Loading...
SC-Coppell MSN-CS 961210 ENGINEERING Client: ¢opoell I.$.D. Pase: I of 1 Project: Coooell Middle School North Date: December 10. 1996 I.S.D. 24-foot Fire Lane./28-foot Public St. By: R. Howman ENGINEER'S COST PROJECTION Item. I Description I Quantity l Unit I Pr'ce I I 6-inch Lime Stabilized Subgrade 2725 SY 2.50 6,813 2 6-inch Reinforced Concrete Pavement 2510 SY 18.50 46,435 w/o Crown (24-ft back-to-back) 3 Concrete Curb 1730 LF 1 .S0 2,.595 5 lO-foot Curb Inlet 6 Striping 1 LS S u~:,,,~.,:..~,, I 10% Co nti n..'z~.~m 1 6-inch Lime Stabilized Subgrade 3175 SY 2.50 7,938 2 6-inch Reinforced Concrete Pavement 2950 SY 20.00 59,000 w/Crown (28-ft back-to-back) 3 l Concrete Curb I 1730 I LF I 1.S0 I 2,SgS'-- 4 18-inch Class III RCP 300 LF 22.50 6,750 5 Curb Inlet 2 Ea. 2,500.00 5,000 6 Striping 1 LS 2,500 2,500 Subtotal 83,783 I I I 10% ContinMency I 8,400 ] I I T'otal I $92,183 Glenn Engineering Corporation 1042 Decker Court, Suite 250 Irving, Texas 75062-2206 972.717.5151 FAX 972.719.4229 D~c-IO-B6 01: lOP Glenr~ngineering 972~719-4P29 P,02 GLENN ENGINEERING Client: Coopell I.S.D./Vista Properties Page: I of 1 Project: Coppell Middle School Date: December 10, 1996 Vista Properties Sectk)n By: R. Howman ENGINEER'S COST PROIECTION Description I quantity I O-it I Price I Amount &inch Lime Stabilizecl Sub-grade 1760 SY 2.50 4,400 7-inch Thick Reinforced Concrete Pavement 1580 SY 25.00 39,500 Concrete Curb 960 LF 1.50 1,440 Asphalt Transition into Denton Tap Rd 1 LS 15,000.00 15,000 w/10:1 Side Taper Traffic Control 1 LS ._ 2.,_5..0__0..00 2,500 I Striping ) ~ I LS t 2,500.001 2,500 18-inch Class III RCP I 200 I LF I ~22.$0 I 4,500 lO-foot Curb Inlets 2 Ea. 2,500.00 5,500 Erosion Control 350 LF 1.50 525 Subtotal 61,865 10% Contingency 6,200 Total $68,065 Glenn Engineering Corporation 100 Decker Court, Suite 250 Irvins, Texas 75062-2206 972.7 ! 7.51S 1 FAX 972.719.4229 Dee-lO-g6 01: lOP glenn,--EngineeY'ing 972-.=,719-4229 P.O~ ENGINEERING Client: Coppell I.S.D./Vista Properties Page: I of 1 Project: Coooell Middle School North Date: December 10, 1996 Copoell I.S.D. Section By: R. Howman ENGINEER'S COST PROIECTION Description I Quantfty I ~nit t Price I ~mlOU.t 6-inch Lime Stabilized Sub-grade 6080 SY 2.50 15,200 7-inch Thick Reinforced Concrete Pavement 5752 SY 25.00 143,800 Concrete Curb 2930 LF 1.50 4,395 24-inch Class RCP 600 I LF [ 32.50[ 19,200 36-inch Class III RCP 400 LF 45.00 18,000 Standard lO-foot Curb Inlet 8 Ea. 2,500 20,000 Erosion Control 1500 LF 1.50 1,500 Striping 1 LS 5000 5000 Subtotal 233,845 10% Contingency 23,400 I I Total $257,245 Gle.. Engln#rlng ¢ofpofatlo~t 100 E~cker Court, Suite 250 Irving,, Texas 7.5062-2206 972.71 ?.5151 FAX 972.719.4229