SC-Coppell HS-LR 991229FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 752.29
Ph (972) 484-8301; Fax (972) 620-7328
OBSERVATION OF CONCRETE PLACEMENT
CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: December 29, 1999
PROJECT: Coppell High School, Multi Purpose Building Project No.: 0791-2208
Coppell, Texas
DATE PERFORMED: December 23, 1999 I
General Contractor: DaI-Mac
Method of Test: Applicable ACl Recommendations and ASTM Standards
Results I Remarks:
Concrete placement observation was performed at the High Iow grade beam between weight room and multi-
following location: purpose building - Grade beam Grid J1-J11 - Multi-
Purpose Building
Time placement began: 12:24
Time placement ended: 4:30
Total cubic yards placed: 120
Slump range (inches): 4.5 - 5,0
Slump required (inches): 5.0
Concrete supplier and plant: Lattimore
Concrete temperature range (°F): 64 - 66°F
Strength required (psi/days): 3000/28
Number of cylinders made: 8
Superplasticizer used: No
William Granger
Fugro South Technician
FUGRO SOUTH, INC.
Reviewed By:
SMH/bg
Distribution: DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford