ST9601-CS 991208 Memorandum To: Larry Davis, City of Coppell From: Mike Jones Date: December 08, 1999 I~e: Wrangler Drive Project 1. Notice to Proceed was issued on June 1, 1999 stating that contract time would begin on June 8, 1999. 2. Letter from Tiseo on July 29, 1999 requesting time to be stopped as of July 19, 1999. / 3. Final Walk-Thru was conducted on August 5, 1999 at which time contract time for the project was stopped at ~H'f'calendar days. 4. Tiseo's request for no liquidated damages is based upon the following' No'Fcr,'t~',J -----~a. A request for addi io al days for Change Order No. 1 / ~0 %- b. A request fo7r~dditional days for additional storm drain work that was performed to accommodate new development at Enterprise Drive. ~,~ ~, ccr~S ial, fa'~d. A delay of 90 days due to utility conflicts. .~,nS~'~ _._ e. A delay of 14 days to the start of Phase II at the request of the school iwi~,41~,/ ~ distrit ~0 wuv '/'v//CZ,,.(~ 30 days due to a A delay of E- shortage of supplies for the concrete box culvert. Ph. (817) 336-5773 Fax (817) 336-2813 Memorandum To: Larry Davis, City of Coppell From: Mike Jones Date: December 08, 1999 Re: Wrangler Drive Project 1. Notice to Proceed was issued on June 1, 1999 stating that contract time would begin on June 8, 1999. 2. Letter from Tiseo on July 29, 1999 requesting time to be stopped as of July 19, 1999. 3. Final Walk-Thru was conducted on August 5, 1999 at which time contract time for the project was stopped at.4/r7 calendar days. 4. Tiseo's request for no liquidated damages is based upon the following: a. A request for 9 additional days for Change Order No. 1 b. A request for 7 additional days for additional storm drain work that was performed to accommodate new development at Enterprise Drive. c. Unusually severe weather conditions amounting to 50 additional days. d. A delay of 90 days due to utility conflicts. e. A delay of 14 days to the start of Phase II at the request of the school district. f. A delay of 30 days due to a shortage of supplies for the concrete box culvert. TEAGUE NALL AND PERKINS, INC. 915 Florence Street, Fort Worth, Texas 76102 Ph. (817) 336-5773 Fax (817) 336-2813 1