FIELD COMPACTION REPORT
PROJECT: The Sonic Addition LOCATION: Coppell
JOB #: 94-1171 DATE: 07-08-94 DAY: Friday TIME: 12 noon
CLIENT: Legend Construction CONTRACTOR: Legend Construction
WATER DRY PER-
TEST PROCTOR CONT. DEN CENT
NO. LOCATION AND LIFT NUMBER (%) (PCF) COMP
8" Water Line: 1. 50' west of Denton Tap 3rd Lift 1 19.2 107.4 97.0
2. 10' off fire hydrant FG 1 18.9 105.4 95.2
3. 15' off fire hudrant 3rd Lift 1 18.1 107.8 97.3
REMARKS:
Ail tests passed.
Minimum Compaction Required: 95%
Minimum of 4 tests per trip.
FG = Final Grade
PROCTORS:
1. Reddissh Brown Sandy Clay 110.7 PCF @ 16.3% MOISTURE
Jeff Holden
Technician