SC-Coppell HS-LR 991221FUGRO SOUTH, INC, 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 FIELD DENSITY REPORT CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. REPORT DATE: December 21, 1999 PROJECT: Coppell High School, High School Expansion, Coppell, Texas PROJECT NO: 0791-2208 DATE PERFORMED: December 16, 1999 Density Test Method: ASTM 0-2922 & 3017 Method of Compaction: ASTM D-698 MOISTURE/DENSITY RELATIONS Material Proctor Results Number Description Maximum Dry Density (pcf) Optimum Moisture (%) 1 Dark gray clay with some gravel 107.4 17.0 TEST RESULTS TEST PROCTOR LOCATION UNIT DRY MOISTURE PERCENT OF NO, ~O. WEIGHT CONTENT PERCENT MAXIMUM DENSITY 66 I Electrical Line, west side of Area "A", 2 102.7 18.5 95.6 feet below grade 67 I Electrial Line, between fire lane and 104.3 17.9 97.1 junction box, 2 feet below grade 68 I Electrical Line, from junction box to multi- 103.2 18.3 96.1 purpose building, 2 feet below grade Remarks: All densities meet project specifications unless otherwise noted. William Granger Fugro South Technician FUGRO SOUTH INC. Reviewed By: {~'~. ~-.,,-----~ SMH/bg Distribution: DaI-Mac Construction - Damo/n Norman City of Coppell - Larry Davis / Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike Elmore JRJ Paving - Jeff Williford FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 STRUCTURAL STEEL INSPECTION REPORT CLIENT: Coppell lSD c/o DaI-Mac Construction Co. DATE: December 21, 1999 PROJECT: Coppell High School, High School Expansion PROJECT NO: 0791-2208 REPORT NO: 10 PAGE 1 Owner: Coppell lSD Architect: SHW Group Engineer: SHW Group Contractor: DaI-Mac Construction Co. Fabricator: Alpha Industries Location of Project: Coppeil, Texas Inspection Performed At: Job Site X Fabrication Shop DESCRIPTION OF INSPECTION: Structural Steel Inspection } Visual Inspection of Welds on (Str I Steel - Metal Deck Units) or Ultrasonic Testing or Magnetic Particle Inspection of Welds and Inspection of Bolted Connections for compliance to Project specifications, Contract Documents, Drawings, and Governing Codes } AWS, AISC, ASTM, SJI, ASNT, ANSI. See attached Field Reoorts for Soecific Items Insoected or Tested and Tvoe of Inspection or Teetina performed Location of Inspection: See attached Field reports for Specific Areas Inspected or Tested. Results of Inspection: . Project Complete Project Incomplete I Fabrication Is: I Erection Is: In Compliance i X Non Compliance Note: Workmanship type deviations noted dudng Inspection. which are being corrected at time of Inspection. are not being listed on Report. NOTE: Inspection was performed to verify compliance to Project specifications. Contract Documents. Drawings. and Governing Codes} AWS. AISC. ASTM. SJL. ASNT, ANSi Inspected By: Doug Post, AWS/Certified Welding Inspector, ASNT/Certified Level 2 (UT, MT) Distribution: DaI-Mac Construction - Damon Norman City of Coppell - Larry Davis Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike Elmore JRJ Paving - Jeff Williford Doug Post STR-1 FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas. Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 NON - COMPLIANCE REPORT CLIENT: Coppell lSD c/o DaI-Mac Construction Co. DATE: December 21, 1999 PROJECT: Coppell High School, High School Expansion PROJECT NO: 0791-2208 REPORT NO: 10 PAGE 2 Number Description Location Deviate Corrective Action Taken From 1 Mislocation of bolt holes Area A, 2nd level Drawings Beam connection, angles have on beam to column been welded @ (3) places to 11/9/99 connection, bolts could AM @ AS, A6 column flange. (No RFI) not be installed 2 Mislocation of anchor Area H G 10 @ Drawings Corrections have been made per bolts on column base GH, attachment C RFI III, except bolt spacing was 11/18/99 plate on RFI III moved 1 1/2 wider due to rebar in C.I.P floor. Depth of holes are in compliance. New RFI has been submittec ~y DaI-Mac showing a change in bolt pattern width. ! NOTE: Architect and Engineer should advise on acceptability of all noted deviations Inspected By: Doug Post, AWS/Certified Welding Inspector. ASNT/Certified Level 2 (UT. MT) STR-I FUGRO :SOUTH, INC. 2880 Virgo Lane; Dallas. Texas 75229 Ph (972) 484-8301; Fax (97:2) 620.7328 FIELD ERECTION - MEMBERS INSPECTED or TESTED CLIENT: ~.~ ~,tor-_! } ~% ~."3 DATE: PROJECT: ~.~,/.:,:;r;i ~ ~. ~_~..'-~.~=i PROJECT NO! REPORT NO: ' '/Z) PAGE -.~ OF Of Inspection I location In I Non Type Coml31iance. Compliance Chec~ s~ze and Proiecaon of Anchor Bolt ] Check Ancl~or Bolt Group I Check Nuts on Anchor Bolts I Tight Check .=_reckon Procedures Check ,'~ Damaged Members Check Welders Qualification Records of Welded Connections Check FibUp Visual Quality of Welds on Joists / Girders J Visual Quality of Welds on Misc Steel Visual Quality of Welds on Pre Cast Connection visual Quali~/of Welds on Coml3oSite Deck Visual Qualit'./of Welds on Roof Deck Visual Qualib/of Welds on Shear Studs Check Size of Welds on Structural Steel Check Size of Welds on Jo~sts / Girders Check Size of Welds on Misc Steel C.heck Size of Welds on Pre Cast Connection C~ec~ S~ze of weics on Composite / C~eck Size cf We!ds on Shear Studs Mag: ;3a~icle Testing c~ Welds .~ecc.-. '~anc~ ,,,n[ten at ',i."ne of :nsl3ec~on by Field Insl3ectcr ~' ~n ~ox = In co...nplianca ~eco.'1. /till =e $,~b ,~.~[ted as is and not typed X in box =Ncn cor~pl[ance ~, See 'qcn Ir.s;ected ~7: Dou~ Post. Aws,'Ce~ifiec welding :ns'-ec:or. ASNT/Ce~i.r'.ec ',.-3ve~ 2 ~',J- ~,I-) FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas. Texas 75229 Ph (972) 484-8301; Fax (972} 620-7328 FIELD ERECTION - MEMBERS INSPECTED or TESTED CLIENT: ~-~C~FII \ %~ : DATE: PROJECT: C~b~_!l t-~,C~?- ~.._~ PROJECT NO: ~?~/-,,~,~' REPORT NO: /~P PAGE z/z' OF "/ Type of Inspection Location In Non · Compliance Compliance ChecX Bolt Tightening Procedure Check Connection for Required Size of Bolts ~.I'~ I C...,.~. ~ ~t"5-1~ Check Connection for Require¢l No. of Bolts , i Check Bolt Tightness with Torque Wrench Visual Inspection of Tension Conb-ol Bolts / Bearing Bolted Connections I Snug Tight Check Bolted Connection / Turn of Nut Check Gap on Loaded Indicator Washers Check Size. Length. and No. of Shear Studs Check Gauge of Composite Deck Check Gauge of Roof Oeck Check Size Lap Connection on Coml~osite Deck Check Size Lap on Roof Deck Check Installation of Sriclging on Joists I Gi~ers : Check Installation of Expansion Anchors -',~.~,' Check Grout I Repot. hand written at time of inspection by Field Inspector ~' in box = In compliance Report will he submitted as is and not typed X in box = Non compliance } See Non compliance report, Inspected By: Doug Post, AWSiCemfied Welding Inspector. ASNT/Cer~jfied Level :2 ' ~' (U ,. MT) FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 DRILLED PIER OBSERVATION REPORT CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: December 21, 1999 PROJECT: Coppell High School, High School Expansion, Coppell, Texas Project No.: 0791-2208 DRILLING CONTRACTOR: Street Foundation Page 1 DATE PERFORMED: December 17, 1999 I Location: Drilled Piers Depth I Shaft to Plan Actual Total Pier Diameter Bearing Penetra- Penetra- Depth Proper Water Casing Number in. Material tion ff. tion ff. ft. Alignment Present(~ Used Remarks ff. 132 18 6.5 6.0 6.1 12.6 Yes Yes Yes 143 18 6.0 10.0 10.2 16.2 Yes Yes Yes 140 18 6.0 10.0 10.0 16.0 Yes Yes Yes 134 18 6.5 10.0 10.1 16.6 Yes Yes Yes 131 18 6.5 7.0 7.2 13.7 Yes Yes Yes 135 18 7.0 9.0 9.0 16.0 Yes No No 136 18 8.0 8.0 8.1 16.1 Yes Yes Yes 25 24 7.0 9.0 9.0 16.0 Yes Yes Yes Reinforcing steel checked in all piers and found to be in accordance with project requirements, unless otherwise noted. Bearing Material: Gray Shale (~) During drilling operations; however, piers were dry prior to placement of concrete. Thomas Cranford Fugro Technician FUGRO SOUTH INC. Reviewed By: '"'~. ~ SMH/bg Distribution: DaI-Mac Construction- Damon Norman , City of Coppell - Larry Davis Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike Elmore JRJ Paving - Jeff Williford