SC-Mockingbird E4-CS 910823August23,1991
Mr. Larry Davis
City of Coppell
Engineering Department
P. O. Box 478
Coppell, Texas 75019
RE: Mockingbird Elementary School
Dear Larry:
Enclosed is a copy of the letter which has been issued to the contractor for the work at
the drainage swale on the north end of the school site. Sparks contractor has indicated
to me that this work will be completed within the next two weeks.
One other item left to complete is the grouting of the storm drainage concrete pipe con-
nection to the concrete headwall at this same swale. This concrete work will be done at
the same time as the concrete work in the drainage swale.
Should you have any questions, please do not hesitate to call.
Sincerely,
SHWC, Inc.
MichaelL. Elmore
Senior Associate
ME/kc
Enclosure
August 16, 1991
Mr. Jim Schooler
K. A. Sparks Contractor, Inc.
Box 869
Hamilton, TX 76531
RE: Coppei; Ei,~bentary
Mockingbird Elementary
Dear Jim:
I am writing this letter to confirm that it is the responsibility of K. A. Sparks Contractor to
clean and regrade the drainage swale along the north property line of all excess sedi-
ments that have occurred during the construction of the new elementary. I realize that
this swale was cut at the very beginning of the project, but this area was not turned over
to the Owner by substantial completion. Therefore, the responsibility of the swale
remains with K. A. Sparks Contractor. Please have this swale cleaned out and the con-
crete rip-rap installed as soon as possible so the certificate of occupancy can be ex-
ecuted for this project.
Should you have any questions, please do not hesitate to call.
Sincerely,
SHWC, Inc.
Michael L. Elmore
Senior Associate
ME/kc