SC-Coppell HS-LR000201FUGRO SOUTH, INC. ~ 2880 Virgo Lane; Dallas. Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 STRUCTURAL STEEL INSPECTION REPORT CLIENT: Coppell lSD c/o DaI-Mac Construction Co. DATE: February 1, 2000 PROJECT: Coppell High School, High School Expansion PROJECT NO: 0791-2208 REPORT NO: 14 PAGE 1 Owner: Coppell lSD Architect: SHW Group Engineer: SHW Group Contractor: DaI-Mac Construction Co. Fabricator: Alpha Industries Location of Project: Coppell, Texas Inspection Performed At: Job Site X Fabrication Shop DESCRIPTION OF INSPEC11ON: Structural Steel Inspection } Visual Inspection of Welds on (Str I Steel - Metal Deck Units) or Ultrasonic Testing or Magnetic Particle Inspection of Welds and Inspection of Bolted Connections for compliance to Project specifications, Contract Documents, Drawings, and Governing Codes } AWS, AISC, ASTM, SJI, ASNT, ANSI. See attached Field Reoort~ for Sgeciflc Items Inel;~ected or Tested and Tyee of Inal~ection or Testino I~erforme~l Location of Inspection: See attached Field reports for Specific Areas Inspected or Tested. Results of Inspection: Project Complete Project Incomplete Fabrication Is: Erection Is: X In Compliance Non Compliance X Note: Workmanship t~pe deviations noted during Inspection, whictt are being corrected at time of Inspection. are not being listed on Report. NOTE: Inspection was performed to verify compliance to Project specificeltons. Contract Documents, Drawings. and Governing Codes} AWS. AISC. ASTM. SJL. ASNT. ANSI Inspected By: Doug Post, AWSICerlJfled Welding Inspector, ASNT/Certified Level 2 (UT. MT) Distribution: DaI-Mac Construction - Damo~0,Horman City of Coppell - Larry Davis ~ Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike Elmore Doug Post STR-1 sou ., 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484.8301; Fax (972) 620-7528 NON - COMPLIANCE REPORT CLIENT: Coppell lSD c/o DaI-Mac Construction Co. DATE: February 1, 2000 PROJECT: Coppell High School, High School Expansion PROJECT NO: 0791-2208 REPORT NO: 14 PAGE 2 Number Description Location Deviate Corrective Action Taken From 1 Item deleted. In Compliance 2 Item deleted. In Compliance 3 Relocated beam due to Higher roof grid Drawings Welded beam connection angles at brick wall. Bolts not EA & ED @ E1 3 places to beam web (Need RFI) 1/14/00 installed in connection beam to beam web 4 1 1/4 pipe supports under Foundation, 2nd Drawings grand stairway not level 2/1/00 installed 5 Mislocation of bolt holes. Elevation Required number of bolts 2/1/00 not installed. Beam to beam connection 2 bolts not installed 6 Grind welds on T.S. to Elevation 106-11 T.S. splice on stringer 2/1/00 NOTE: Architect and Engineer should advise on acceptability of all noted deviations Inspected By: Doug Post, AWSICertified Welding Inspector, ASNT/Certified Level 2 (UT, MT) STR-1 FUGRO SOUTH, INC. ,!~0 ~ ,.jne: Oaltaa. Texa~ ?S229 FIELD ERECTION - MEMBERS INSPECTED or TESTED CLIENT: . DATE: ~~ ~ ~ ~ . PROJECT NO: PROJE~: ~ .EPORT.O: __t~~ ~~ ~t~.'~.__ PAGE N~ Ty. ~ In.~on I Lo.. I In I Compl,~c. ~ f~ ~ Me~e~ .... ~~ -- ~ ~ Villi Q~ of W~S on P~ ~ ~ S~ ~ W~ ~ S~ Cne~ Si~ Qf w~ ~ ~ I ~f ~ ~e~ Size of wel~ ~ Shear Ul~s~lc Testing of W~ds Mag Pa~e ~e~ng of we~es Repo~ ~and ~tten at ~me of ~n Oy F;eld I~pector ~ ~ ~x · In ~pllan~ Insoected By: Ooug Post, AW~Ce~fle{ wel~l~ Ins~r, ASNT/Ce~8~ Level 2 (UT, STR.2