 3. There appears to be inaccurate elevations provided in the profile view on the proposed 48" RCP. Remove and dispose of the existing wooden barricade across the Fairway Drive entrance and salvage the existing metal guardrail and transport to the City's storage site at Royal and Bethel Road. 5. The lime stabilized subgrade should be 30 lbs. per/sy minimum. 6. Please comment as to what the pipe on the east side of the railroad crossing that ties into the proposed storm drainage pipe is and will it be installed wi~_ this project. 7. Some of the existing paving in thilf..approach has failed, therefore,i should be removed and replaced with this project. 8. Include Eller Sign Company in the contact list and provide the telephone number, which is (817) 640-4550. 9. Show existing trees on the north side of the railroad tract with a note that the contractor should remove and dispose of same. Page P-2 1. Please provide some information as to what extentq~ailroad ~;ontrols ~m t~ it will be designing and constructing. Does it include all associated signage.,etc? 2. The crossarms should be relocated so that they also block access across the sidewalk. It is anticipated that children in this area i~ will be walking along this route to access a proposed elementary school in the Valley Ranch area. 3. Please give some thought to installing a small curb on either side of the railroad crossing to prevent vehicles from driving around the crossing arms when they are lowered for oncoming '~n~s. If you have a concern with this please contact me so that it can be discusse e i:tesign being performed by Railroad Controls ~ include synchronization with the proposed traffic light? Page P-3 1. Show the proposed roadway to the south to service the apartment complex (see attached plan).T'~. Page S-2 1. As previously discussed, the power source for this project is on the south side of Belt Line Road. The existing overhead electric on the north side is a private line to the Eller Sign Company. Therefore, the controller will need to be relocated to the south side of the roadway. 2. Under your conduit runs note that Conduit #2 and #17 should also be bored. 3. It is my understanding that the traffic light and the intersection will be designed to accommodate the future loops and detectors for the north bound roadway out of the apartment complex. Is there any conduit, etc. that needs to be installed ' ' to insure that that can be accomplished with minimum disruption in the ~mthr~'?nne There are also various other minor conunents throughout the plans that need attention. Specifications: In regard to the proposal, please evaluate the following items to insure the quantities are correct: #9 - Changes due to 30 lbs per/sy #18 - Only see one southbound advisory marker #36 - Should be #14 lead #39 - Quantity appears wrong and it should be #20 conductor #40 - Quantity appears incorrect, should be 4 opticom detectors #51 - Indicate where this is located #52, 53 & 54 - Appear to have inaccurate quantities #68 - Will ~ihange I appreciate the thoroughness of which the preliminary plans were provided to the City. It did make our review much quicker. If you should have any questions please feel flee to contact me at your convenience. If not, I look forward to working with you to finalize the construction plans. Sincerely, Kenneth M. Griffin, P.E. Director of Engineering and Public Works