Loading...
Park West CC(13)-SY 910502r r r G~OT~CHNICAL INVESTIGATICN TOYO TIRES PARK WEST ~ CENTER COPP~.V., TEXAS FOR Prentiss Properties Limited, Dallas, Texas MASON JOHNSTON & ASSOCIATES, INC. geotechnical consultants 235 Morgan Ave., Dallas, Texas 75203-1088 ~1~41~808 02200 - EARTHWORK PART I - GENERAL 1.01 SOILS INVESTIGATION Refer to Mason Johnston & Associates Soil Report %MJ 5771 dated March 6, 1991. 1.02 PROTECTION~ Car6fully maintain bench marks, monuments, layout stakes and other reference points. Protect property, including adjoining property and public rights-of-way, from damage by trucks and equipment. PART 2 - PRODUCTS 2.01 MATERIALS~ ae Fill under building (including backfill against inside of tilt-up panels): After stripping, the cut material below the stripped depth will be used for fill at the site, if approved by the geotechnlcal engineer. The building pad areas may be filled up to within 11" from the concrete slab 'elevation with existing on-site soils or similar. This fill will be installed in maximum 8-inch loose lifts at a moisture content of 0 to 4 percent above optimum and compacted to 92 percent minimum and 98 percent maximum of maximum dry density determined by ASTM D698. This fill will be used first in all paving areas and then the fill will be used under the building. The floor slab shall rest on a minimum of 6" of select fill. The contractor at his option may substitute a 2" sand leveling coarse with 4" of select fill (Total 6"). The site fill will be placed under the building to a level of 6 inches below the bottom of the slab. Select fill consisting of predominately granular material with a Liquid Limit less than 35 and a Plasticity Index between 6 and 15 will be compacted below the building floor slab. In the event that the site material available is not adequate to fill to a level of 6 inches below the bottom of the building slab, the select fill layer will exceed 6 inches. The depth of select fill below the slab will be approximately the same throughout the building with the maximum deviation allowed being 2 inches. 02200-1 22 ROSS DESIGN GRP INC 214 350-?344 P. 0~ Fill shall be free from trash, debris, roots over 1" in diameter, matted roots, rocks over 3" in diameter, topsoil, high plastic soils or other deleterious matter. (Contractor's option) Top 2" of fill material under floor slab shall be clean, tamped sand, free of roots and debris. Place sand over over 6 mll polyethylene moisture barrier under office· 5. The building pad shall be constructed in the sequence shown on the structural drawings. Building pad must be constructed to building limits, then cut back 3' to erect panels. B. The soil moisture content must be maintained in all at- grade soll surfaces, both building pad and truck court and parking areas. The goal ks to avoid surface checking which is an indication of drying of the subgrade soils. The soil mousture must be maintained in the subgrade and select fill until covered by the floor slab or pavement· This will require soaker hoses, continual water truck passes, or other approved means to maintain the subgrade soil moisture throughout its exposure to the atmosphere. The actual soil moisture content percentage level will be determined during construction by the owner's testing laboratory and is expected to be in the order of 26 to 28 percent. C. Site Fill and Backfilling: On-site materials. If adequate quantities do not exist, acceptable fill must be comparable to acceptable on-site materials, or better. i. Fill under paving shall be compacted to 95% to 98% Standard Proctor Density, ASTM D698, at moisture contents within 0 to 4% of optimum moisture. Utility trenches: Under Paving: On-site materials or equal compacted to 95% to 98% Standard Proctor Density, ASTM D-698, at 0 to 4% of optimum moisture. Under Building: Select fill having plasticity index of 6 to 15 compacted to 92 to 98% Standard Proctor Density, ASTM D-698 with a moisture content of 0 to 4% above optimum. Ail other areas: On-site materials or equal compacted to density of existing earth. 02200-2 Fill and backfill for all utility trenches shall be free from trash, debris, matted roots, rocks over in diameter topsoil, clods and other deleterious matter. PART 3 - EXECUTION 3.01 CLEARING~ Remove trees, shrubs, bushes, trash, debris and other obstructions, found at or above existing grade, from areas of building, walks, curbs and paving. Strip 18" of soil from the site. This material is expected to be a darker colored clay topsoil. If the material changes in color before 18 inches is stripped, the darker topsoil should be stockpiled separately. Cw Remove stumps, roots over 2" in diameter, matted roots and other obstructions, found at or below existing grade, from cleared areas. 3.02 EXCAVATION: Excavate to bring areas to grades and subgrades indicated. Make excavations large enough to permit placing and removal of shoring, forms, etc., and for proper inspection of work. Where it is necessary to cut on-site material, under paving or building, cut to required elevation, scarify top 6" of remaining soil, replace and recompact to minimum 92% and 98% maximum of maximum dry density determined by ASTM D698 at a moisture content of 0 to 4% above optimum. Where it is necessary to cut on-site material, cut to required elevation, scarify top 6" of remaining soil, replace and recompact to min. 90% Standard Proctor Density at moisture content at or within 3% above optimum, as determined by ASTM D698. Remove and dispose of excavated material that is unsuitable or not required for backfilling. Remove underground obstructions. Drainage and pumping= Provide for adequate surface drainage during construction in manner to keep site free of surface water without creating nuisance in adjacent areas. Keep excavations free of water. 02200-3 3.03 Shoring: Properly sheet and brace sides of excavations where necessary and maintain securely until permanent construction is in place. Remove temporary shoring and bracing as backfill is placed. FILL AND BACKFILL~ A. Placement: Place materials in looser even, successive horizontal lifts, not to exceed 8# deep under building and paving, and 12" deep elsewhere. B. Compaction: Thoroughly and evenly compact each lift to following densities and moistures: 1. Fill and backfill under building: Reference 2.01, A, 1. Fill and backfill under paving.' Reference 2.01, C, 1. Site fill and backfill: To density equivalent to 90% of Standard Proctor Density, ASTM D-698. Site backfill and fill at all sloping conditions shall be placed and compacted to Texas Highway Department Standards for Embankments, Item #132. Moisture Control: When moisture must be added prior to compaction, uniformly apply water to surface but do not flood. Free water shall not appear on surface during or after compaction operations. Remove and replace, or scarify and air-dry soil too wet to allow proper compaction. Grading: Uniformly grade areas, including adjacent transition areas to smooth surface at required grades and elevations. Adjust contours to eliminate water ponding and provide positive drainage. Where rock strata or large rocks 6" or more in dia. are encountered in areas indicated on site plan to be planting, excavate min. 8" below adjacent tops of curbs, sidewalks, or finish grade lines, and refill to within 1" of these levels w~th acceptable topsoil free from rocks, heavy clay lumps, or trash. Uniformly distribute stockpiled topsoil over areas designated for planting and areas of site where grades have been modified, which are not covered by building or paving. Place to man. 4" depth; grade level and smooth. Remove excess and waste materials; dispose of off site, unless directed otherwise. 02200-4 25 3.04 TRENCHING Perform all trenching required for the installation of items where the trenching As not specifically described in other Sections of these Specifications. Make all trenches open vertical construction with sufficient width to provide free working space at both sides of the trench and around the installed item as required for caulking, joining, backfilling, and comDacting. Depth: Trench as required to provide the elevations shown on the Drawings. Where elevations are not shown on the Drawings, trench to sufficient depth to give a mini- mum of 18" of fill above the top of the pipe, measured from the adjacent finished grade, except provide a minA- mum 30" cover on cement pipe. Correction of Faulty Grades: Where trench excavation is inadvertently carried below proper elevations, backfill with material approved by the Architect, and then compact to provide a firm and unyielding subgrade and/or foundation to the approval of the Architect and at no additional cost.to the Owner. Trench Bracing: Properly support all trenches in strict accordance with all pertinent rules and regulations. Brace, sheet, and support trench walls in such a manner that they will be safe and that the ground along side the excavation will not slide or settle, and that all existing improvements of every kind, whether on public or private property, will be fully protected from damage. e In the event of dmmage to such improvements, immedlately make all repairs and replacements necessary to the approval of the Architect and at no additional cost to th Owner. Arrange bracing, sheeting and shoring so as to not place stress on any portion of the completed work until the general construction thereof has proceeded far enough to provide sufficient strength. Removal of trench bracing: Exercise care in the drawing and removal of sheeting, shoring, bracing and tinbering to prevent collapse and caving of the excavation faces being supported. 02200-5 26 3.05 3.06 Grading and stockpiling trenched material: Control the stockpiling of trenched material in a manner to prevent water running into the excavations. Do not obstruct surface drainage, but provide means whereby storm and waste waters are diverted into existing gutters, other surface drains, or temporary drains. FOUNDATION FOR PIPES: Grade the trench bottoms to provide a smooth, firm, and sta61e foundation free from rock points throughout the length of the pipe. Select fill material: Place a minimum of six inches of the specified select fill material in the bottom of the trench. C. Subsurface condtttons~ In areas where sole, unstable materials are encountered at the surface upon which select fill is to be placed, remove the unstable material and replace it with material approved by the Architect. Make sufficient depth to develop a firm foundation for the item being installed. If the need for such over-excavatuib has been occasioned by an act or failure to act on the part of the Contractor, make the over-excavation and replacement at no additional cost to the Owner. D. 'Shaping: At each joint in pipe, recess the bottom of the trench as required into the firm foundation in such a manner as to relieve the bell of the pipe of all load and to ensure continuous bearing of the pipe barrel on the firm foundation. Accurately shape all pipe subgrade and fit the bottom of the trench to the pipe shape. Use a drag template shaped to conform to the outer surface of the pipe if other methods do not produce satisfactory results. BEDDING FOR PIPES: Place the specified select fill material in the trench, simultaneously on each side of the pipe for the full width of the trench, to a maximum depth of three feet and a minumum depth of one foot above the outside diameter of the pipe barrel. 02200-6 27 05/02/91 09:52 ROSS DESIGN GRP INC 214 350-?~44 P, 08 3.07 3.08 B. Densification: Dens/fy the bedding material after placing by thoroughly saturating with water and compacting with avibratory compactor. Take special care to provide firm bedding support on the underside of the pipe and fittings for the full length of the pipe. ~lternate Bedding~ Other bedding procedures and materials may be used if prior written approval has been obtained from the Architect. BACKFILL FO~ PIPES~ Using Imported Select Fill: After the pipe has been thoroughly bedded and covered, fill the remaining portion of the trench with the specified fill material, and densify as specified in this Section. TESTING= Underfloor Area Fill: Moisture and density tests shall be conducted by the Owner's soil laboratory at the rate of one test per every 5,000 square feet of underfloor area fill for each compacted layer. There shall also be one test per each 100 linear feet along each of the tilt- up wall sides in the interior backfill area for each compacted layer. Paving Area Fill: Moisture and density tests shall be conducted by the Owner's soll laboratory at the rate of one test per every 10,000 square feet for each compacted layer. ~ND OF SECTION 02200-7 28 MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS m GEOLOGI&T&I GEOTECHNZC~L ZNVESTZG~TZON TOYO TIRES pARK~EST COI. fl~,ERCE CENTER COPPELL~ TEX~S FOR PrentiSs Properties Limited, Inc. Dallas, Texas INTRODUCTION In accordance with the authorization of our proposal dated 26 December 1990, we have completed a geotechnical investigation for the captioned project. Plans provide for the design and construction of a one-story office/warehouse building to be located at the southeast corner of the intersection of Airline Drive and Enterprise Drive in Park West Commerce Center, Coppell, Texas. SCOPE The scope of the geotechnical investigative activities reported includes subsurface exploration and laboratory testing on selected samples from the borings. The resulting data were used to develop general recommendations to guide design and construction of the new facility. This report has been prepared for the exclusive use of Prentiss -1- MASON--JOHNSTON A ASSOCIATES, INC. DALLAS, TEXAS Properties Limited, Inc. for specific application to the Toyo Tires site in Park West Commerce Center, in accordance with generally accepted soil and foundation engineering practices. No other warranty, expressed or implied, is made. SUBSURFACE INVESTIGATION Subsurface investigation of the site of the proposed office/warehouse construction consisted of advancing five (5) NX-size core borings to depths ranging from 46.5 to 58 feet below existing grade and two (2) soil borings approximately 10 feet in depth, drilled at the approximate locations shown on Plate 1. The borings were drilled and located in the field by Mason-Johnston personnel using a tape measure and site plan. The boring locations should be considered accurate only to the degree implied by the method used. These borings were advanced by means of a truck-mounted rotary drilling rig which uses water as a drilling fluid. Undisturbed samples of cohesive soils encountered were obtained using a thin-walled, seamless, Shelby-tube sampler advanced into the soil by a rapid, continuous thrust from two balanced hydraulic rams on the drilling rig. Continuous cores of the primary sediments encountered were obtained using a double-tube core barrel equipped with a suitable cutting bit. -2- MASON--JOHNSTON · ASSOCIATES, INC* DALLAS, TEXAS Samples obtained from the borings were wrapped in polyethylene plastic to prevent changes in moisture content and to preserve in situ physical properties. Ail samples were classified as to basic type and texture in the field, labeled as to appropriate boring number and depth, and placed in core boxes for transport to the laboratory. An observation well (perforated PVC pipe) was installed in Boring 3 to monitor the groundwater level at the site. A schematic of the installation and a summary of data obtained to date are presented on Plate 2. L~BORATORY T~8~ZNG Ail samples were classified inthe laboratory by an experienced technician. To aid in the classification process, series of Atterberg Limits, Moisture Contents and Dry Unit Weight Tests were performed on representative samples. These test data are presented on Plates 3 and 4. Strength properties were investigated by a series of Unconfined Compression Tests. In this test, an axial load is applied to a laterally unsupported cylindrical core sample until failure occurs within the sample. These test data are summarized on Plate 5 and stress-strain curves for selected samples are presented on Plates 6 through 11. The expansive characteristics of the overburden soils were -3- MASON--JOHNSTON & ASSOCIATES, INC. OAI. LAS, TEXAS investigated in the laboratory by conducting Absorption Pressure and Swell Tests. These tests provide a measure of the maximum pressure that may be expected to be generated when the soil sample is exposed to water and restrained from movement and a measure of the maximum free swell when vertical restraint is removed. Graphical results of these tests are presented on Plates 12 and 13. SUBSURFACE CONDITIONS Detailed descriptions of the types, depths and thicknesses of the various strata encountered may be seen on the attached "Log of Boring" illustrations. In general, from the ground surface down, materials present at the site consist of varying thicknesses of moderate to high plasticity clay underlain by the primary geologic formation identified as the Eagle Ford Shale. The overburden soils present at the proposed site are for the most part residual in nature having been derived from differential weathering of the Eagle Ford Shale Formation during previous geologic time. The resulting soil cover is of varying thickness, from 6 to 12.5 feet. After penetrating the residual overburden materials, the core borings drilled at the site encountered the compact clayey shale of the Eagle Ford Shale Formation of Cretaceous Age. Typically, and in its unweathered state, the Eagle Ford Shale -4- MASON--JOHNSTON & ASSOCIATES, INC* DALLAS, TEXAS Formation generally consists of dark to medium gray, firm, thinly laminated, well compacted clayey shale strata. The borings encountered occasional thin bentonite or bentonitic clay seams, and thin, hard to very hard limestone seams as noted on the logs. Throughout the project area, the uppermost layer of Eagle Ford Shale, ranging in thickness from about 16 to 25 feet, is tan to light gray in color, having experienced differential weathering in the form of leaching. The degree of weathering decreases with increasing depth. The Absorption Pressure and Swell Tests performed on near-surface clays indicate a low potential for heave with increases in moisture content at present soil moisture content. Maximum swell pressure was less than 900 psf and the maximum free-swell was less than i percent. Measurements of groundwater level in the observation well set in Boring 3 show that the water level has risen from 24 feet below ground surface to about 13 feet below ground surface in the ten days over which readings have been taken. The water level has not yet reached equilibrium and may rise more before it does. We recommend that additional water level readings be taken up to the time construction activities destroy the installation. FOUNDATION DESIGN CONSIDERATIONS Based on the results of this investigation, we recommend that -5- MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS ~ GI~OL OGI&TG structural loads be transferred into the firm, unweathered, gray shale of the Eagle Ford Shale Formation by means of straight-walled, auger-excavated, cast-in-place, concrete shafts. The borings drilled for this site indicate a distinct reduction in strength in the shale below a depth of about 50 feet. We recommend that the higher allowable stress transfer values given below be used for design of piers based at least three pier diameters above the 50 foot depth level and the lower values used for piers based below that depth range. Stress Transfer Value End Bearing Side Shear, Compression Side Shear, Tension Greater than 3 Diameters above 50 feet Less than 3 Diameters above 50 feet 16.5 tsf 9.5 tsf 5.2 tsf 3.1 tsf 2.6 tsf 1.5 tsf Side-shear stress transfer is limited to the perimeter portion of the pier shaft in intimate contact with firm, gray unweathered shale extending below the base of any temporary casing that may be required to install the shafts. Accordingly, it is recommended that the upper 2 feet of the shale formation be neglected in computing required penetrations. The side shear values provided are directly applicable for isolated drilled shaft foundations separated in plan by a clear distance of at least two shaft diameters. If this spacing cannot be maintained, this office should be -6- ENGINEERS MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS OGleS TS contacted so that additional studies can be carried out and reduced design values developed to compensate for stress overlap between adjacent footings. We anticipate that settlement of shafts installed in the shale formation will be less than about one-half inch. Much of the settlement will occur as elastic deformation which should be substantially complete at the end of construction. The overburden soils and weathered shale strata to be penetrated by the drilled shafts have a swell potential particularly within the upper zones and thus the shafts will be potentially subjected to uplift forces caused by expansion of the adjacent materials. The normal "rule of thumb" for such. conditions is to provide liberal shaft reinforcement to resist these potential forces. Minimum reinforcement on the order of one percent of the shaft area is recommended. CONSTRUCTION PROCEDURES Each shaft installation should be vertical (within acceptable tolerances), placed in proper plan location and cleaned prior to concrete placement. Reinforcing steel cages should be prefabricated in a rigid manner to allow expedient placement of both steel and concrete into the excavation. It is essential that the placement of both steel and concrete be completed as soon as practical after completion of the excavatiOn. This will insure that the maximum benefit of the bearing stratum -7- I~NGINEEN$ MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS rebound properties are utilized. In all cases, no portion of the stratum being counted on to provide structural support should be exposed to atmospheric conditions for more than eight (8) hours prior to the placement of the concrete. The use of temporary casing should be anticipated to control groundwater seepage. The casing should be installed a sufficient distance into the bearing stratum to insure a water tight seal; normally a distance of 1 to 2 feet is adequate for this purpose. After the satisfactory installation of any temporary casing, the required shaft penetration may be excavated by machine auger within the casing in a conventional manner. If the groundwater level is above the base of any temporary casing being utilized, extreme care should be maintained at all times to insure that the head of the plastic concrete is higher than the static groundwater level outside the casing. In actual practice, it is desirable that the head of the plastic concrete be appreciably above the static groundwater level prior to breaking of the seal between the temporary casing and the bearing stratum. Once the seal is broken, the temporary casing may be slowly removed in a vertical direction only (no rotation permitted) while additional concrete is elevated to the top of the casing and placed through a tremie in order to connect with the existing concrete contained within the lower portion of the shaftl -8- MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS FLOOR SLAB AND GRADE BEAMS Structural elements in direct contact with the natural clay soils will be potentially subject to movements associated with soil heave caused by soil moisture variations. The magnitude of movements will vary depending on sustained pressure, soil moisture levels at the time of construction, and moisture variations actually experienced following construction. Cutting and filling probably will be needed to level the site. Swell calculations, which include a layer of inert fill, indicate that about 0.5 to 1.0 inches of swell should' be anticipated. It should be noted that the soil samples were taken during a wet season and are therefore already have relatively high mositure content. This phenomenon reduces the current laboratory swell potential. If the site dries before construction of the floor slab begins, higher swell potential may be encountered at a later time when the soil enters a new seasonal cycle of wetting and drying. Such dry conditions could create the potential for more than 2 inches of soil.heave. To take advantage of the current moist condition of the site, the soil surface when cut to grade must be maintained in the moist condition. This will require periodic sprinkling of the soil surface, probably several times a day in hotter weather, or the use of soaker hoses. The soil surface, once exposed, must not be allowed to begin drying before it is finally covered with select fill and the floor slab. In using this -9- MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS approach, we recommend that floor slabs be physically separated from grade beams and columns to allow for some movement. If this magnitude of swell cannot be tolerated by the structure, then alternate schemes can be discussed at a later date in conference once perfomance and economic objectives are more firmly established. Alternatative measures include one or more of the following: stabilization with hydrated lime, more extensive cutting and filling, preswelling the site, and a structural floor system. The grade beams and other pier-supported beams require a positive separation from the underlying soil (about 4 inches) if swell of the above magnitude cannot be tolerated. E~RTHWORK Earthwork recommendations are as follow: 1. Excavate and waste or stockpile organic topsoil present in the construction area. 2. Scarify soils exposed in fill areas and transitional areas (cut to fill and fill to cut) to a depth of approximately six (6) inches, add moisture (if required), mix and recompact to a density of 92 to 98 percent of the maximum density obtained by the Standard Proctor Compaction Test (ASTM D-698). The moisture content of the compacted soils should be maintained between optimum and plus four percent of the optimum value (determined from ASTM D-698) until covered by -10- E#OINEER$ MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS fills and the slab. Sprinkling or use of soaker hoses as described above should be planned. 3. Place fill soils in loose lifts not exceeding nine (9) inches and compact to the moisture/density values specified in No. 2 above. 4. Fill material should be inorganic, having a Liquid Limit less than 35 and a Plasticity Index between 6 and 15. Soils present at the site may be manufactured and used for fill material if they meet the above requirements. To enhance pavement performance, it is recommended that clay soils exposed at grade be maintained at current moisture content as described above for the floor slab. We recommend that a geotextile'material, such as Mirafi 600X or 700X be placed over the soil surface at all joints to assist in providing soil stability. If there is a requirement for soils to be stabilized with hydrated lime for use as subbase, a minimum treatment depth of six (6) inches should be contemplated. Subject to modification during construction, a hydrated lime content of five (5) percent by dry soil weight (approximately 5 pounds of lime per cubic foot of soil treated) would be expected to effectively stabilize the subgrade soil. Soils treated with hydrated lime for use as subbase should be compacted to a minimum dry density of 95 percent of the maximum density as defined by Texas -ll- MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS Highway Department Test Method TEX-ll3-E and at a moisture content at least two (2) percentage points above the optimum moisture content determined by that test. This requirement is important in minimizing post construction movement and in assuring complete hydration of the lime treated soils. Pavement grades should be established in anticipation of some vertical movement associated with expansion or contraction of the near surface clay soils. It is important to establish good surface drainage to provide for rapid removal of surface water away from the building and paved area. The following minimum pavement sections have been developed for your consideration: ASPI~ALTIC CONCRETE Light Vehicular Traffic (Parking Lots, Drives, Etc.) 1-1/2 inch HMAC Surface Wearing Course 3 1/2 inch HMAC Base Course 6 inch Stabilized, Compacted Subgrade Heavy Vehicular Traffic (Service Drives, Trucks, Etc.) 1-1/2 inch HMAC Surface Wearing Course 5 inch HMAC Base Course $ inch Stabilized, Compacted Subgrade -12- MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS REINFORCED CONCRETE Light Vehicular Traffic (Parking Lots, Drives, Etc.) 5 inch Reinforced Concrete Paving (Re-Steel: #3 at lS inches on center) 6 inch Stabilized, Compacted Subgrade Heavy Vehicular Traffic (Trucks, Service Drives, Etc.) 6 inch Reinforced Concrete Paving (Re-Steel: #3 at 18 inches on center) 6 inch Stabilized, Compacted Subgrade In the event reinforced concrete paving is used, it is essential that any and all reinforcing be placed so as to insure a minimum of 1 1/2 inch cover. It is believed that one or more of the above suggested pavement sections may be entirely suitable for use on this project. Selection of the proper section should be based on anticipated traffic loads, frequency, and long term maintenance, as well as project economics. In general, asphaltic concrete sections have a lower initial cost, but require more frequent maintenance than the concrete surface. It is recommended that the soil and foundation engineer be provided the opportunity for a general review of final design and specifications in order that earthwork and foundation -13- MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS recommendations may be properly interpreted and implemented in the design and specifications. In the event that any changes in the nature, design or location of the building are recommendations contained considered valid unless planned, the conclusions and in this report shall not be the changes are reviewed and conclusions of this report modified or verified in writing. We appreciate the opportunity to assist in this phase of the project. Please call us if we can be of further service during later stages of design or during construction. ~,,,~... -; .....-r~: ~. ~ ~o,~ w. ~o,,s~R~.., ~-.-v ..................... : G JWJ 6 March 1991 ~ No. 5771 Respectfully submitted, Mason-Johnston & Associates, Inc. -14- i,i AIRLINE DRIVE LEGEND I {~ CORE BORING N CORE BORING WITH OBSERVATION WELL SOIL BORING 0 $0 60 120 ~-- ~-- , Scole Feet MASON-JOHNSTON & ASSOCIATES. INC. GEOLOGISTS - ENGINEERS LOCATION OF BORINGS TOYO TI RES PARK WEST COMMERCE CENTER COPPELL, TEXAS MJAN_O. 5771 ! DATE 2/91 I "~.ATE I I I GROUNDWATER LEVEL READINGS BORING DEPTH TO NUMBER DATE WATER 2-26-91 24-.0 2-27-91 21.9 2-28-91 20.0 3-04--91 13.1 VENTED CAP SEAL CAP GROUND SURFACE BENTONITE) --ILL TOYO TIRES Park WEST COMMERCE CENTER OBSERVATION WELL INSTALLATION AND READINGS MASON-JOHNSTON &: ASSOCIATES,INC. GEOLOGISTS-ENOIN E]~S JOB NO.: 5771 I 2 DATE INS"r/u ! I:TI: 2--19-91 I MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS BORING NUMBER 1 1 1 1 1 1 1 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 5 6 6 6 6 6 6 6 6 6 TOYO TIRES PARK~EST COHI(ERCE CENTER COPPELL, TEX~S SUI. fl~.RY OF CLASSIFICATION TESTS DEPTH LL PI MC DUW (ft.) (%) (%) (pcf) 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.5 7.5-9.0 9.0-10.5 58 25.5 24.3 114.7 26.3 25.7 27.2 30 27.8 95.5 26.3 UNIFIED SOIL CLASSIFICATION 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.5 7.5-9.0 9.0-10.5 27.7 26.1 30.4 28.7 27.7 29.4 30.0 0.0-1.5 1.5-3.0 1.5-3.0 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.5 7.5-9.0 9.0-10.5 13.0-14.5 17.5-19.0 22.5-24.0 31.0-31.5 41.8-42.3 55.9-56.4 50 53 54 22 8 9 30.7 29.9 90.8 28.4 28.5 28.9 91.1 28.6 92.7 34.6 25.7 95.9 30.7 27.2 16.6 109.6 15.3 109.8 16.0 113.3 CH 4% LIME 6% LIME 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.5 7.5-9.0 53 27 23.1 28.1 25.6 24.5 23.2 43.0 CH 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 43 20 22.6 24.4 24.8 23.0 96.8 CL 0.0-1.5 1.5-3.0 64 1.5-3.0 59 1.5-3.0 62 3.0-4.5 4.5-6.0 63 6.0-7 · 5 63 7.5-9.0 9.0-10.5 31 9 11 33 33 29.9 32.2 28.9 30.0 29.7 34.5 33.3 89.3 92.7 MH or OH 4% LIME 6% LIME CH CH PLATE 3 MASON--JOHNSTON & ASSOCIATES, INC. OALLA$, TEXAS, m GEOLOGISTS BORING NUMBER 7 7 7 7 7 7 7 7 TOYO TIRES PARK ~EST CONNERCE CENTER COPPELL~, TEXt8 SUMIO~Y OF CL~SSZFZC~TZON TESTS DEPTH LL PI MC DUW (ft.) (%) (%) (pcf) 0.0-1.5 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.5 7.5-9.0 9.0-10.5 UNIFIED SOIL CLASSIFICATION 39 16 22.7 43 7 37 14 24.1 20.9 27.5 29.2 29.1 26.6 CL 4% LIME CL PLATE 4 MASON--JOHNSTON & ASSOCIATES, INC. DALLAS, TEXAS BORING DEPTH NUMBER (ft.) SOIL 3 6.0-7.0 TOYO TIRES P~K~EST COI(MERCE CENTER COPPELLv TEX~S SUI~Y~.RY OF STRENGTH TESTS FAILURE TANGENT Qu STRAIN MODULUS CDsi) (%) (ksi) DESCRIPTION 25 8.8 0.9 CLAY, stiff, dk. brown 1 28.7-29.1 1138 1 34.8-35.2 705 1 42.1-42.5 649 2 31.4-31.8 613 2 35.8-36.2 904 2 44.1-44.5 935 3 7.5-9.0 23 3 13.0-14.5 27 3 29.0-29.4 760 3 31.0-31.5 642 3 38.0-38.4 1010 3 41.8-42.3 559 3 50.1-50.5 853 3 55.9-56.4 265 4 28.4-28.8 836 4 30.3-30.7 989 4 39.1-39.5 1384 5 31.7-32.1 1000 5 40.2-40.7 1030 8.8 5.2 1.4 1.9 1.3 1.2 0.9 42.9 23.5 29.7 SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, sev. wea., soft to med. firm, tan SHALE, sev. wea., soft to med. firm, tan SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray SHALE, firm to mod. hd., gray 'I[NGINEER& PLATE 5 25 BORING NO:: 3 DEPTH (IT). 6.0-7.5 CLAY, stiff, dk. brown 5 (24.7,6.77) TANGENT MODULUS AT 50~ ULTIMATE STRESS: 0.93 KSI I ' ~ t I ~ ' t · 0.0 2.0 4.0 6,0 AXIAL STRAIN I I i 8.0 10.0 TEST ~YPE: UNCONFINE~ COMPRESSION TEST (ASTM 2166) MOISTURE CONTENT (=): 28.9 DRY UNIT WEIGHT (P~I~): 91.1 TOYO TIRES PARK WEST COMMERCE CENTER STRESS-STRAIN PLOT MASON-JOHNSTON & ASSOCIATES,INC. GEOLOGISTS-ENGINEeRS JOB NO.; 5771 J DATE TESTED: 2--26-91I PLATE 6 25 BORING NO.: 3 DEPTH (F-F): 7.5-9.0 SHALE, sev. we(]., soft to med. firm, i i , I i i [ I 2.0 4.0 AXial StRaIN TANGENT MODULUS AT 50~ ULTIMATE STRESS: 1.16 KSI 0 ~ I I I I ~ I I ~ i i 0.0 6.0 8.0 10.0 TEST 'FCPE: UNCONFINED COMPRESSION TEST (ASTld 2166) MOISTURE CONTENT (5): 28.6 DRY UNIT WEIGHT (P~F'): 92.7 TOYO TIRES PARK WEST COMMERCE CENTER STRESS-STRAIN PLOT MASON-JOHNSTON &: ASSOCIATES,INC. GEOLOGISTS-ENGINEE~ JOB NO.: 5771 I DATE TESTED:. 2-26-91I PLATE 7 30 ~10- 0 BORING NO.: 3 DEPTH (F-I'): 13.0-14.5 SHALE, sev..weo., soft to med. firm, ton (27.1.5.17) MODULUS AT 50~ ULTIMATE STRESS: / 0.86 KSI 1 I I I 0.0 2.5 5.0 AXIAL STRAIN (~) 7.5 TEST 'IYPE: UNCONFINED COMPRESSION TEST (ASTM 2166) MOISTURE CONTENT (~:): 25.7 DRY UNIT WEIGHT (P~IO: 95.9 TOYO TIRES =ARK WEST COMMERCE CENTER STRESS-STRAIN PLOT MASON-JOHNSTON · ASSOCIATES,INC. OEOLOGISTS-ENOINE]~S JOB NO.: 5771 PLATE 8 DATE TESTED: 2--26-91 75O _~' 5OO ~250 BORING NO.: DEPTH (..F-F): ¢1.0-31.5 SHALE, f~rm to mod' hard, gray .7.1.40) TANGENT MODULUS AT ULTIMATE STRESS: 42.9 KSl 0.0 0.5 [ I I I 1.0 AXIAL STRAIN (~) I I I I ' I 1.5 2.0 TEST 'IYPE: UNCONFINED COMPRESSION TEST (~TM 2~S) MOISTURE CONTENT (s)l: 16.6 DRY UNIT WEIGHT (Pi~l¢): 109.6 TOYO TIRES PARK WEST COMMERCE CENTER STRESS-STRAIN PLOT MASON-JOHNSTON · ASSOCIATES,INC. GEOLOGISTS-ENGINE~ JOB NO.: 5771 PLATE 9 DATE TEETED: .~-01-91 BORING NO.: ,3 DEPTH (..FI-): 41.8-42.,3 SHALE, f~rm to mod. hard, gray 600 500 _~ 400 300 ~200 1 O0 0 0.0 - ~8.=,'~ .9,,,.) TANGENT MODULUS AT 50~ ULTIMATE STRESS: ~ 2,3.5 KSI 0.5 1.0 1.5 2.0 AXIAL STRAIN (m) 2.5 TEST 'iYPE: UNCONFINED COMPRESSION TEST (ASTM 2938) MOISTURE CONTENT (~): 15.3 DRY UNIT WEIGHT (P~IO: 109.8 TOYO TIRES ~ARK WEST COMMERCE CENTER STRESS-STRAIN PLOT MASON-JOHNSTON &: ASSOCIATES,INC. GEOLOGISTS-ENGINEERS DATE TES'I~: ,~--01-91 LAT~ 10 BORING NO.: 3 DEPTH (..FT): 55,9-56.4 SHALE, f~rm to mod. hard, gray 3oo t 250 200 L~ 150 100 50 0 I ' 0.0 0.5 TANGENT MODULUS AT 50~ ULTIMATE STRESS: 29,7 KSI I ~ ~ I ~ ' ' ' I 1.0 1.5 AXIAL STRAIN (~) I I I I 2.0 TEST '[YPE: UNCONFINED COMPRESSION TEST (ASTM 29,38) MOISTURE CONTENT ('~): 16.0 DRY UNIT WEIGHT (P{~: 113.3 TOYO TIRES PARK WEST COMMERCE CENTER STRESS-STRAIN PLOT MASON-JOHNSTON &: ASSOCIATES, INC. GEOLOGISTS-ENGINEERS JOB NO.: 5771 PLATE 11 DATE TESIE~: ,.3-01-91 MOISTURE CONTENT: BEFORE (~): 29:9 .AFTER (~): UNIT DRY WEI.G.HT ~pcf): 90.8 EQUlD LIMIT (~): 50 PLASTICrTY INDEX: 22 32.9 BORING NO.: 5 DEPTH (..F~.): 1.5-3.0 CLAY, stiff, dk. brown 1.0 0.8 0.2 0.0 0 ' ' .... -I ~ ~ ' I 400 600 VERTICAL PRESSURE I 1000 TOYO TIRES PARk WEST COMMERCE CENTER PRESSURE-SWELL TEST MASON-JOHNSTON · ASSOCIATES. INC. GEOLOGISTS-ENGINE]RS JOB NO.: 5771 PLATE 12 DATE TE:S'I~): 2-25-91 MOISTURE CONTENT: BEFORE (s~): 24.:8 .AFTER (s~): 28.0 UNIT DRY WEI.G.HT ~pcf): 96,B UQUID LIMIT (~): 43 PLASTICITY INDEX: 20 BORING NO.: 5 CLAY, v ff rown 1,0 0.8 0.6 0.2 0.0 I I I 0 1 O0 200 300 400 500 VERTICAL PRESSURE (psf) TOYO TIRES PARK WEST COMMERCE CENTER PRESSURE-SWELL TEST MASON-JOHNSTON ~c ASSOCIATES,INC. GEOLOGISTS-EN~31NI~:RS JOB NO,: 5771 I DATE TESTED: 2-25-91I PLATE 13 CLASSIFICATION SYMBOLS (Soil) Asphalt Concrete Fill Gravel or Sandy Gravel GW well-graded Gravel or Sandy Gravel GP poorly-graded Silty Gravel or GM Silty Sandy Gravel Clayey Gravel or GC Clayey Sandy Gravel Sand or Gravelly Sand SW well-graded Sand or Gravelly Sand SP poorly-graded Silty Sand or SM Silty Gravelly Sand Clayey Sandy or SC Clayey GravellY Sand Silts, Sandy Silts, Gravelly ML Silts, or Diatomaceous Soils Lean Clays, Sandy Clays, CL or Gravelly Clays Organic Silts or OL Lean Organic Clays Micaceous Clays or MH Diatomaceous Soil CH Fat Clays OH Fat Organic Clays CLASSIFICATION SYMBOLS (Rock) LS. Limestone ah. Shale Marl SS. Sandstone Sltst. Slltstone Weathered Zone ABBREVIATIONS CONSISTENCIES AND HARDNESS DESCRIPTIONS abnl. abundant eng. angular arch. arenaceous erg. argillaceous bdd. bedded bdg. bedding bent. bentonite bldr. boulder calc. calcareous carb. carbonaceous cmt. cemented clst. claystone cbl. cobble cgl. conglomerate fossil, fossiliferous frac. fracture gyp. gypsiferous Incl. inclusion Intbdd. interbedded jnt. joint lam. laminated nod. nodule ccc. occasional part. particle phos. phosphatic py. pyritized Rec. Recovery rnd. rounded RQD Rock Quality Designation ~at. uturated sept. septarlan sik. siickensidod ail. siliceous wee. weathered sli. slightly mod. moderately v. very sev. severely It. light med. medium dk. dark Consistency FOR SANDS, GRAVELS, & SANDY SILTS Pe~k, Hanson & Tho~nburn (1974) Standard Penetration Consistency Resistance N Very loose Lees than 4 Loose 4-10 Medium 10-30 Dense 30-50 Very Dense Greater than 50 FOR CLAYS & SANDY CLAYS (COHESIVE SOILS) Peok, Hanson & Thornburn (1974) UNCONFINED Standard Penetration COMPRESSION tsf Resistance N Very Soft Less than 0.25 Lees than 2 Soft 0.25-0.5 2--4 Medium 0.5-1.0 4-8 Stiff 1.0-2.0 8-15 Very Stilf 2.0-4.0 15-30 Hard Greater than 4.0 Greater than 30 RELATIVE HARDNESS MODIFIERS (ROCK) (RELATED TO FRESH SAMPLE) Modified fr~m ~ E-WP. Tech. Guide No. 4 Hardness Rule of Thumb Test Soft Firm Mod. Hard BT Brazil Tensile Test dia. diameler DUW Dry Unit Weight Hard El. Bevatio~ LL Liquid Limit MC Moisture Content ME Modulus of Elasticity Very Hard min. minutes Pen. Penetrometer PI Plasticity Index Qu Unconfined Compression Test T.D. Total Depth Permits denting by moderate finger pressure. Resists denting by fingers but can be pene- trated by pencil point to medium to shallow depth. (No. 2 pencil) Very ~hallow penetration of pencil point, can be scratched by knife and In ~ome Instances cut with knife. No pencil penetration, can be scratched with knife, can be broken by light to moderate hammer blows. Cannot be ~cratched by knife, can be broken by repeated heavy hammer blows. MASON-JOHNSTON & ASSOCIATES, INC GEOLOGISTS - ENGINEERS DALI.~, TEXAS LEGEND, LITHOLOGY, SOIL CONSISTENCY, & RELATIVE ROCK HARDNESS HP, SnN-dnHNSTnN & Rssn¢., INC. I_DG nF BrlR lNG 6'E:aT£¢H~I,CnL CDNqLILTRNTS 0~ ~ ~RLLRS, 'rCXRS TOY a IRES ~ ! ar 2 PARR NEST COMMERCE CENTER PROdECT: ~71 TYPE: ~E ~(RTIDN= ~ P~N ~ CORE XNFILTRATION TEST Ii C~Y, very stiff, dark gray. X  C~Y, very stiff, dark bro~. X C~Y, very stiff, slightly sandy, X with l~estone particles, tan. 12 5 S~E, severely weat~red, soft to medium firm, tan. HRsn~-,JnHNs'rn~ ~ Fm~n¢., inc. LnG ~F ~R ~nT~CHNI~L C~LTR~5 d ~ ~L.~, ~X.~ TOY n IRES ~ 2 nr 2 PARK ~EST COHHERCE CENTER ~RTE: ~1 ~RING NB. 1 P~n~CT= ~71 TYPE~ ~E ~CR~n~= STANDARD PENETRATION (BPF) m -- ~ PDC~ PE~RDH~ER ~ ~ ~ HRTER 1 RL DESCR I PT 1 DN ~ ~ S~T.~. (SEE P~VIOUS PA~3  SHOE, slightly weathered, fi~, gray and tan. S~E~ f~rm eo ~od, ~rd~ gray. - ~.8-'-- I 18.8 18.8 _ ~.~_~- ~ ':--~ 37. O' ~" bentonitic clay b~d. - ~.5 --- - ~.8- --- I 2,, benton~e~c clay band, 18.8 - I - 47.5- HFL~ON-OOHI~TON & n~n¢., iN(:. LOG OF' BORING ~LRS, ~CXRS TOY IRES PARR WEST COMMERCE CENTER ~ou~ ~. $TANOARO PENETRATION m -- ~ ~ ~ HRTER 1 RL DESCR 1 PT 1 ON ~ ~ ~ ~ ~ ~ING X, TSr ~-- C~Y, very stiff, dark bro~. X  C~Y, very stiff, slightly sandy, X bro~. // C~y ~v. stiff ~ sli. sandT~ lt. brn ~ lt. t~.n. X _ ~.~_~ S~LE, severely weathered , soft to medium fi~, tan. - - ~.8-~ ~ S~E, sli~., med. ft~ Co f~m, gray.and tan. I, Im~ON-OOHNS'I'ON a R~-~O¢., mi, lc. LOG OF' BORING I)RLLRS, 'rEXR5 TOYO°'TiRES"= ~ 2 o? PARK ~/EST COHHERCE CENTER =Rou= o.~. 8.8 PROO£¢T: 5771 'ryP£: Q:RE tOCn~ Io.= SEE PLAN STAND&RD PE NICTRATION '~ CORE Z XNFILTRATION TEST ~ -- ~ PnCk'E'r ~ ~ ~ HRTER 1 RL I)ESCR 1 PT I BN ~ ~ I firm to firm, gray and tan. .__--_-. SHALE, firm t:o moderately hard, __ thin hard limestone lens, 18.8 18.1 - 48o8-?~. 60.2 ~" thin bent:onieic clay band. .... 40.5 ½" thin bent:onit±c clay band. 61.2 2" bentonit±e clay band. __'--- 63.5 2" benton±tic c.l. ay band. I 44.1 ½' benton±tic clay band. __ 65.5 I'~I. gh. angle fracture. DRLLRS, ZEXRS Toyoa. TIRES~" ~ I ar 3 PARK ~EST COHHERCE CENTER anau~ mm. bATE: ~1~91 ~Rl.~ ~a. 3 PRad~cT: 5771 TYP~: ~E ~cRT~o,: S~ ~ ~ MRTER 1 RL DESCR 1 PT 1 ON ~ ~ ~ ~IN~ X~ TS~ :- ~.S- . ' ' ~ ~ ,C~Y,v. stiff~sli, sacd~ w/l~eston~ . X S~E, severely weat~red, soft . ~ medium fi~, tan. 18.~-~ ~ 15.8 ~.1 ~'~- ~' ] HR.~DN-,.JDHI4STDId ,t RSSD¢., INC. LnG rlF' p~rlR lNG b"EaT£¢HNi CRL CDNS'ULTn#T; ...k"'D~ bRLLR~, TEXRq TOYU/TRES P^RK NEST CI3HHERCE CENTER GRDLINi) ELL"V. 11-11 bRTE ' 2-19-91 PRD, IECT'- 5771 TYPE: CORE LDCRTIrIN: SEE PLAN :~ (:DEE z.~,.**r.A'r,o. *r,~$*r <- ~u't -- I~ Pn eL'ET pENL"TRnHETER ~ --.J "" PIRTERIRL bE:SCRIPTIE]N c3 _.J rr- RERblI~ X. TSF' ci.. tdd ~--- .~- 1..d tdJ ,_1 ~j .... , , · · .T..,-t .~[-[ALF. ($~ P~VTOUS PAG]Z) -LT ~AT~E:wea.. med.firm.tan & ~rav. ~.-~ SHALE, firm to moderately hard, i--~ gray. - 27.5-~ 3.8 2.! - ~8.8- '--' .-.-- 32.2 ½" thin ben~onitic clay band. - 32.5---- --_-~ 33.7 ½" t~in bentonitic clay band. -_----_- 34.0 hard limestone lens. ~-* 34.3 thin bemtonittc c.lay band. - ~.S-.L~ -__--, - 37.5----- :_:-_-'5 :--, 30. ~ th..~ benton±t~tc clay band - 411.8----~ 4q.2 2½" beaCorl, iCie c.~ay h~nd. ----~__ 61.1 1" benton'tt'tc clay band. - ~.5- ~-'. -- 43.2 2" be~/tonit:£c clay band. '-' 43.0 tl~Ln benton±tie clay l. en~. - ~$.8- -- _ ~?.$.---- I, IRSON-dnHNSTOkl & RSSOC., INC. LnEi nF' BnRING bRLLRS, TI~XRS TOYO~FiRES PARK t~EST I:OHHERI:E ~ENTER ~R~: ~IHI ~ ~ N~ ~n. 3 ~d~c~: 5771 ~y~: ~E STANDARD PENETRATI~ (SPF) ~ ~ HHTER 1 RL DESCR 1 PT I ~ ~ ~INE X; T~ ~~ ~ ~ ~ ........ ~= 55.3 ~d l~esco~e - ~.5--- 5" benco~iCic clay ~TAL ~ s ~.8 - ~.8- - ~.5- - ~.8- - ~.5- . 78.8- - 72.5- HR~ON-OOHNSTON & RSSO¢., INC. lOG DF GOR I NG ~L~S, ~X~S TOY~IRES ~ I or ~ PARK ~EST COMMERCE CENTER ~ou~ ~. e.e ~= ~1 ~ ~ ~o. 4 PRDO~CT: ~71 TYP~: ~E ~CRTIDN: ~ ~ [ STANDARD PENETRATI~ (8PF) + ~ ~ HRTER 1 RE DESCR 1 PT I ON ~ ~ - wft~ l~estone particles, tan. -- 18.8-- ~ed~um f~rm~ tan. 15'8-,, ~ 1%5- ~.~- ~.5~ HFISnN-LInHNSTnN & ~SSo¢., INC. LnG nF 6DR I NG o.u..s, TEX,S TOY~"'I'IRES ~ :~ ar 2 PARK ~/EST COHHERCE CENTER r,,au~ n.~. ORTE: 2--29-91 im~ ~.~ ~n. 4 PRfldECT: 577! TYPE: ~ LnCRT I DH: SEE PLJ~ STANDARD PENETRATION (BPF) · ~ CDRE ZNFILTRATION TEST ~ "J ,,, HRTER i RL DEc;ER 1 PT I DN ,_, ~: n-- ~ P., R'["RO INI~ X, TS? ,_,_ -, § ........ ,,,"% I, Ltl jLrl I,t !, "%' ~ I I I I I m m ~ $.F,_A~'F,,, severely weat~erecl., soft to ~-~ medium f~rm. tan. _-~ SHALE, slightly weathered, firm, ~-_ gray and tan. - '-- SHALE, firm to moderately hard, .__~ [ gray. - a$.$- ------ 15.$ 1~.~ - ~.~-~| 3a.a t~ benton~tic clay lens. ~-~-~.~_-: 33.1 thin bentonitic clay lens. _ ~.8_''-~ ! ,~_-:. 35.8 th~_n bentonitic clay lens. - 1t'/.5--- - ~8. B---~ 60.5 thin bent:on£t'tc clay lens. -._~_' '--- 62.5 th.~. benton±t£c clay lens. 18.8 - ~..5---= -- 62.7 2~" bentonitic clay band. ,, ,~..-- - 45.B-~-' I I 46.3 2½" bent:onitic clay band. - 47.5- ---~ TOTAL DEFTH ' 47.5 Iql:~rtN-dUHNBTnN & RSSnC., INC. LOG DF BEIR I NG ~.LL.S, ~Ex~s TOY~IRES ~ I ar ~ PARK ~EST COMMERCE CENTER. a.au~ ~. ~.~ ORTE: ~91 ~ ~a. S PRDdECT: ~71 TYPE: ~E ~CRT~a,: S~ ~ z ~ ~ HRTER i RL DESCR 1 PT 1 ~N ~ ~ ~ IN~ X~ TS~ ~~ ~ ~ ~ ........ ~,~ C~Y, very st~f, dark bro~. X x - ~.S'  C~Y, very st~f, bro~. X - 5.9- x 12.5'~ HRSON-dOHNSTDN I, fl~O¢., INC. LOG OF' BOR I NG ORLLRS, TEXR5 TOYu~ [RES PARK WEST COMMERCE CENTER PROdECT: ~71 ~ye~: ~E ~C~T~o~: S~ P~ STANDARD PENETRATI~ ~ C~ ZNFILTRATION TEST ~ ~ ~ HRTEE I RL DES~R i PT I DN ~ ~ ~ ~ ~  S~LE, severely w~t~ered, soft to  medium fi~, tan. - ~.5 *= ~ S~E, slightly weathered, medi~ ~ fi~, gray and tan. - ~.~-~ --- S~E, fi~ to moderately ~rd, ~ gray. - ~.5-~ __ 35.9 e~ beneon~tfc clay lens. 37.6 e~ beneon~e~e clay lens. - ~.5-'-' r~ 39.2 ~" th~ bentonttic clay lens. _ ~.8_~ 39.9 ~" t~ bentonltic clay lens. __7~ 40.4 1" bentonitic clay band. ----- 40.5 1" bentonitic clay band. - ~.5- -- -:~ 1o.o - ~.~- i~ __--- t~ ben:onitfc clay lens. -~ 45.9 th~ ~rd l~estone b~d. - 47.5---' ~OTECHNI~L CON~LTRNTS d ~ ORLLRS, 1EXRS TOY o IRES ~ t or t PARK ~EST COMMERCE CENTER ~ROU~ ~. e.e STANDARD PENETRATI~ (BPF) · ~ HRTER I RL DESCR ! PT I ON ~ ~ m ~IN~ X~ ~ ~,.,~ ~1~1 ~ ~ ~ ........ ~ ~1~1 ~ ~ = , , , , , , , ,  C~Y, ve~ sti~, da~k b~. X X - ~.5- C~ very st~ff, brom. ~ S~E, severely weathered, soft - to medium firm, tan. - 7.5 - ~2.5- - ~5.8- - ~7.5- - ~.8- - ~.5- aRSna-dn~sTn~ ~ R~nc., ~C. LnG DF EnRING I)RLLFIr;, 1EXR5 TOYI~I' I RES sm~'T tnr t PARK WEST COMMERCE CENTER ~.au.~ ~L~. ~Od£CT: 5771 TYPe: SOIL LUCRT~O,: ~EE PLAN STANDARD PENETRATION (BPF) tn -- ~ PflCL'k~ PENL'"rRI~ETER :~ c~-J '".~ HRTER I RL I)ESCR I PT 1 DH k-cc~t~~1~ R~'1t01 ~ X, TSr CLAY, very sttff, da~k bro~a.. X - :~.5 '~ -- 5.8--~ CLAY, stiff, tan. X  SHALE, severely weathered, soft to , ~ medium firm, tan. '- 1.5- - 18.8- 'ffil~l. ~ ~ 18.8 - 17o§- - ~.8-