SC-Wilson E5-CS 920625 PU~CHLIST FOR COPPELL #§/WILSI ELEMt~
6/25/92 ~,
The punchlist for Coppell #5 Ele~nentar¥/Wilson Elementary should
completed as follows:
1) Paint ML Blue caps
Fl{ Red
2) Hydrant by vaults bound leaking
3) MLV - North reset stack and pad
4) MLV - South reset stack and pad
5) M.H. by school reset ring c/o bottom grout
6) M.H. in back regrout c/o bottom & line
7) Grade around Fire Vault needs to be properly set to prevent extrusion
from ground or vault needs to be lowered
8) Clean and patch concrete paving in drives and parking area
9) Repair damaged sidewalk
10] Seal saw joints
11) Complete all saw joints
12) Provide maintenance bond
13) Provide "As-Built" plans
14) Clean and grade channel next to Coppell Road to drain
15) Seal asphalt to concrete
16) Compact around headwalls
17) Random crack in south drive apron (ear)
18) Seal headwall to drive
19) Delineators to distinguish between drive and headwall.
20) Establish ditch and erosion control along Coppell Road
If v~u hav~~uestions please feel free to call me.
Construction Inspector
06/25/92 10:~? COPPELL PUBLIC WORKS 002
¢oPpeT,L pU~I',ZC~ WOI~KI~
TO: Larry Davis, Construction Inspector~
FROM: Ray Gonzales, Street Superintendent~]~
RE~ Walk Thru - Wilson Elementary/Coppe11 ~5
The following is a list of discrepancies found at this job site.
Please make sure that the contractor is provided a copy of this
list.
Random crack mn S. drive apron (ear).
· ~ompact around headwalls.
· ~sal headwall to drive.
· Delineators to distinguish between drive and headwall.
· Establish ditch and erosion control along Coppell Road.
If you have any questions please let me know.
RG/bo
STWTWiLSON.RG
PUNCHLIST FOR COPPELL #5/WILSON ELEMENTARY
The punchlist for Coppell #5 Elementary/Wilson Elementary should be
completed as follows:
1) Paint ML Blue caps
FI{ Red
2) Hydrant by vaults bound leaking
3) MLV - North reset stack and pad
4) MLV - South reset stack and pad
5) M.H. by school reset rinG c/o bottom Grout
6) M.H. in back reGrout c/o bottom & line
7) Grade around Fire Vault needs to be properly set to prevent extrusion
from Ground or vault needs to be lowered
8) Clean and patch concrete paving in drives and parking area
9) Repair damaged sidewalk
10) Seal saw joints
11) Complete all saw joints
12) Provide maintenance bond
13) Provide "As-Built" plans
14) Clean and Grade channel next to Coppell Road to drain
If you h~y questions, please feel free to call me.