SC-CFBISD Riverchase-LR 990914FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
CLIENT:
PROJECT:
GENERAL REPORT
Carrollton-Farmers Branch lSD, c/o DaI-Mac Const. REPORT DATE: September 14, 1999
Riverchase Elementary School, Coppell, Texas PROJECT NO: 0791-2184
DAILY ACTIVITY REPORT: August 17, 1999
Services Performed:
Weather Conditions:
Contractors on Site:
Visual Inspection
Sunny / Hot
Dalmac / Berkel
Remarks: On this date, a representative of Fugro South, Inc. was present on the above mentioned project
to perform the following tests and observations as requested:
· Started at 1:00 p.m.
· Production: 3 Auger cast piles, sonic logging to be completed next day.
· Total Piles to date: 3
Nabil Mikhail
Fugro South Project Engineer
SMH/bg
Distribution:
FUGRO SOUTH, INC.
David A. Belcher, P.E.
Sr. Project Manager
DaI-Mac Construction - Jason Lillard
DaI-Mac Construction - Nate Payne
City of Coppell - Larry Davis
City of Coppell - Lee Stone
SHW Group - Joe Craddock
SHW Group - Terry Hoyle
Carrollton - Farmers Branch lSD - Tom Bell
"FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
CLIENT:
PROJECT:
COMPRESSIVE STRENGTH OF GROUT CUBES
Carrollton-Farmers Branch lSD, cio DaI-Mac Const. Report Date: September 14, 1999
Riverchase Elementary School, Coppell, Texas Project No.: 0791-2184
SAMPLE DATE: August 17, 1999
General Contractor:
Method of Test:
Sample Location:
Time Batched:
Results I Remarks:
DaI-Mac Construction / Berkel
ASTM C-109
Pile B-51
1:28 p.m.
Type 9000-B
Time Sampled: 3:35 p.m.
SAMPLE AGE 'DATE AREA APPLIED COMPRESSIVE REQUIRED
NUMBER TESTED LOAD STRENGTH STRENGTH
(days) (sq. in.) (lbs.) (psi) (psi/days)
REC 9 3 8-20-99 4.0 17650 4413 4000128
REC 10 3 8-20-99 4.0 17430 4358
REC 11 7 8-24-99 4.0 21134 5285
REC 12 7 8-24-99 4.0 21154 5289
REC 13 28 9-14-99 4.0 23750 5938
REC 14 28 9-14-99 4.0 23680 5920
REC 15 Hold 4.0
REC 16 Hold 4.0
REC 17 Hold 4.0
Remarks:
Michael Overstreet
Fugro South Technician
FUGRO SOUTH INC.
SMH/rm
Distribution:
Reviewed By: ~ --
II
DaI-Mac Construction - Jason Lillard DaI-Mac Construction - Nate Payne
City of Coppell - Larry Davis / City of Coppell - Lee Stone
SHW Group - Joe Craddock SHW Group - Terry Hoyle
Carrollton - Farmers Branch lSD - Tom Bell
-- IGLOO
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972)484-8301; Fax (972) 620-7328
CLIENT:
PROJECT:
GENERAL REPORT
Carroilton-Farmers Branch lSD, c/o DaI-Mac Const. REPORT DATE: September 14, 1999
Riverchase Elementary School, Coppell, Texas PROJECT NO: 0791-2184
DAILY ACTIVITY REPORT: September 7, 1999
Services Performed: visual Inspection
Weather Conditions: Sunny/Hot
Contractors on Site: DaI-Mac I Berkel
Remarks: On this date, a representative of Fugro South, Inc. was present on the above mentioned project
to perform the following tests and observations as requested:
· Production: 16 piles
· Total number of piles to date: 155 piles
· Two sets of grout cubes from Pile C-92A
· Sonic PVC: C-86, C-92a, A-47, C-87
· No major problems
Nabil Mikhail
Fugro South Project Engineer
FUGRO SOUTH, INC.
David A. Belcher, P.E.
Senior Project Manager
SMH/bg
Distribution:
DaI-Mac Construction - Jason Lillard
DaI-Mac Construction - Nate Payne
City of Coppell - Larry Davis
City of Coppell - Lee Stone
SHW Group - Joe Craddock
SHW Group - Terry Hoyle
Carrollton - Farmers Branch lSD - Tom Bell
FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
GENERAL REPORT
Carroilton-Farmers Branch lSD, c/o DaI-Mac COnst. REPORT DATE: September 14, 1999
Riverchase Elementary School, Coppeli, Texas PROJECT NO: 0791-2184
DAILY ACTIVITY REPORT: September 8, 1999
Services Performed:
Weather Conditions:
Contractom on Site:
visual Inspection
Cloudy
Dalmac / Berkel
Remarks: On this date, a representative of Fugro South, Inc. was present on the above mentioned project
to perform the following tests and observations as requested:
* Production: 23 piles
* Total number of piles to date: 178 piles
* Two sets of cubes from Piles D174, D175, D176 were cast
* Two piles were added next to A46 (A46a, 4 feet to the east and A46b, 4 feet to the west)
* A-46 a drilled to 65 feet
* A-46 b drilled to 65 feet
* Sonic PVC: C-93, C-94
* Tim Roberts doing the Sonic Tests.
Note: Todays drilling completes the Auger ClP piles.
Nabil Mikhail
Fugro South Engineer
SMH/bg
Distribution:
FUGRO SOUTH INC.
David A. Belcher, P.E.
Sr. Project Manager
Dal-Mac Construction - Jason Lillard
DaI-Mac Construction - Nate Payne
City of Coppell - Larry Davis
City of Coppell - Lee Stone
SHW Group - Joe Craddock
SHW Group - Terry Hoyle
Carrollton - Farmers Branch lSD - Tom Bell
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
CLIENT:
PROJECT:
OBSERVATION OF CONCRETE PLACEMENT
Carrollton-Farmers Branch lSD, c/o DaI-Mac Const. REPORT DATE: September 14, 1999
Riverchase Elementary School, Coppell, Texas PROJECT NO: 0791-2184
DATE PERFORMED: September 10, 1999
General Contractor: DaI-Mac
Method of Test:
Applicable ACI Recommendations and ASTM Standards
Results / Remarks:
Concrete placement observation was performed at the Building D and Building B Grade Beams
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range (°F):
Strength required (psi/days):
Number of cylinders made:
Superplasticizer used:
8:30 a,m.
10:55 p.m.
40
4.5 to 5
5
Pioneer / Plant No. 27
85 - 90°F
3000/28
4
No
William Granger
Fugro South Technician
FUGRO SOUTH, INC.
SMH/bg
Distribution:
Reviewed By:
DaI-Mac Construction - Jason Lillard
DaI-Mac Construction - Nate Payne
City of Coppell - Larry Davis
City of Coppell - Lee Stone
SHW Group o Joe Craddock
SHW Group - Terry Hoyle
Carrollton - Farmers Branch lSD - Tom Bell