Loading...
SC-Coppell HS-CS 890921COPPELL PUBLIC WORKS DATE: TO: FROM: RE: September 21, 1989 Larry Davis, Construction Inspector ~ ~ Howard Pafford, Water Utilities Superintendent~ Preliminary Walk Thru Punch List for Coppell High School I assigned a Crewleader of my Division to walk through the above referenced project. Below you will find a list of items that have been found to be deficient. Station N,,mher 1. 16 + 00 2. 13 + 77 3. 11 + 37 4. 11 + 37 5. 11 + 45 6. 11 + 15 7. 15 37 8. 15 + 37 9. 51 + 35 10. 3 + 84.61 11. 6 + 65.63 12. 6 + 73.83 13. 6 + 73.83 14. 3 + 39.94 Description 2" meter box needs lid 2" meter box needs lid 2" meter box needs lid Double Check box is missing Fire Hydrant Valve lid stuck in stack (concrete) Unable to locate main line valve Fire Hydrant leaks Under pressure Unable to locate Fire Hydrant pressure Grout inside of manhole ring Clean out fire hydrant valve stack Clean out mainline valve stack Clean out fire hydrant valve stack Fire hydrant leaning (not level) Unable to locate manhole 15. 4 + 63.87 16. 6 + 46.87 17. 11 + 19.09 18. 13 + 59.09 19. 15 + 67.55 20. 9 + 06 21. 10 + 21.05 Unable to locate manhole 4 x 4 blockout around manhole is cracked. Grout inside ring and clean out invert. Unable to locate manhole Unable to locate manhole Reset ring, grout inside, and outside of ring, then clean out invert. 2" meter not shown on plans- no double check box Unable to locate fire hydrant valve 22. * Paint all valve stack lids Mainline - Blue Fire Hydrant - Red 23. * Mark all valves and manholes on curbs, and (WV) blue for water valve. (MH) red for manhole Please make sure these items are addressed prior to acceptance of this project. If you have any questions regarding this matter, please advise. HLP/bb xc: Steve Goram, Director of Public Works Ted Dutt, Water Utilities Crewleader HIGHSCHL.HLP