SC-Coppell HS-LR000705FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo lane; Dall~, Texas 75229
Ph (9;'2) 464-~01; Fax (972) 620-7328
OBSERVATION OF CONCRETE PLACEMENT
Coppell lSD, c/o Dal - Mac Construction Co. Report Date: July 5, 2000
Coppell High School, Tennis Court/Parking Lot Project No..' 0791-2208
Coppell, Texas
DATE PERFORMED: June 28, 2000
General Contractor: The Cortez Group
Method of Test:
Applicable ACI Recommendations and ASTM Standards
Results / Remarks:
Concrete placement observation was performed at the Paving for Tennis Court
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range (°F):
Strength required (psi/days):.
Number of cylinders made:
Superplasticizer used:
8:00 a.m.
3:00 p.m.
200
3.0 - 5.0
5.0
Lattimore - Plant No. 3
87 - 91°F
3000/28
8
No
Sammy Roberts
Fugro South Technician
FUGRO SOUTH, INC.
SMH/bg
Distribution:
Reviewed By:
DaI-Mac Construction - Damon Norman
City of Coppell - Lee Stone
City of Coppell - Larry Davis -~
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo {.~ne; 0~11~, Tex~ ;'5229
Ph (972) 484-8301; Fax (972) 620-7328
OBSERVATION OF CONCRETE PLACEMENT
Coppell lSD, c/o Dal - Mac Construction Co.
Coppell High School, Tennis Court/Parking Lot
Coppell, Texas
Report Date: July 5, 2000
Project No.: 0791-2208
DATE PERFORMED: June 29, 2000
General Contractor: Cortez Group
Method of Test:
Applicable ACI Recommendations and ASTM Standards
Results I Remarks:
Concrete placement observation was performed at the Paving lot for Tennis Court
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range (°F):
Strength required (psi/days):.
Number of cylinders made:
Superplasticizer used:
6:30 a,m,
1:00 p,m,
4O0
5,0
3,0
5,0
90 - 85°F
3000/28
16
No
Sammy Roberts
Fugro South Technician
FUGRO SOUTH, INC.
SMH/bg
Distribution:
Reviewed By:
DaI-Mac Construction - Damon Norman
City of Coppell - Lee Stone
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford