November 18, 1999
Mr. Kevin C. Young, E.I.T.
Freese and Nichols, Inc.
1701 N. Market, Suite 500, LB 51
Dallas, Texas 75201
Re:
Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Dear Mr. Young:
In accordance with your request for a cost break down regarding the additional cost required to construct the
multiple box culvert in two stages, the following information is provided for your review:
Stage 1
Dirtwork for two lane detour
Culvert for detour
Provide and set CTB w/end protection (300 LF)
HMAC for demur surface (350 TNS)
Remove demur
Striping for demurs
Shoring at box end and between box and road (2180 SF)
Drainage through shoring
Extra handling of dirt (2600 CY)
$20,120.00
$1,000.00
$10,800.00
$26,500.00
$7,000.00
$1,500.00
$54,300.00
$2,180.00
$15,800.00
Stage 2
Dirtwork for detour
Reset CTB w/end protection
Remove CTB w/end protection
HMAC for detour surface (240 TNS)
Remove detour
Additional traffic control
Striping for detours
Labor/Equipment increase for decreased production
$10,500.00
$2,500.00
$3,500.00
$18,800.00
$4,000.00
$12,000.00
$1,500.00
$75,200.00
Total
$267,200.00
If you have any questions regarding this information, don't hesitate to contact our office.
~rely,
/ ~..i.o ,c.~~Company
Robert D. Weber
Project Engineer