SC-Coppell MSN-CS 961210 ENGINEERING
Client: ¢opoell I.$.D. Pase: I of 1
Project: Coooell Middle School North Date: December 10. 1996
I.S.D. 24-foot Fire Lane./28-foot Public St. By: R. Howman
ENGINEER'S COST PROJECTION
Item. I Description I Quantity l Unit I Pr'ce I
I 6-inch Lime Stabilized Subgrade 2725 SY 2.50 6,813
2 6-inch Reinforced Concrete Pavement 2510 SY 18.50 46,435
w/o Crown (24-ft back-to-back)
3 Concrete Curb 1730 LF 1 .S0 2,.595
5 lO-foot Curb Inlet
6 Striping 1 LS
S u~:,,,~.,:..~,, I
10% Co nti n..'z~.~m
1 6-inch Lime Stabilized Subgrade 3175 SY 2.50 7,938
2 6-inch Reinforced Concrete Pavement 2950 SY 20.00 59,000
w/Crown (28-ft back-to-back)
3 l Concrete Curb I 1730 I LF I 1.S0 I 2,SgS'--
4 18-inch Class III RCP 300 LF 22.50 6,750
5 Curb Inlet 2 Ea. 2,500.00 5,000
6 Striping 1 LS 2,500 2,500
Subtotal 83,783
I I I 10% ContinMency I 8,400
] I I T'otal I $92,183
Glenn Engineering Corporation
1042 Decker Court, Suite 250
Irving, Texas 75062-2206
972.717.5151 FAX 972.719.4229
D~c-IO-B6 01: lOP Glenr~ngineering 972~719-4P29 P,02
GLENN
ENGINEERING
Client: Coopell I.S.D./Vista Properties Page: I of 1
Project: Coppell Middle School Date: December 10, 1996
Vista Properties Sectk)n By: R. Howman
ENGINEER'S COST PROIECTION
Description I quantity I O-it I Price I Amount
&inch Lime Stabilizecl Sub-grade 1760 SY 2.50 4,400
7-inch Thick Reinforced Concrete Pavement 1580 SY 25.00 39,500
Concrete Curb 960 LF 1.50 1,440
Asphalt Transition into Denton Tap Rd 1 LS 15,000.00 15,000
w/10:1 Side Taper
Traffic Control 1 LS ._ 2.,_5..0__0..00 2,500
I Striping ) ~ I LS t 2,500.001 2,500
18-inch Class III RCP I 200 I LF I ~22.$0 I 4,500
lO-foot Curb Inlets 2 Ea. 2,500.00 5,500
Erosion Control 350 LF 1.50 525
Subtotal 61,865
10% Contingency 6,200
Total $68,065
Glenn Engineering Corporation
100 Decker Court, Suite 250
Irvins, Texas 75062-2206
972.7 ! 7.51S 1 FAX 972.719.4229
Dee-lO-g6 01: lOP glenn,--EngineeY'ing 972-.=,719-4229 P.O~
ENGINEERING
Client: Coppell I.S.D./Vista Properties Page: I of 1
Project: Coooell Middle School North Date: December 10, 1996
Copoell I.S.D. Section By: R. Howman
ENGINEER'S COST PROIECTION
Description I Quantfty I ~nit t Price I ~mlOU.t
6-inch Lime Stabilized Sub-grade 6080 SY 2.50 15,200
7-inch Thick Reinforced Concrete Pavement 5752 SY 25.00 143,800
Concrete Curb 2930 LF 1.50 4,395
24-inch Class RCP 600 I LF [ 32.50[ 19,200
36-inch Class III RCP 400 LF 45.00 18,000
Standard lO-foot Curb Inlet 8 Ea. 2,500 20,000
Erosion Control 1500 LF 1.50 1,500
Striping 1 LS 5000 5000
Subtotal 233,845
10% Contingency 23,400
I I Total $257,245
Gle.. Engln#rlng ¢ofpofatlo~t
100 E~cker Court, Suite 250
Irving,, Texas 7.5062-2206
972.71 ?.5151 FAX 972.719.4229