February 1, 1994
Dupey Management Corporation
9015 Sterling Street
Irving, Texas 75063
Attn: Mr. Robert McCann Re: M J Designs Distribution Center
Coppell, Texas
Job No. 17931033
Dear Mr. McCann:
A Terracon Consultants, Inc. representative has continued to perform earthwork observation and
testing sen, ices for the referenced project. This report covers the services performed from
January 17 to January 29, 1994. Sen, ices provided during this period consisted of performing
field density tests on select fill placed in the building area and compacted clay fill placed in the
storm sewer excavation on the south side of the project.
Results of the field density tests performed during this period along with a standard Proctor tests
performed on a sample of select fill. Tests 323-325, 332-340, 346-348, and 364-372 were
performed in the storm sewer excavation. The remaining tests were performed on select fill and
were referenced to the northwest building corner which was given an assumed station of 0 south
and 0 east. Following the precipitation which occurred during the week of January 24, 1994,
any wet and soft select fill soils were removed prior to continuing fill placement.
Offices of The Terracon Companies, Inc. Geofechnical, Environmental and Materials Engineers
¢-' z. cq.q T..cfic- · .Er' .:.ra2c C-3 ?¢raLl.2- S2' ".g~. :::er'.'~' F' .";c ~ ":~. '3'~e e?' ..0".?' ::" ! · 3,-.'"': ~:: S:? · "T';~' E.l,:3m - ;;;c",
ffi S-h~Dma D~a"Cm~ C:; -.;~a I ~',a~ Be ~ ;:'t ¢,'or:" I _:t~" Sat _:~-'e :: :.'
O~[llf E~aI~EE~I~6 SI~CE 1~65
Dupey Management Corporation Terracon
Job No. 17931033
February 1, 1994
If you have any questions regarding this report or it's attachments, please contact this office.
Sincerely,
Project Engineer
ElC:kms
Attachments
Copy To: James, Harwick + Partners, Inc.
Mr. Mark Wolf
Albert Halff & Associates, Inc.
Mr. Dennis Chovan
Bob Moore Construction, Inc.
Mr. Phil Bell
City of Coppell
Mr. Larry Davis
2
FIELD COMPACTION REPORT
JobNo. 17931033
Job Name and Location M.J. DESIGNS DISTRIBUTION CENTER Date 2-2-94
Architect or Engineer JAMES,. HAR~CK + P~, INC.
Contractor _BQB FDORE CONSTRUCTION, INC.
Datum SITE DATUM
Lift No. Maximum In-Place In-Place
Test Date Location or Mtl. Lab Dry Wet Water Dry Percent Conments
No. Elev. Mark Density Density Content Density Comp.
292 1-17 580 - S
30 - E LIFT 2 E 125.0 133.5 9.5 121.9 98
293 1-17 570 - $ LIFT 2 E 125.0 133.0 9.0 122.0 98
100 - E
294 1-17 560 - S
200 - E LIFT 2 E 125.0 134.4 9.3 122.9 98
295 1-17 580 - S
280 - E LIFT 2 E 125.0 132.7 9.0 121.7 97
296 1-18 280 - S LIFT 2 E 125.0 131.3 9.2 120.2 96
320 - E
297 1-18 280 - S
430 - E LIFT 2 E 125.0 131.0 9.0 120.1 96
298 1-18 280 - S
550 - E LIFT 2 E 125.0 133.5 9.5 121.9 98
299 1-18 220 - S
560 - E LIFT 2 E 125.0 132.0 9.2 120.8 97
300 1-18 220 - S
450 - E LIFT 2 E 125.0 131.7 8.8 121.0 97
301 1-18 220 - S
320 - E LIFT 2 E 125.0 132.4 9.4 121.0 97
302 1-18 170 - S
LIFT 2 E 125.0 134.1 9.3 122.6 98
320 - E
303 1-18 170 - S
LIFT 2 E 125.0 131.6 8.5 121.2 97
450 - E
304 1-18 170 - S
550 - E LIFT 2 E 125.0 132.5 9.4 121.1 97
305 1-19 180 - $
30 - E LIFT 2 E 125.0 133.8 9.8 121.8 97
306 1-19 180 - S
420 - E LIFT 2 E 125.0 131.5 9.3 120.3 96
307 1-19 180 - S
550 - E LIFT 2 E 125.0 134.0 9.6 122.2 98
3O8 1-19 80 S
560 - E LIFT 2 E 125.0 133.4 9.3 122.0 98
3O9 1-19 80 - S
440 - E LIFT 2 E 125.0 132.2 9.0 121.2 97
310 1-19 80 - S
LIFT 2 E 125.0 133.0 9.0 122.0 98
32O - E
311 1-19 20 - S
LIFT 2 E 125.0 134.2 9.6 122.4 98
320 - E
312 1-19 20 - S
440 - E LIFT 2 E 125.0 133.5 9.5 121.9 98
313 1-19 20 - S
550 - E LIFT 2 E 125.0 132.6 9.2 121.4 97
314 1-20 580 - S
320 - E LIFT 3 E 125.0 134.2 9.8 122.2 98
315 1-20 580 - S
420 - E LIFT 3 E 125.0 132.6 9.3 121.3 97
316 1-20 580 - S
LIFT 3 E 125.0 133.3 9.5 121.7 97
540 - E
317 1-20 530- $
560 - E LIFT 3 E 125.0 133.0 9.2 121.7 97
318 1-20 530 - S
470 - E LIFT 3 E 125.0 135.4 9.7 123.4 99
NOTES: Densities shown: pounds per cubic foot
Water Content: Percent of dry weight I rerracon
Percent Coovpaction: Based on maximum dry density obtained on
sample indicated by material mark.
FIELD COMPACTION REPORT
Job No. 17931033
Job Name and Location I~I.3. DESIGNS DISWRII31~ION ~ Date 2-2-94
Architect or Engineer JAMEB, HARgTICK + PARIIxlERS, INC.
Contractor BOB I,'ODRE ODNSTRUCWION, INC.
Datum SITE DATUM
lift No. Maxin~n In-Place In-Place
Test Date Location or Mt[. Lab Dry Uet Water Dry Percent Cor~ents
No. Ete~.' .... Mark Density Density Content Density Comp. _ ................
319 1-20 530 - S LIFT 3 E 125.0 132.8 9.3 121.5 97
35O - E
320 1-20 470 - S
320 - E lIFT 3 E 125,0 133.3 9.5 121.7 97
321 1-20 470 - S LIFT 3 E 125.0 134.6 9.2 123.2 99
440 - E
322 1-20 470 - S
550 - E LIFT 3 E 125.0 133.5 9.4 122.0 98
323 1-20 STATION 0+20 FT LIFT 1 C 98.5 119.7 25.2 95.6 97 STORM
324 1-20 STATION 0+40 FT LIFT I C 98.5 121.2 26.0 96.2 98 STORM
325 1-20 STATION 0+40 FT LIFT 1 C 98.5 119.3 25.5 95.1 96 STORM
326 1-21 430 - S LIFT 3 E 125.0 133.0 9.2 121.7 97
32O - E
430 - S LIFT 3 E 125.0 134.6 9.2 123.2 99
327 1-21 440 - E
328 1-21 430 - S LIFT 3 E 125.0 132.7 9.0 121.7 97
55O - E
329 1-21 380 - S
550 - E LIFT 3 E 125.0 134.0 9.5 122.3 98
330 1-21 380 - S
440 - E LIFT 3 E 125.0 133.5 9.3 122.1 98
331 1-21 380 - S LIFT 3 E 125.0 134.5 9.6 122.7 98
340 - E
332 1-21 STATION 0+20 LIFT 2 C 98.5 118.6 25.3 94.7 96 STORM
333 1-21 STATION 0+40 LIFT 2 C 98.5 119.0 25.5 94.8 96 STORM
334 1-21 STATION 0+60 LIFT 2 C 98.5 119.3 26.0 94.7 96 STORM
335 1-21 STATION 0+20 LIFT 3 C 98.5 121.4 25.8 96.5 98 STORM
336 1-21 STATION 0+40 L FT 3 C 98.5 120.1 25.1 96.0 97 STORM
337 1-21 STATION 0+60 L FT 3 C 98.5 119.6 26.0 94.9 96 STORM
338 1-21 STATION 0+20 L FT 4 C 98.5 119.3 26.2 94.5 96 STORM
339 1-21 STATION 0+40 L FT 4 C 98.5 121.1 25.8 96.3 98 STORM
340 1-21 STATION 0+60 L FT 4 C 98.5 119.5 26.1 94.8 96 STORM
341 1-27 580 - S
40 - E L FT 3 E 125.0 133.7 9.8 121.7 97
342 1-27 520 - S
120 - E L FT 3 E 125.0 135.0 10.0 122.7 98
343 1-27 590 - S
190 - E I FT 3 E 125.0 132.5 9.5 121.0 97
344 1-27 530 - S LIFT 3 E 125.0 134.0 9.0 122.9 98
260 - E
345 1-27 590 - S
280 - E LIFT 3 E 125.0 133.5 9.4 122.0 98
NOTES: Densities shown: pounds per cubic foot
Water Content: Percent of dry weight lbrracan
Percent Compaction: Based on maximum dry density obtained on
sample indicated by material mark.
FIELD COMPACTION REPORT
Job No. 17931.033
Job Name and Location }4.J. DESIGNS DISTRIBUTION ~ Date 2-2-94
Architect or Engineer 0'bI4ES, HARNICK + P~, INC.
Contractor BOB I~IOORE CONSrIRUCI'ION, INC.
Datum SITE DATUM
Lift No. Maximum In-Ptace In-Ptace
Test Date Location or Ntt. Lab Dry Net Water Dry Percent Comments
No. E[ev. Mark Density Density Content Density Comp.
346 1-27 STATION 0+60 LIFT 1 C 98.5 119.3 26.4 94.4 96 STORM
347 1-27 STATION 0+100 LIFT I C 98.5 122.2 25.1 97.7 99 STORM
348 1-27 STATION 1+50 LIFT 1 C 98.5 120.0 25.0 96.0 97 STORM
349 1-28 580 - S
320 - E GRADE E 125.0 134.2 9.5 122.5 98
350 1-28 580 - S
390 - E GRADE E 125.0 135.0 10.0 122.7 98
351 1-28 580 - S GRADE E 125.0 133.5 9.4 122.0 98
450 - E
352 1-28 580 - S
510 - E GRADE E 125.0 133.0 9.2 121.7 97
353 1-28 580 - S
580 - E GRADE E 125.0 134.0 9.0 122.9 98
354 1-28 490 - S
580 - E GRADE E 125.0 133.7 9.8 121.7 97
355 1-28 490 - S GRADE E 125.0 132.6 9.4 121.2 97
510 - E
356 1-28 480 - S
440 - E GRADE E 125.0 132.5 9.5 121.0 97
357 1-28 480 - S GRADE E 125.0 134.0 9.8 122.0 98
350 - E
358 1-28 410 - S
310 - E GRADE E 125.0 133.4 9.9 121.3 97
359 1-28 410 - S
410 - E GRADE E 125.0 134.5 10.2 122.0 98
360 1-28 410 - S
510 - E GRADE E 125.0 132.5 9.5 121.0 97
361 1-28 380 - S
580 - E GRADE E 125.0 134.8 9.3 123.3 99
362 1-28 380 - S
470 - E GRADE E 125.0 133.5 9.4 122.0 98
363 1-28 370 - S
350 - E GRADE E 125.0 133.3 9.0 122.2 98
364 1-28 STATION 0+60 LIFT 2 C 98.5 120.1 27.0 94.6 96 STORM
365 1-28 STATION 1+00 LIFT 2 D 98.5 119.5 26.8 94.2 96 STORM
366 1-28 STATION 1+50 LIFT 2 C 98.5 121.3 26.6 95.8 97 STORM
367 1-28 STATION 0+60 LIFT 3 C 98.5 122.5 25.7 97.5 99 STORM
368 1-28 STATION 1+00 LIFT 3 C 98.5 121.8 26.1 96.6 98 STORM
369 1-28 STATION 1+50 LIFT 3 C 98.5 119.5 26.0 94.8 96 STORM
370 1-28 STATION 0+60 LIFT 4j C 98.5 120.0 27.3 94.3 96 STORM
371 1-28 STATION 1+00 LIFT 4 C 98.5 119.8 26.8 94.5 96 STORM
372 1-28 STATION 1+50 LIFT 4 C 98.5 119.0 26.6 94.0 95 STORM
NOTES: Densities shown: pounds per cubic foot
Water Content: Percent of dry weight ] ~rracan
Percent Compaction: Based on maximum dry density obtained on
sampte indicated by materiat mark.
HELD COMPACTION REPORT
Job No. _1.793]_033
Job Name and Location M.J. DESIGNS DISTRIBUTION C~X~fER Date 2-2-94
Architect or Engineer JAMES, HA..q~CK + P~, INC.
Contractor BOB MOORE CONSTRUCTION,. INC.
Datum SITE DATUM
Lift No. Maximum In-Ptace In-Ptace
Test Date Location or Ntt. Lab Dry get Water Dry Percent Comments
~o. Etev. Mark Density_ Density Content Density Comp.
373 1-29 340 -S GRADE E 125.0 133.6 9.5 122.0 98 310 - E
374 1-29 290 - S GRADE E 125.0 131.0 9.2 119.9 96 380 - E
375 1-29 340 - S
450 - E GRADE E 125.0 134.1 9.5 122.4 98
376 1-29 280 - S GRADE E 125.0 132.4 9.2 121.2 97 520 - E
377 1-29 330 - $ GRADE E 125.0 133.5 9.3 122.1 98 580 - E
NOTES: Densities shown: pounds per cubic foot
Water Content: Percent of dry weight 1 l'erracon
Percent Compaction: Based on maximc~n dry density obtained on
sample indicated by material mark.
· ll'err can
135 ,
\ MOISTURE-DENSITY RELATIONSHIP
Job No. 17931033 Date 1/2119~1
13o ~ ~ Project MJ DESIGNS DISTRIBUTION
CENTER - COPPELL. TEXAS
~ Source of Material OFF SITE-FORT WORTH
125 ~,
Description of Material REDDISH TAN CI.AYEY
SAND
120 ~ Material Designation F
Test Method ASTM D-698 {METllOD A)
115 ~
TEST RESISTS
o -- Maximum Dry Densily 117.0 PCF
o
Optimum Water Content 13.5 %
.9. 11o ~
o ATTERBERG LIMITS
a. ~05 LL PL PI
-o 25 14 11
o
'-' CURVES OF 100% SATURATION
I00 FOR SPECIFIC GRAVITY EQUAL TO:
H -- 2.80
-- 2.70
>- 95
n. -- 2.60
90
85
80
75
0 5 10 15 20 25 30 35 40 45
I41~TER CONTENT (Percent Drg Weight)