Loading...
SC-Wilson E5-CS 920625 PU~CHLIST FOR COPPELL #§/WILSI ELEMt~ 6/25/92 ~, The punchlist for Coppell #5 Ele~nentar¥/Wilson Elementary should completed as follows: 1) Paint ML Blue caps Fl{ Red 2) Hydrant by vaults bound leaking 3) MLV - North reset stack and pad 4) MLV - South reset stack and pad 5) M.H. by school reset ring c/o bottom grout 6) M.H. in back regrout c/o bottom & line 7) Grade around Fire Vault needs to be properly set to prevent extrusion from ground or vault needs to be lowered 8) Clean and patch concrete paving in drives and parking area 9) Repair damaged sidewalk 10] Seal saw joints 11) Complete all saw joints 12) Provide maintenance bond 13) Provide "As-Built" plans 14) Clean and grade channel next to Coppell Road to drain 15) Seal asphalt to concrete 16) Compact around headwalls 17) Random crack in south drive apron (ear) 18) Seal headwall to drive 19) Delineators to distinguish between drive and headwall. 20) Establish ditch and erosion control along Coppell Road If v~u hav~~uestions please feel free to call me. Construction Inspector 06/25/92 10:~? COPPELL PUBLIC WORKS 002 ¢oPpeT,L pU~I',ZC~ WOI~KI~ TO: Larry Davis, Construction Inspector~ FROM: Ray Gonzales, Street Superintendent~]~ RE~ Walk Thru - Wilson Elementary/Coppe11 ~5 The following is a list of discrepancies found at this job site. Please make sure that the contractor is provided a copy of this list. Random crack mn S. drive apron (ear). · ~ompact around headwalls. · ~sal headwall to drive. · Delineators to distinguish between drive and headwall. · Establish ditch and erosion control along Coppell Road. If you have any questions please let me know. RG/bo STWTWiLSON.RG PUNCHLIST FOR COPPELL #5/WILSON ELEMENTARY The punchlist for Coppell #5 Elementary/Wilson Elementary should be completed as follows: 1) Paint ML Blue caps FI{ Red 2) Hydrant by vaults bound leaking 3) MLV - North reset stack and pad 4) MLV - South reset stack and pad 5) M.H. by school reset rinG c/o bottom Grout 6) M.H. in back reGrout c/o bottom & line 7) Grade around Fire Vault needs to be properly set to prevent extrusion from Ground or vault needs to be lowered 8) Clean and patch concrete paving in drives and parking area 9) Repair damaged sidewalk 10) Seal saw joints 11) Complete all saw joints 12) Provide maintenance bond 13) Provide "As-Built" plans 14) Clean and Grade channel next to Coppell Road to drain If you h~y questions, please feel free to call me. ,_b~rr¥ Davis ~3z~-~ £~.~ Construction Inspector CLD/bd COPPPUN