Summer Place-CS 860922DI~AL A~ ASSOCIATES ~nc
TO: Randy Fleming
Ginn, Inc. DATE: 9-22-86
16135 Preston Rd., #106 JOB NO' 22-D-86
Dallas, Tx. 75248 REPORT NO: 86-1044
RE: Lime check on material PROJECT- Summer Place
DATE PERFORMED- 9-11-86 LOCATION: Coppe11
GENERAL REPORT
REMARKS: As requested by Randy Fleming with Ginn, Inc. our technician was on
project to perform lime checks on base material under the pavement.
The area in question is towards the west side of the property at the
curve in Alley way A:
A 2" utility line is backfilled in this area. A visual observation
was made in the area which disclosed that a layer of fill material
had been placed on top of the lime treated material at the south end
of the ditch.
Samples of both materials were obtained and returned to ourlaboratory
for Atterburg Limit Tests. Results are recorded on Report #86=1046.
Both materials are below 12 P.I. The sandy clay material does not
appear to be the full length of ditch backfill.
TECHNICIAN: T. Martin
TECHNICIAN TIME: 3 hrs.
MILEAGE: 53 miles
cc: Ned Tankersley-Southwestern Contracting Jim Jenne - Jim Jenne Homes
Mike Cummings-Cumming & Pewitt D. Kight - Director Construction Services
DUVAL ~.~ ASSOCIATES ~.~c
CLIENT' Mr. Randy Fleming DATE: 9-22-86
Ginn, Inc. JOB NO.'22-D-86
16135 Preston R.d, #106
Dallas, Texas 75248 REPORT NO.-86-1044A
SUMMER PLACE
Coppe11, Texas
FIELD DENSITY-REPORT
CONTRACTOR' Southwestern Contracting
REMARKS' As requested by Randy Fleming with Ginn, Inc. , technician was on
project to perform density tests on pavement base materials.
DENSITY TEST RESULTS
DATE TESTED- 9-11-86
MOISTURE CONTENT UNIT DRY WEIGHT PERCENT LBS./CU.FT.
86-1045 SP-1 Alley B-Electric
cut out in street 13.8 14.0 107.2 114.0 94.0
Test as noted indicates slightly low moisture content with adequate compaction-
recommend acceptnace.
TECHNICIAN: T. Martin
TECHNICIAN TIME:
~.Kight
CC: Southwestern Contracting Director Construction Services
Jim Jenne Homes
Cummings & Pewitt