Loading...
ST9601-CS000127 PAVING COMPANY 419 East Highway 80 P.O. Box 270040 Dallas, Texas 75227-0040 Tel (972) 289-0723 Fax (972) 216-5637 Thursday, January 27, 2000 The City of Coppell Via Hand Delivery Attn: Michael A. Martin, P.E. Re: Wrangler Drive In response to your letter dated January 13th, 2000, Tiseo Paving Company believes the letters and meetings that were conducted were sufficient notice to the City in regards to the lost time resulting from utility conflicts. In fact, there was no reply from the City of Coppell on any of our letters regarding the delays we encountered. The only response was a verbal reply stating that it would be discussed after the project was completed. You also state that Cog No. 1.36 was brought up in every project meeting. Neither I or any other member at those meeting recall this being mentioned. In regards to the Critical Path Schedule, your letter states that your requested a schedule a few months past. In fact, this letter is the only letter that mentions a Critical Path Schedule. For all intents and purposes this project was completed July of 1999. Prior to the completion of the project I submitted schedules in January, March and May of 1999. There was no rejection of these schedules nor was there any request for a Critical Path Schedule. As for the GTE conflicts, their conflicts began during Phase I on the North side. During the construction of Phase 1 we had meetings on site with J. Simms about the conflicts in Phase I and II. In fact, we had numerous meetings on site and at City Hall with GTE regarding these conflicts. Most times we did not receive any response from J. Simms and were forced to contact his supervisor. However, his supervisor's only response was to say that he would see xvhat he could do. ~ l~74 It appears that if the City is going to hold the contractor to the Standard Specification than the City needs to follow the specifications as well. For example, "Extra Work" Item 1.37.3 "...the contractor shall do such work, but only when as ordered in writing by the engineer." Tiseo Paving Company submitted a letter regarding the price to adjust existing sanitary sewer manholes. We did not receive a letter from the engineer, but were instructed by Lan'y Davis to proceed with the extra work. Furthermore, the City of Coppell has withheld payment from Tiseo Paving Company in access of the liquidated damages deduction in question for over four months in direct violation of Cog Item 1.52. We feel that it is inappropriate for the City of Coppell to hold Tiseo Paving Company to Cog No. 1.36 for delays well known and thoroughly discussed verbally with the City, when the City of Coppell does not adhere to the North Central Texas Standard Specifications. In regards to the date charged time was to be stopped, it was my understanding on site, that time would be stopped if I wrote a letter stating, "the project is substantially complete and request that time be stopped" per Larry Davis. On July 29th, 1999 I forwarded this letter to the City of Coppell. I was unaware that time was still being charged to this project. In fact, a letter from Mike Jones dated October 26th, 1999 stating that time was stopped August 5th, 1999 and 417 calendar days were charged to the project was the first time I became aware that time had not stopped July 29th, 1999. I believe the City of Coppell failed to inform us of their intent when they charged time beyond July th 19 (the date of the meeting with Larry Davis). Is it the City's intent to penalize contractors without any communication in order to prolong the resolution of the problem? We are still pursuing compensation for the additional days requested in our letter dated November 19th, 1999. (See attached copy). Sincerely, Robert Caudill Project Admn.