REPORT OF
STRUCTURAL STEEL ERECTION INSPECTZON
Project: M J Designs Corporate Headquarters Report No: 3044-4
Coppe]l, Texas Attention:
Client: Terracon Date of Service: 05-10-94
12801Stemmons Freeway, Suite 907 Page 1 of 2
Dallas, TX 75234
REPORT OF INSPECTION
Drawings utilized: Contract Documents / AWS D1.1-94 / AZSC
Locations/item inspected: See below.
Discrepancies/Comments:
NORTH MEZZANINE (EAST AND WEST SIDE)
1) Joist to panel pocket welded connections - Welds comply,
except one (1) joist east side welded one (1) side only.
Erector was advised.
2) Joist to beam welded connections - Welds comply.
3) Beam to panel pocket welded connections - Welds comply.
4) Continuous angle 3 1/2 x 3 x 1/4 on A line (West side)
not is contact with all joist. Contractor was advised.
5) Modification of column (East side) - Welds comply according
to revision from Ennis Steel.
6) A325 3/4 inch high strength bolts - Bolts have not been
tensioned at this inspection.
This report is for the exclusive use of our client and shall not be modified or reDrouuced without written al)proval from said client
CONTRACT INSPECTION SERVICE
Project: U. J. Design Corporate Headquarters Report No: 3044-4
Coppe11, Texas Date of Service: 05-10-94
Client: Terracon Page 2 of 2
Discrepancies/comments:
SOUTH MEZZANINE (PARTIAL) WEST SIDE
1) Joist to panel pocket welded connections - Welds comply
after some corrections were made for missed welds.
2) Joist to beam welded connections - Welds comply.
3) Beam to panel pocket welded connections - Welds comply.
4) A325 3/4 inch high strength bolts - Bolts have not been
tensioned at this inspection.
David Wheeler, CAWI #94010524
Contract Inspection Service
This report is for the exclusive use of our client and shall not be t0dified or reproduced ,ith0ut ~ritten apDr0va! fr0a said client