ST9302-CS010914FAX (214) 352-3201 TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220
September 14, 2001
Mr. Ke~meth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re: Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Horn Project #: 06940600
DWU Project #: 98-311F
Dear Mr. Griffin:
It is our understanding that a traffic pull box, 4" conduit, and existing wire needs to be relocated
at the Denton Tap and Sandy Lake intersection to accommodate construction of the remainder of
the concrete pavement at that intersection. Our lump sum price for this work is $2,875.00. This
price excludes any new wire or traffic loops. Please add two days to the contract duration for
this extra work.
If you have any questions regarding this information, don't hesitate to contact our office.
]lBincerely'
ell ~on~i~ction Company
Project Manager
xc: Michael G. DeMotte, Kimley-Horn and Associates, Inc., 801 Cherry Street, Suite 1100
Fort Worth, Texas 76102-6803
AN EQUAL OPPORTUNITY EMPLOYER