SC-Coppell HS-LR000310FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal- Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: March 1, 2000
CONTRACTOR: Cortez Group
TICKET NO.: 7084067
AMBIENT TEMP. (°F): 61
CONCRETE TEMP. (°F) (ASTM C-1064): 80
TIME BATCHED: 10:41
TIME SAMPLED: 11:15
WEATHER CONDITION: Clear
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: , 7-757
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 4.7
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C.'143): 4 -1/2
Slab Area B-2 5 feet South 30 feet East
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 680 7 3-8-00 88000 3110 3000/28 days
CHC 681 28 3-29-00
CHC 682 28 3-29-00
CHC 683 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Types°f [~] ~] [~1E]
Cudng: Methods: ASTM C-39 Fracture: A B C D
REMARKS:
Technician:
SMH/mm
Distribution:
Thomas Cranford
Reviewed By: ~
FUGRO SOUTH INC.
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal- Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: March 1, 2000
CONTRACTOR: Cortez Group
TICKET NO.: 7084063
AMBIENT TEMP. (°F): 60
CONCRETE TEMP. (°F) (ASTM C-1064): 80
TIME BATCHED: 10:08
TIME SAMPLED: _ 10:35
WEATHER CONDITION: Warm
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7-958
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 4.7
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C-'143): 4 -3/4
Slab Area B-2 15 feet South 25 feet East
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 676 7 3-8-00 84000 2970 3000/28 days
CHC 677 28 3-29-00
CHC 678 28 3-29-00
CHC 679 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Types°f [~ ~] [~D
Cudng: Methods: ASTM C-39 Fracture: A B C D
REMARKS:
Technician: Thomas Cranford
SMH/mm
Distribution:
FUGRO SOUTH INC.
Reviewed By: ~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project NO.: 0791-2208
Coppell, Texas
SAMPLE DATE: March 1, 2000
CONTRACTOR: Cortez Group
TICKET NO.: 7084058
AMBIENT TEMP. (°F): 60
CONCRETE TEMP. (°F) (ASTM C.'1064): 80
TIME BATCHED: 9:40
TIME SAMPLED: 10:25
WEATHER CONDITION: Warm
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7-706
MIX ID NUMBER: 16
AIR (%) (ASTM C-231) .' 4.6
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C-143): 5
Slab - Area B3 10 feet South 15 feet East
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 672 7 3-8-00 83000 2940 3000/28 days
CHC 673 28 3-29-00
CHC 674 28 3-29-00
CHC 675 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof ~?~ m ~--/1 r-]
Curing: Methods: ASTM C-39 Fracture: AI(....~ V~l VI I lB C D
REMARKS:
Technician:
SMH/mm
Distribution:
Thomas Cranford
FUGRO SOUTH INC.
Reviewed By: ~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: March 1, 2000
CONTRACTOR: Cortez Group
TICKET NO.: 708470
AMBIENT TEMP. (°F): 63
CONCRETE TEMP. (°F) (ASTM C-t064): 81
TIME BATCHED: 11:07
TIME SAMPLED: 11:45
WEATHER CONDITION: Warm
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7-959
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 4.5
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C-143): 5
Slab Area B-2 3 feet South 40 feet East
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 684 7 3-8-00 101000 3570 3000/28 days
CHC 685 28 3-29-00
CHC 686 28 3-29-00
CHC 687 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof J~;;;l r-~--i r-~ [~j
Curing: Methods: ASTM C-39 Fracture: AY..~l V~ VI I lB C D
REMARKS:
Technician: Thomas Cranford
FUGRO SOUTH INC.
SMH/mm
Distribution:
Reviewed By:
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: March 1, 2000
CONTRACTOR: Cortez Group
TICKET NO.: 7084052
AMBIENT TEMP. (°F): 57
CONCRETE TEMP. (°F) (ASTM C-1064): 81
TIME BATCHED: 9:20
TIME SAMPLED: 10:15
WEATHER CONDITION: Clear
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7-757
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 4.7
WATER ADDED (gal):
SLUMP (in.) (ASTM C-143): 4
Slab 5 feet East - 4 feet South Area B - 3
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 668 7 3-8-00 81000 2870 3000/28 days
CHC 669 28 3-29-00
CHC 670 28 3-29-00
CHC 671 Hold
Fracture mode is (A) unless otherwise noted
Making & ASTM C-31 Testing ASTM C-143, Typesof r~ ['~ r-~ ~
Specifications:
Cudng: Methods: ASTM C-39 Fracture: AI~1 Y_.~l Y._l L.JB C D
REMARKS:
Technician:
SMH/mm
Distribution:
Thomas Cranford
FUGRO SOUTH INC.
Reviewed By: ~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike EImore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: March 1, 2000
CONTRACTOR: Cortez Group
TICKET NO.: 3100253
AMBIENT TEMP. (°F): 66
CONCRETE TEMP. (°F) (ASTM C-1064): 82
TIME BATCHED: 1:07
TIME SAMPLED: 2:00
WEATHER CONDITION: Warm
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 3-1059
MIX ID NUMBER: 16
AIR (%) (ASTM C-23'1): 4.6
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C-143): 5
Slab Area B-1 9 feet East 10 feet South
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 692 7 3-8-00 82000 2900 3000/28 days
CHC 693 28 3-29-00
CHC 694 28 3-29-00
CHC 695 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof ~] [~ ~ E~]
Cudng: Methods: ASTM C-39 Fracture: A B C D
REMARKS:
Technician: Thomas Cranford
FUGRO SOUTH INC.
SMH/mm
Distribution'
Reviewed By: ~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT:
PROJECT:
Coppell lSD, c/o Dal - Mac Construction Co.
Coppell High School, Multi Purpose Building
Coppell, Texas
Report Date: March 10, 2000
Project No.: 0791-2208
SAMPLE DATE: March 1, 2000
CONTRACTOR:
TICKET NO.:
AMBIENT TEMP. (°F):
CONCRETE TEMP. (°F) (ASTM C-t084):
TIME BATCHED:
TIME SAMPLED:
WEATHER CONDITION:
LOCATION OF PLACEMENT:
Cortez Group
3100244
65
87
12:20
12:55
Warm
Slab Area B 1
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 3-956
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 4.8
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C-143): 4 1/2
6 feet East 7 feet South
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 688 7 3-8-00 98000 3470 3000/28 days
CHC 689 28 3-29-00
CHC 690 28 3-29-00
CHC 691 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof r~ r-j-] r~ r-]
Cudng: Methods: ASTM C-39 Fracture: AVq VXI VI I lB C D
REMARKS:
Technician:
SMH/mm
Distribution:
Thomas Cranford
FUGRO SOUTH INC.
Reviewed By: ~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) §20-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT:
PROJECT:
Coppell lSD, c/o Dal - Mac Construction Co.
Coppell High School, Multi Purpose Building
Coppell, Texas
Report Date: March 10,2000
Project No.: 0791-2208
SAMPLE DATE: March 1, 2000
CONTRACTOR:
TICKET NO.: 3100257
AMBIENT TEMP. (°F): 67
CONCRETE TEMP. (°F) (ASTM C-t064): 82
TIME BATCHED: 1:20
TIME SAMPLED: 1:50
WEATHER CONDITION: Warm
LOCATION OF PLACEMENT: Slab Area B-1
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 3-1064
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 4.6
WATER ADDED (gal): 10
SLUMP (in.) (ASTM C.143): 5
6 feet South - 15 feet East
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 696 7 3-8-00 84000 2970 3000/28 days
CHC 697 28 3-29-00
CHC 698 28 3-29-00
CHC 699 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM 0-31 Testing ASTM C-143, Typesof ~:1 ~1]'] [-'/I F-']
curing: Methods: ASTM C-39 Fracture: AVq VXI VI lIB C D
REMARKS:
Technician: Thomas Cranford
FUGRO SOUTH INC.
SMH/mm
Distribution:
Reviewed By:~.-.--------~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Vi~go Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, cio Dal- Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Multi Purpose Building Project NO.: 0791-2208
Coppell, Texas
SAMPLE DATE: February 10, 2000
CONTRACTOR: Cortez
TICKET NO.: 83218
AMBIENT TEMP. (°F): 58
CONCRETE TEMP. (°F) (ASTM C-'1064): 75
TIME BATCHED: 4:35
TIME SAMPLED: 5:10
WEATHER CONDITION:
LOCATION OF PLACEMENT:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7/757
MIX ID NUMBER: 16
AIR (%) (ASTM C-231):
WATER ADDED (gal): 5
Partly cloudy SLUMP (in.) (ASTM C-143): 4.75
Lower half of Area C at southwest corner Multi Purpose Building slab
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 596 7 02/17/00 89000 3150 3000/28 days .
CHC 597 28 03/09/00 120000 4250
CHC 598 28 03/09/00 122000 4320
CHC 599 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof ~1 [T~ r-~ r--~
Cudng: Methods: ASTM C-39 Fracture: AY..~l V',I VI I lB C D
REMARKS:
Technician:
SMH/bg
Distribution:
David Putman
FUGRO SOUTH INC.
Reviewed By: ~ !
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike EImore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
Coppell lSD, c/o Dal- Mac Construction Co. Report Date: March 10, 2000
Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: February 10, 2000
CONTRACTOR:
TICKET NO.:
AMBIENT TEMP. (°F):
CONCRETE TEMP. (°F) (ASTM C.1064):
TIME BATCHED:
TIME SAMPLED:
WEATHER CONDITION:
LOCATION OF PLACEMENT:
Cortez Group
83214
63
73
4:00
4:45
Partly cloudy
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7/1045
MIX ID NUMBER: 10
AIR (%) (ASTM C-231):
WATER ADDED (gal): 8
SLUMP (in.) (ASTM C-143): 4.5
Lower half of Area C, 40 feet east, 75 feet south from northwest corner
Multi Purpose Building slab
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 592 7 02/17/00 87000 3080 3000/28 days
CHC 593 28 03/09/00 115000 4070
CHC 594 28 03/09/00 112000 3960
CHC 595 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof ~] ~ ~D
Cudng: Methods: ASTM C-39 Fracture: A B C D
REMARKS:
Technician:
SMH/bg
Distribution:
David Putman
FUGRO SOUTH INC.
Reviewed By: ~ ·
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike EImore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: March 10, 2000
PROJECT: Coppell High School, Stadium Expansion Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: February 9, 2000
CONTRACTOR:
TICKET NO.:
AMBIENT TEMP. (°F):
CONCRETE TEMP. (°F) (ASTM C-1064):
TIME BATCHED:
TIME SAMPLED:
WEATHER CONDITION:
LOCATION OF PLACEMENT:
Dal Mac / Cortez Group
3899O34
72.1
66.1
4:16 pm
4:56 pm
P/C & Windy
Piers:
CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 3/972
MIX ID NUMBER: 16
AIR (%) (ASTM C-231): 3
WATER ADDED (gal): 0
SLUMP (in.) (ASTM C-143): 5
B.3/3.5, B/3.5, Ail
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 580 7 02/16/00 96000 3400 3000/28 days
CHC 581 28 03/08/00 102000 3600
CHC 582 28 03/08/00 104000 3680
CHC 583 Hold
Fracture mode is (A) unless other,vise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof ~1 r'~ ~! r--]
Cudng: Methods: ASTM C-39 Fracture: AV'd V~ VI I lB C D
REMARKS:
Technician: Phillip Forrest
SMH/bg
Distribution:
FUGRO SOUTH INC.
Reviewed By: ~
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
Coppell lSD, c/o Dal- Mac Construction Co. Report Date: March 10, 2000
Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
SAMPLE DATE: February 10, 2000
CONTRACTOR:
TICKET NO.:
AMBIENT TEMP. (°F):
CONCRETE TEMP. (°F) (ASTM C.1064):
TIME BATCHED:
TIME SAMPLED:
WEATHER CONDITION:
LOCATION OF PLACEMENT:
62
74
3:33
4:10
Partly cloudy
Cortez Group, Inc.
83210 CONCRETE SUPPLIER: Lattimore
PLANT/TRUCK: 7/757
MIX ID NUMBER: 16
AIR (%) (ASTM C-23'1):
WATER ADDED (gal): 5
SLUMP (in.) (ASTM C-143): 5
Lower half of Area C, 5 feet east 30 feet south from northwest corner
Multi Purpose Building slab
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard 6" x 12", 28.27 square inches
TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE
CYLINDER AGE DATE LOAD STRENGTH STRENGTH
NUMBER (days) TESTED (pounds) (psi) (psi)
CHC 588 7 02/17/00 93000 3290 3000/28 days
CHC 589 28 03/09/00 130000 4600
CHC 590 28 03/09/00 127000 4490
CHC 591 Hold
Fracture mode is (A) unless otherwise noted
Specifications: Making & ASTM C-31 Testing ASTM C-143, Typesof ~] ~ ~ ~
Curing: Methods: ASTM C-39 Fracture: A B C D
REMARKS:
Technician: David Putman
FUGRO SOUTH INC.
SMH/bg
Distribution:
Reviewed By:
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Wiiliford