ST9801-CS 991118 (2)Project:
Date:
Time:
I.
II.
III.
CITY OF COPPELL, TEXAS
PROGRESS MEETING AGENDA
Coppell Road Paving, Drainage and Water Line Installation
November 18, 1999
9:00 AM
PROJECT ISSUES
A. Utility Conflicts/Relocations (TXU Electric/TXU Gas/Paragon Cable/GTE)
B. Tree Removal and Fence Relocation
C. Waterline Construction
D. Box Culvert Construction
E. Paving Issues
F. Communications with Property Owners/Residents
SCHEDULE ISSUES
A. Traffic Control Plan - Need Acceptable Plan by December 1
B. Work Expected in Next Month?
LIPCOMING CALENDAR EVENTS
A. Next Progress Meeting (Tentative): December 2, 9:00 am
B. Thanksgiving Holidays: November 251h & 261h
..Sent,by: FREESE & NZCHOLS 214~02565 11/29/99 lO. AM Job 816 Page 2/3
F: F~ i= l= ~ l= - NICHOL~
Meetin l Minutes
Project: Coppell Road Improvements
Project #ST98-01
Subject: Cons[ruction Meeting
Recorded by: Kevin Young
Date: November 18, 1999
Location: Cily of Coppell Town Hall
Attendees: Larry Davis, Kent. Collins, .Mike Martin, Roberl Weber, Gary Pryor, Kevin,
Young
The following is our understanding of the subject matter covered during the subject meeting.
If this differs from your understanding, please n. ot~[y us within five worlcing days,
Prqicct Issues:
1. *There ,u'c some utility concerns in ti'ont of the Bn~os Electrical station. There may 1~ one or two
~)lcs that will tm in the way of construction. ~'LI will need to move these prior to commencement
of the paving operations.
2. The waterli ne tie-in at Sandy Lake Road will be easier than anticipated since there is a ! 2" stub
provided across the road. There should be no need to open cut Sandy I,x~c.
3. Ed Bell will have to relocate the t~nce prior to the stump relnoval operations.
4. Thc trees have been removed. A stump count must be done. Thc City, Ed Bell and Freesc&,
Nichols will meet at the site to determine an exact count. This shotfld be reflected in the next
estimate.
5. Any pressure testing of the waterline is encouraged but will not be official until final inspection.
6. A cost b~akdown of the extra cost involved in the two-phased box construction was provided
today. The shoring item would not ~ necess~ I~)r one-way dctom's. The one-way option wou Id
be the cheapest.
7. *The City will need a phasing Plan from Ed Bell by December t~'.
8. Regarding the subgrade p~eparation, the City will have to review the geotcchnical investigation
prior to making a decision.
I;REESE AND NICHOI~R · 1.t41 W. M(~TKINGBIRD LANE, SUITE 230-E · DAI.I..AS, T[:.'.XAS 752,17-.1922
'Tt"2LEI"HONE: 214,920-25(h') · FAX: 214-020-2565 ~, FORM DAT[';: 913197
.sept.by: FREESE & NICHOLS 2149202565 11/29/99 10:22AM Job 816 Page 3/3
Meeting Minute,q
Coppell Road Improvements ST98-01
November 18, 1999
Page 2
9. *Thc contractor has been asked to coordinate with GTE regarding landscaping conflicts on their
site.
I(1. *Pavement marking replacement is needed in the vicinity of the 9()-degree bend.
I !~ ~:I.,arry Davis needs to know what construction, it' any, will occur on Wednesday. I !/24,.
12. Tree stump removal, storm drain, and fence relocations will occur in tt~e ncxl two weeks.
13. The next council meeting is scheduled for December 14th.
14. *The etk~;L/west portion of the roadway ix in Ed Bell's schedule fin' Decen~bcr and should be ready
for excavation. Mr. Davis would like for EB to begin traffic control measures, barricading iill(.t
excavation in mid-December in preparation for paving operations to begin in the first week
January, in this area.
15. * Ihkl Bell will provide staging exhibits to the City. Phase one shoukl covcr I.hc northern (ea..q/wcst)
portion. Pha, e two and three will cover the north/south portion, north-bound and soulh-boLmd.
respectively.
16. *Ed Bell would like to finalize the traffic control plans byThanksgiving. They have asked the City
~o provide box staging desires in the way of one--, or two-way traffic.
17. In advance of work in thc subdivision ',flley, coordination will need to occur R)rclosing of the alley.
! 8. Regarding the tree relocations, Ed Bell would like Io have thern mm'ked as soon as possible, The
City wilt direct them in these efforts.
*Action Items
- ENI) -