ST9301-CS 990908 TXU TXU Electric 1506 Commerce Street Dallas, TX 75201 September 8, 1999 Mr. Ken Griffin, P.E. Director of Engineering and Public Works City of Coppell 255 Parkway Blvd. P. O. Box 478 Coppell, Texas 75019 RE: Difference in Cost for Circuit Crossing on Sandy Lake Rd. east of MacArthur Per our recent conversation, I have prepared an estimate for the difference in cost for the circuit crossing on Sandy Lake Road east of MacArthur. The difference between overhead construction and underground construction is $15,484.00. This price does not include a spare 6" pvc sleeve, as TXU Electric & Gas will cover that cost. Relocation of the TXU Electric & Gas facilities for the Sandy Lake Road expansion are being coordinated with a project to add system capacity to the Coppell area and will start late this fall. If you have any questions please give me a call at ( 214 ) 812-7310. Thanks. Sincerely, Bobby Inmon Engineering Analyst East Design Engineering Dept. TXU Electric & Gas