Park West CC(12)-LR010117GEOTECHNICALAND G F;I r"3 I I I=~
ENVIRONMENTAL CONSULTANTS
REPORT OF WATER INJECTION OBSERVATION
Parkwest Commerce Center - Building 5
Enterprise and Wrangler
Coppell, Texas
REPORTED TO: Pritchard Associates
2501 State Street
Dallas, Texas 75201
ATTN: Mr. Roger Dahlin
REPORT NO. 3
REPORT DATE: 01-17-01
REG PROJECT NO. 7479
TECHNICIAN: C. Johnson
PAGE: 1 of 1
CONTRACTOR: McFadden & Miller, Inc.
On these dates a representative of Reed Engineering Group, Inc. observed water injection
operations on the referenced project. The injection operations proceeded in accordance
with project specifications unless otherwise noted.
Specification
Injection Depth Injection Spacing I Injection Pressure Injection Intervals
(ft) (ft) I (psi) (in)
10 5 100-200 12-18
Equipment
Number of Number of Probes I Length of Probes Probe Spacing
Ricjs (ea) J (ft) (ft)
2 4 11.5 5
I01-09-01 10,000 180 1
01-11-01 2,000 180 1
Date J Area Injected (sq ft) J Avera~le Pressure (psi) J Pass No.
Surfactant added at regular intervals: Yes
Mail
Distribution: (1)
(1)
Pritchard Associates/
Mr. Roger Dahlin
O'Brien & Associates/
Mr. Mick Granlund
(1) Technistructures/Mr. Keith Leslie
(1) McFadden & Miller, Inc./
Mr. Jon Jacobson
(1) Halff Associates/Mr. Dave Littleton
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
Submitted by:
REED ENGINEERING GROUP, INC.
Original Signed By
James F. Phipps, P.E.
BW/mm
2424 STUTZ DR. · SUITE 400 · DALLAS. TX 75235 · TEL [214] 350 5600 ,, FAX [214] 350 0019
GEOTECHNICALAND J~ R r-I I I ~
ENVIRONMENTAL CONSULTANTS
REPORTED TO:
REPORT OF WATER INJECTION OBSERVATION
Parkwest Commerce Center - Building 5
Enterprise and Wrangler
Coppell, Texas
Pritchard Associates
2501 State Street
Dallas, Texas 75201
ATTN: Mr. Roger Dahlin
REPORT NO. 4
REPORT DATE: 01-17-01
REG PROJECT NO. 7479
TECHNICIAN: C. Johnson
PAGE: 1 of 1
CONTRACTOR: McFadden & Miller
On these dates a representative of Reed Engineering Group, Inc. observed water injection
operations on the referenced project. The injection operations proceeded in accordance
with project specifications unless otherwise noted.
Injection Depth
(ft)
Specification
Injection Spacing J Injection Pressure Injection Intervals
(ft) J (psi) (in)
10 5 100-200 12-18
Equipment
Number of Number of Probes I Length of Probes Probe Spacing
Rigs (ea) J (ft) (ft)
2 4 11.6 5
Date J Area Injected (sq fi) J Average Pressure (psi) J Pass No.
01-13-01 16,000 180 1
01-15-01 26,000 180 2
Surfactant added at regular intervals: Yes
Mail
Distribution:
(1) Pritchard Associates/
Mr. Roger Dahlin
(1) O'Brien & Associates/
Mr. Mick Granlund
(1) Technistructures/Mr. Keith Leslie
(1) McFadden & Miller, Inc./
Mr. Jon Jacobson
(1) Halff Associates/Mr. Dave Littleton
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
Submitted by:
REED ENGINEERING GROUP, INC.
Original Signed By
James F. Phipps, P.E.
BW/cg
2424 STUTZ DR. · SUITE 400 · DALLAS, TX 75235 · TEL [214] 350 5600 · FAX [214] 350 0019