SC-Coppell HS-LR000328FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
GENERAL REPORT
Coppell lSD, c/o Dal - Mac Construction Co.
Coppell High School, Stadium Expansion
Coppell, Texas
Report Date: March 28, 200
Project No.: 0791-2208
DAILY ACTIVITY REPORT: March 27, 2000
Services Performed:
Weather Conditions:
Contractors on Site:
Visual Inspection
Clear
DaI-Mac
Remarks: On this date, a representative of Fugro South, Inc. was present on the above mentioned project
to perform the following tests and observations as requested:
Observed concrete placement and cast one set of four concrete test cylinders to represent placement of
concrete on this date.
Mark Strittmatter
Fugro South Technician
SMH/bg
Distribution:
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Eirnore
JRJ Paving - Jeff Williford
FUGRO SOUTH, INC.
Sr. Project Manager
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
CLIENT:
PROJECT:
COMPRESSIVE STRENGTH OF MORTAR CUBES
Coppell lSD, c/o Dal - Mac Construction Co.
Coppell High School, Tennis Court/Parking Lot
Coppell, Texas
Report Date: March 28, 2000
Project No.: 0791-2208
SAMPLE DATE: February 28, 2000
Contractor:
Method of Test:
Sample Location:
Time Batched:
Results I Remarks:
Dal Mac
ASTM C-109
Area E
Type S
Time Sampled:
SAMPLE . AGE DATE AREA APPLIED COMPRESSIVE REQUIRED
NUMBER TESTED LOAD STRENGTH STRENGTH
(days) (sq. in.) (lbs.) {psi) . .
CHC 13 7 03/06/00 4.0 4260 1070 1800/28
CHC 14 7 03~06~00 4.0 3850 960
CHC 15 7 03/06/00 4.0 4120 1030
CHC 16 28 03/27/00 4.0 7840 1960
CHC 17 28 03/27/00 4.0 7990 2000
CHC 18 28 03/27/00 4.0 7230 1810
Remarks:
Ambient temperature 62°
Mortar temperature 74°
Thomas Cranford
Technician
FUGRO SOUTH INC.
SMH/rm
Distribution:
DaI-Mac Construction - Damon Norman
· City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford
Reviewed By: __~'"~
FUGRO SOUTH, INC.
CLIENT:
PROJECT:
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
OBSERVATION OF CONCRETE PLACEMENT
Coppell lSD, c/o Dal- Mac Construction Co.
Coppell High School, Stadium Expansion
Coppell, Texas
Report Date: March 28, 2000
Project No.: 0791-2208
DATE PERFORMED: March 27, 2000
General Contractor: DaI-Mac
Method of Test:
Applicable ACI Recommendations and ASTM Standards
Results I Remarks:
Concrete placement observation was performed at the
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range (°F):
Strength required (psi/days):
Number of cylinders made:
Superplasticizer used:
Columns: Level I Stadium Columns: A/20, A/21, A/22,
Ag23, A/24, B/20, B/21, B/22, B/23, B/24, C/20, C/21,
C/22, D/20, D/21, D/22
2:00 p.m.
4:30 p.m.
38
4.0 to 5.0
5.0
Lattimore - Plant No. 7
74 - 76°F
4000/28
4
No
Mark Strittmatter
Fugro South Technician
FUGRO SOUTH, INC.
SMH/bg
Distribution:
Reviewed By:
DaI-Mac Construction - Damon Norman
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Group - Joe Craddock
SHW Group - Mike Elmore
JRJ Paving - Jeff Williford