SC-Coppell HS-LR000429FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texa~ 75229
Ph (972) 4848301; Fax (972) 820-7328
CLIENT:
PROJECT:
OBSERVATION OF CONCRETE PLACEMENT
Coppell lSD, c/o Dal - Mac Construction Co. Report Date: April 29, 2000
Coppell High School, Stadium Expansion Project NO.: 0791-2208
Coppell, Texas
DATE PERFORMED: April 25, 2000
General Contractor: DaI-Mac
Method of Test:
Applicable ACl Recommendations and ASTM Standards
Results I Remarks:
Concrete placement observation was performed at the
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range (°F):
Strength required (psi/days):
Number of cylinders made:
Superplasticizer used:
Stadium - Slab on Grade - Bathroom A-111 and
Mechanical Room A-111
10:00 a.m.
12:30 p.m.
5.0 - 5-1/4
5±1
Lattimore - Plant No. 14
75 - 80°F
3000/28
4
No
Mike Flute
Fugro South Technician
FUGRO SOUTH, INC.
SMH/bg
Distribution:
Reviewed By: '~'~-
DaI-Mac Construction - Damon Norman
City of Coppell - Lee Stone
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford