SC-Coppell HS-LR000621FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
NON - COMPLIANCE REPORT
CLIENT: Coppell lSD c/o DaI-Mac Construction Co. DATE: June 21, 2000
PROJECT: Coppell High School, High School Expansion PROJECT NO: 0791-2208
REPORT NO: 16 PAGE 2
Number Description Location Deviate Corrective Action Taken
From
1 Item deleted. In Compliance
2 Item deleted. In Compliance
3 Relocated beam due to Higher roof grid Drawings Welded beam connection angles at
brick wall. Bolts not EA & ED @ E1 3 places to beam web (Need RFI)
1/14/00 installed in connection
beam to beam web
4 1 1/4 pipe supports under Foundation, 2nd Drawings
grand stairway not level
2/1/00 installed
5 Mislocation of bolt holes. Elevation
Required number of bolts
2/1/00 not installed. Beam to
beam connection 2 bolts
not installed
6 Grind welds on T.S. to Elevation 106-11
T.S. splice on stringer
2/1/00
NOTE: Architect and Engineer should advise on acceptability of all noted deviations
Inspected By: Doug Post, AWS/Certified Welding Inspector, ASNT/Certified Level 2 (UT. MT)
STR-1