Stoneleigh P1-CS 970227 NATHAN D. MAIER
CONSULTING ENGINEERS, INC.
February27,1997
Ms. Jan Sidner
Dallas Area Rapid Transit
1401 Pacific Avenue
Dallas, Texas 75202
RE: ,.Vtoneleigh at Riverchase
NDM $ob No.: 96-10-119
Dear Ms. Sidner:
Attached is a set of Site Development Plans for the above referenced project which abuts DART's Right-
of-Way.
In order to relieve the problem of ponding storm water accumulating in DART's right-of-way adjacent to
our development, we are requesting DART's permission to enter upon the right-of-way, perform minor
grading work and r~g of the ground at the project's completion.
We will also need to install temporary silt fence to control erosion prior to the germination of the new
grass.
Please review our plans and let us know your feelings' concerning our request.
Thank you for your consideration of thin matter.
Sincerely,
NATHAN D. MAIER
Mike Daniel, P.E.
MD/Idb
Ken Griffin
Keller Webster
Todd Shaw
Thrsa NorthPark / 8800 N. Csntral £xpwy. / Suite 300 / Dallas, Taxas 75231 / (214) 739-4741
NATHAN D. MAIER
CONSULTING ENGINEERS, INC.
'~'-uugo4_Hi
F~ 27, 1997
Mr. Kevin Page
Lone Star Gas Company
P. O. Box 306
Lewisville, Texas 75067-0306
Dear Kevin:
,.~toneleigk at Riverchase
NDM,Iob No.: 96-10-119
ARac~ is a set of our civil sim plans for the proposed project. Please review our plans and let us know
of any potential conflicts with your facilities.
Also, the City of Copper has asked that we seek the approval of Lone Star for grading improvements over
your transmission line and its easement that is located north of and parallel to our south property line.
Thank you for your assistance in this matter.
NATHAN D. MAIER
Mike Daniel, P.E.
Ken Griffin
Keller Webster
Todd Shaw
Three NorthPark / 8800 N. Central Expw¥. / Suite 300 / Dallas, Texas 75231 / (214) 739-4741
NATHAN D. MAIER
CONSULTING ENGINEERS, INC.
February 27, 1997
Trinity River Authority
Central Regional Wastewater System
P. O. Box 531196
Grand Prairie, Texas 75053
S~oneleigb at Riverckase
NDM Job No.: 96-10-119
Attached are site development plans for the above referenced project. Note that we are proposing to
construct a parking lot over TRA's easement and sewer line. Also note that we are proposing to lower the
rinl5 of two manholes.
Please be aware that when this site was reclaimed from the flood plain in the mid 1980's, with TRA's
penmssion, we filled over this line with approximately 5 feet o¢fill material and raised these manholes.
Please review our plans and let us know your thoughts about our proposal. Thank you for your
consideration of this matter.
Sincerely,
NATHAN D. MAIER
Mike Daniel, P.E.
Ken Griffin
Keller Webster
Todd Shaw