SC-Coppell MSW-LR001109 FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 620-7328
DRILLED BELLED PIER OBSERVATION REPORT
CLIENT: Coppell lSD, c/o K A Sparks REPORT DATE: November 9, 2000
PROJECT: Coppell Middle School West, Coppell, Texas PROJECT NO: 0700-2227
DRILLING CONTRACTOR: North Texas Drilling Page 1
DATE PERFORMED: October 4, 2000
LOCATION: Concession & Restroom Building - Baseball & Softball Fields
Pier Required Required Total Depth, Proper Water Remarks
Number Shaft Bell ft. Alignment
Diameter, in. Diameter, in. Present
A-1 24 48 10.1 Yes No
A-2 30 66 10.6 Yes No
A-3 30 66 10.4 Yes N o
A-4 30 66 10.5 Yes No
A-5 24 48 10.5 Yes No
A.7-6 18 36 10.1 Yes No
B-1 30 66 10.0 Yes No
B-2 30 66 10.3 Yes No
B-3 30 66 10.3 Yes No
B-4 30 66 10.1 Yes No
B-5 30 66 10.9 Yes No
B.4-6 18 36 10.1 Yes No
C- 1 24 48 10.2 Yes No
C-2 30 60 10.5 Yes No
C-3 30 60 11.8 Yes No
C-4 24 54 10.0 Yes No
C-5 24 48 11.5 Yes No
Reinforcing steel checked in all piers and found to be in accordance with project requirements, unless
otherwise noted.
Bearing Material: Tan gray shaley clay
Phillip Forrest
Fugro Technician FUGRO SOUTH INC.
Reviewed By:
SMH/bg
Distribution: K A Sparks Contractors Inc. - Jim Schooler SHW Group - Mike Elmore
K A Sparks Contractors Inc. - Rick McKinney (Fax: 972-745-4511) City of Copp(~ll - Lee Stone
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Goup - Joe Craddock
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484-8301; Fax (972) 820-7328
DRILLED PIER OBSERVATION REPORT
CLIENT: Coppell lSD, c/o K A Sparks REPORT DATE: November 9, 2000
PROJECT: Coppell Middle School West, Coppell, Texas PROJECT NO: 0700-2227
DRILLING CONTRACTOR: North Texas Drilling Page 1
DATE PERFORMED: October 4, 2000
Location: East Parking Lot - Light Poles
Depth
Shaft to Plan Actual Total
Pier Diameter Bearing Penetra- Penetra- Depth Proper Water Casing
Number in. Material tion ft. tion ft. ft. Alignment Present Used Remarks
ft.
1-N 24 11.0 - 11.0 Yes No No
2-N 24 11.2 - 11.2 Yes No No
3-N 24 10.8 - 10.8 Yes No No
4-N 24 10.3 - 10.3 Yes No No
5-N 24 10.3 - 10.3 Yes No No
Reinforcing steel checked in all piers and found to be in accordance with project requirements, unless
otherwise noted.
Bearing Material: Tan gray shaley clay
Phillip Forrest
Fugro Technician FUGRO SOUTH INC.
Reviewed By: "~- '~___~,~
SMH/bg
Distribution: K A Sparks Contractors Inc. - Jim Schooler
K A Sparks Contractors Inc. - Rick McKinney (Fax: 972-745-4511 )
City of Coppell - Lee Stone
City of Coppell - Larry Davis
Coppell lSD - Mickey Harper
SHW Goup - Mike Elmore
SHW Goup - Joe Craddock