MA FY 00/01-CS010402 April 2, 2001
Miguel Guzman
Nova Construction Co., Inc.
10514 Wire Way
Dallas, Texas 75220
RE: Reinforced Concrete Pavement Repair Project # ST 01-01
Dear Mr. Guzman:
This letter will serve as your official notice to begin work on the referenced project. For purposes
of the contract, your calendar days will start ten days fi.om the date on this letter. This is a project
funded from current year budget; therefore the project should be completed no later than September
30, 2001.
If you have any questions feel free to call Garreth Campbell, the inspector on this project, at (972)
304-3685.
Sincerely,
Kenneth M. Griffin, P.E.
Director of Engineering/Public works
cc: Garreth Campbell, Construction Inspector