Loading...
Park West CC(17)-LR001017 TS1T 2502 Gravel Drive - Ft. Worth, TX 76118 817-589-9933 Date: October 17, 2000 Report of Built- Up Roof Inspection PROJECT: Park West ITl Phase II Coppell, TX GENERAL CONTRACTOR: McFadden Miller, Inc. CONTACT: limmie Laxen 214-808-4953 ROOFING CONTRACTOR: HEC 4815 Grema - Dallas, Tx 75356 ROOFD~G FOREMAN: Robert Morris 214-638-5970 MANR.rFACTORER: Johns Manville - Type III Asphalt - 4 ply with aggregate ballast Technical Information WEATHER CONDITIONS: Sunny AMBIENT TEM. PERATURES: 65 to 78 FORECAST FOR NEXT DAY: Same SIZE OF CREW 10 TIME: NA ROOFING M. ATERLALS RECEIVED? No LABELS ATTACHED? Yes MATERIALS STORED AS REQUIRED? Yes MATERI. ALS REJECTED? No SPECIFITD TEMPERATURES: (Asphalt) Kettle: 500 + 25 degrees F. EVT (Application): 450 +25 degrees F. Kettle: 11:15 am- 500 EVT: 11:45 am-450 DECK INSPECWED? Yes .... cRICKETS INSTALLED? Yes Location: .North east wall between-drains - iow area -- AREA OF ROOF APPLICATION: Northeast corner wall - to north expansion joint Number of SQ's (SF X 100) placed this date: approximately 80 SQ Was placement per specifications: Yes OPERATIONS INSPECTED: Inspection this date at the above referenced project revealed Application along the east wall, a low area no sloped, as is the remainder of the deck was cricketed to the drains. Insulation application was as required. One layer staggered, mechanically attached fesco ( 8 fasteners per 4' X 8' area) Felt application had not begun The area of application included 7 skylights and 4 drain areas. Advised GC that the panel lift bolts needed to be fdled with grout, prior to roo£mg. Technician: I. Halverson/W'illiams Time: 4 hours Chad McEntee