SC-Coppell HS-LR000413FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
OBSERVATION OF CONCRETE PLACEMENT
Coppell lSD, cio Dal - Mac Construction Co. Report Date: April 13, 2000
Coppell High School, Stadium Expansion Project No.: 0791-2208
Coppell, Texas
DATE PERFORMED: April 10, 2000
General Contractor: DaI-Mac
Method of Test:
Applicable ACl Recommendations and ASTM Standards
Results / Remarks:
Concrete placement observation was performed at the
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range (°F):
Strength required (psi/days):
Number of cylinders made:
Superplasticizer used:
Bleachers for Stadium - Second level of beams and
columns for bleachers
1:30 p.m.
5:30 p.m.
130
7.5 to 4.5
5.0
Lattimore - Plant No. 7
63 - 71°F
4000/28
16
No
Yancey Divings
Fugro South Technician
FUGRO SOUTH, INC.
SMH/bg
Distribution:
Reviewed By:
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford