Loading...
SC-Coppell HS-LR000612FUGRO SOUTH, INC. CLIENT: PROJECT: 2880 Virgo Lane; Dallas. Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 OBSERVATION OF CONCRETE PLACEMENT Coppell lSD, c/o Dal- Mac Construction Co. Report Date: June 12, 2000 Coppell High School, Stadium Expansion Project NO.: 0791-2208 Coppell, Texas DATE PERFORMED: June 9, 2000 General Contractor: The Cortez Group Method of Test: Applicable ACI Recommendations and ASTM Standards Results I Remarks: Concrete placement observation was performed at the following location: Time placement began: Time placement ended: Total cubic yards placed: Slump range (inches): Slump required (inches): Concrete supplier and plant: Concrete temperature range (°F): Strength required (psi/days): Number of cylinders made: Superplasticizer used: Retaining wall at north end - west half 11:10 a.m. 12:15 p.m. 30 5-314 - 6-1/2 3.0 - 5.0 Lattimore - Plant No. 7 86 - 87°F 4000/28 4 No Yancey Bivings Fugro South Technician FUGRO SOUTH, INC. SMH/bg Distribution: Reviewed By: DaI-Mac Construction - Damon Norman City of Coppell - Lee Stone City of Coppell - Larry Davis Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike EImore JRJ Paving - Jeff Williford FUGRO SOUTH, INC. CLIENT: PROJECT: 2880 virgo Lane; Dallas, Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 OBSERVATION OF CONCRETE PLACEMENT Coppell lSD, c/o Dal - Mac Construction Co. Report Date: June 12, 2000 Coppell High School, Stadium Expansion Project No,: 0791-2208 Coppell, Texas DATE PERFORMED: June 8, 2000 General Contractor: The Cortez Group Method of Test: Applicable ACI Recommendations and ASTM Standards Results I Remarks: Concrete placement observation was performed at the following location: Time placement began: Time placement ended: Total cubic yards placed: Slump range (inches): Slump required (inches): Concrete supplier and plant: Concrete temperature range (°F): Strength required (psi/days):. Number of cylinders made: Superplasticizer used: Retaining wall at east half of north end 12:40 p.m. 3:10 p.m. 4O 5.0 - 6-1/4 3.0 - 5.0 Lattimore - Plant No. 7 85 - 89°F 4000/28 4 No Yancey Bivings Fugro South Technician FUGRO SOUTH, INC. SMH/bg Distribution: Reviewed By: DaI-Mac Construction - Damon Norman City of Coppell - Lee Stone City of Coppell - Larry Davis Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike EImore JRJ Paving - Jeff Williford FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas, Texas 7~ Ph (972)484-8301; Fax (972) 620.7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT: Coppell lSD, c/o Dal - Mac Construction Co. Report Date: June 12, 2000 PROJECT: Coppell High School, Stadium Expansion Project No.: 0791-2208 Coppell, Texas SAMPLE DATE: June 1, 2000 CONTRACTOR: Cortez Group TICKET NO.: 3105692 AMBIENT TEMP. (°F): 84 CONCRETE TEMP. (°F) (ASTM C-1064): 89 TIME BATCHED: 9:35 TIME SAMPLED: 10:45 WEATHER CONDITION: Warm LOCATION OF PLACEMENT: CONCRETE SUPPLIER: Lattimore PLANT/TRUCK: 3/01093 MIX ID NUMBER: 42 AIR (%) (ASTM C-231): 4.9 WATER ADDED (gal): 10 SLUMP (in.) (ASTM C-143): 5 Columns at stadium, column #138 to #148 Press box CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS Standard 6" x 12", 28.27 square inches TOTAL COMPRESSIVE SPECIFIED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CHC 1222 7 06/08/00 92400 3270 4000/28 days CHC 1223 28 06/29/00 CHC 1224 28 06/29/00 CHC 1225 Hold Fracture mode is (A) unless otherwise noted Specifications: Making & ASTM C-31 Testing ASTM C-143, Types°f ~] [~ [~1 E] Curing: Methods: ASTM C-39 Fracture: A B C D REMARKS: Technician: SMH/rm Distribution: Thomas Cranford FUGRO SOUTH INC. Reviewed By: DaI-Mac Construction - Damon Norman City of Coppell - Lee Stone City of Coppell - Larry Davis Coppell lSD - Mickey Harper SHW Group - Joe Craddock SHW Group - Mike Elmore JRJ Paving - Jeff Williford