Memorandum
To: Larry Davis, City of Coppell
From: Mike Jones
Date: January 26, 2000
Re: Wrangler Ddve Project
I have reviewed the latest Pay Estimate No. 15 from TISEO PAVING, dated 01/21/00 and
offer the following comments:
1. The time charged to date on the estimate does not reflect the ~me charged to the
project according to the Citys records, as per the letter from Mike Marljn to TISEO,
dated 01/13/00. !n that letter, Mike stated that the time charged is 469 days.
2. The percentage completions for Pay Items No, I-12 & I-13 and Pay Items No. 11-23 &11-
24 do not correspond to our calculations. Based upon the areas of perkway restoration
which were deleted from the project scope as a result of new construction and/or
development on adjacent properties, our calculations indicated that the following
percentages should be used for final payment:
Item I-12 Block Sod 80%
Item I-13 Hydromulch 70%
Item 11-23 Block Sod 95%
Item 11-24 Hydromulch 30%
Final payment forthese percentages of completion should be contingent upon
verffication that allareas that required sod and/or hydromulch have uniform grass
coverage (i.e., 100%coverage alive and growing) in a__c,:ordance with the project
spectcations.
Should you have any questions or need any additional information, please give me a call.
TEAGUE NAIL AND PERKINS, INC.
915 Florence Street. Fort Worth, Texas 76102
Ph. (817) 336-5773 Fax (817) 336-2813